One-Stop Supply of Conventional & Solar Power Equipment · Power Distribution System Design

1 MW Port Crane Power System Cost Breakdown (Q3 2026 China Supplier Pricing)

1 MW Port Crane Power System Cost Breakdown (Q3 2026 China Supplier Pricing) — itemized bill of materials and FOB pricing for a typical configuration.

Last updated: 2026-09-12 · copper-linked items track the daily LME copper price

Estimated total (FOB): $161,139 · 800 kVA transformer

Bill of materials

ItemSpecificationQtyPrice (USD)
HV incoming panel (KYN61-40.5-1250-25)1250 A / 25 kA · vacuum1$4,451
Main transformer (S13-M-800/35)800 kVA · Oil-Immersed · Copper · S131$13,937
LV incoming panel (GGD-1600)1600 A busbar · In 1155 A1$4,549
LV feeder panel (GGD-1600)distributes 4 circuits1$4,549
Main feeder cable (TX→LV) (YJV 0.6/1kV 240 mm² ×3)3× 240 mm² Cu · ΔU 1.56% @ 100 m · $123.0/m3$36,900
Feeder cable — Quay crane 1 (×4) (YJV 120 mm² ×2)2× 120 mm² Cu · 515 A · ΔU 2.1% · $68.8/m8$55,040
Main busbar (Cu) (Cu 80×8)80×8 · 1400 A rating · ref $75.6/mincludedPOA
Grounding electrode (Φ20mm × 2.5m rod)R₁ 39.6 Ω → 13 rod(s) ≤ 4 Ω13$125
Dynamic reactive compensation (SVC/SVG) (±1 Mvar)Static Var Generator · fast response for impact loads · FOB reference1$28,000
Detuned PFC capacitor bank (899 kvar)automatic · 7% detuned · 0.4 kV1$10,800
Series detuning reactor (7%) (62.9 kvar)189 Hz tuning · below 5th harmonic1$2,788
Quay crane regenerative drive (500 kW four-quadrant)regenerative VFD (energy feedback on lowering) · per crane2POA
Shore power supply (岸电) (150 kVA)50/60 Hz frequency converter + shore connection panel · IEC/ISO 80005-1 · quoted per project1POA

Single-line diagram

CTCT 30/5APTPT 35kV/100V50/5151NHV incomingKYN61-40.5-1250-251250 A / 25 kA - vacuumS13-M-800/35800 kVAZ = 4%Oil-Immersed - Copper - S13kWhmeteringLV incomingGGD-16000.4 kV LV busbar80x8 Cu - 1400 ASPDLV feeder panel x1 - 4 circuitsQuay crane 1 - 515 AYJV 120 mm2Quay crane 2 - 515 AYJV 120 mm2LV feeder circuit 3 - 515 AYJV 120 mm2LV feeder circuit 4 - 515 AYJV 120 mm2Grounding 13xdia20mmx2.5m rod
LEGENDBreaker (52)DisconnectorCTCT (current transformer)PTPT (voltage transformer)50/51Protection relay 50/51/51N/87kWhMeter (kWh)SPD (surge protection)Transformer

How it was calculated

What drives the cost

  • Equipment — the transformer/switchgear/inverter is the largest single line item.
  • Storage (where applicable) — batteries are the biggest swing factor.
  • Copper & freight — copper-linked cabling and freight shift landed cost ±5–10%.

Frequently asked questions

How do impact loads affect power quality at a port?
Quay cranes and winches impose rapid, large load swings (impact loads) that cause voltage flicker. The impact factor is the ratio of peak to average load, often 1.3-1.5. When flicker violates GB/T 12326 limits, a dynamic reactive compensator (SVC or SVG) with 5-20 ms response is added. The calculator sizes compensation from the impact factor.
Why do arc furnaces need SVC or SVG compensation?
Electric arc furnaces draw erratic current with severe flicker and harmonics, pulling power factor down to 0.6-0.7 during meltdown. An SVC or SVG rated 30-50% of furnace capacity restores power factor and damps flicker to meet GB/T 12326 and IEEE 519. A 50 MW furnace typically needs 15-25 Mvar of dynamic compensation.
What voltage level feeds a port crane system?
Large quay cranes (500 kW-1.5 MW per crane) are fed at 10 kV or 35 kV, stepped down near the berth to 0.4/0.69 kV for drives. A 10 kV ring feed with RMU or switchgear along the quay is standard. The calculator's 35 kV default models a multi-berth crane cluster; smaller ports use 10 kV.
How are crane harmonics controlled?
Crane drives are VFD-based, injecting 5th, 7th, 11th harmonics; THDi commonly reaches 30% without treatment. Active front-end (AFE) drives or a passive detuned filter plus an APF keep THD under the IEEE 519 limit of 5-8% at the point of common coupling. The calculator sizes harmonic filtering when THDi exceeds the threshold.
What is the typical crane duty cycle for sizing supply?
Quay cranes run intermittent duty (hoist/lower/travel), so average demand is 40-60% of installed power even during busy periods. Supply transformers are sized to the peak simultaneous demand plus starting inrush of the largest hoist, not the sum of nameplates. The calculator applies an impact factor and diversity to avoid oversizing.
What short-circuit duty must port switchgear withstand?
Port 35 kV switchgear is usually rated 25-31.5 kA; 10 kV panels 25-31.5 kA; LV boards 50-65 kA. The rating must exceed the computed fault current at each busbar (IEC 60909). Crane drives contribute fault current, so a 35 kV bus fed by a 50 MVA source needs at least 25 kA. The calculator checks panel ratings against the fault level.

Size your own configuration

Run the calculator for your exact load and get a full BOM + FOB price.

Open calculator Request a Quote

Related