1MW 数据中心供电系统(2026年第三季度中国供应商价格)
1 MW Data Center Power System Cost Breakdown (Q3 2026 China Supplier Pricing) — itemized bill of materials and FOB pricing for a typical configuration.
Estimated total (FOB): $557,962 · 1600 kVA transformer
Bill of materials
| Item | Specification | Qty | Price (USD) |
|---|---|---|---|
| HV incoming panel (KYN28A-12-630-315) | 630 A / 31.5 kA · vacuum | 2 | $4,896 |
| HV bus-tie panel (KYN28A-12-630-315) | 630 A / 31.5 kA · vacuum | 1 | $2,448 |
| Main transformer (each) (SCB13-1600/10) | 1600 kVA · Dry-Type · Copper · SCB13 | 2 | $53,534 |
| LV incoming panel (GGD-2500) | 2500 A busbar · In 2309 A | 2 | $12,310 |
| LV bus-tie panel (GGD-2500) | 2500 A busbar | 1 | $6,155 |
| LV feeder panel (×2) (GGD-2500) | distributes 8 circuits | 2 | $12,310 |
| Cable branch box (LV) (DFW-0.4) | 1-in / 4-out · 0.4 kV · 630 A | 1 | $630 |
| Main feeder cable (TX→LV) (YJV 0.6/1kV 300 mm² ×5) | 5× 300 mm² Cu · ΔU 0.90% @ 60 m · $154.0/m | 5 | $46,200 |
| Feeder cable — IT feeder 1 (×8) (YJV 185 mm²) | 185 mm² Cu · 319 A · ΔU 1.0% · $103.0/m | 8 | $49,440 |
| Branch trunk cable (LV → branch box 1) (YJV 300 mm² ×3) | 3× 300 mm² Cu · 1276 A · ΔU 0.8% · $154.0/m | 3 | $27,720 |
| Main busbar (Cu) (Cu 125×10) | 125×10 · 2500 A rating · ref $147.8/m | included | POA |
| Grounding electrode (Φ20mm × 2.5m rod) | R₁ 39.6 Ω → 13 rod(s) ≤ 4 Ω | 13 | $125 |
| Online double-conversion UPS module (1/2) (1250 kVA / 1125 kW) | 0.9 output PF · 92% efficiency · 10 min battery (181 kWh total) | 1 | $162,500 |
| Online double-conversion UPS module (2/2) (1250 kVA / 1125 kW) | 0.9 output PF · 92% efficiency · 10 min battery (181 kWh total) | 1 | $162,500 |
| UPS battery bank (VRLA / LiFePO4) (181 kWh) | battery autonomy 10 min @ full IT load · $95/kWh | 1 | $17,195 |
| DCIM / monitoring system (DCIM platform) | power & environmental monitoring, metering, alarms (POA — not included in estimate) | 1 | POA |
| Rack PDU (end-of-row / column head cabinet) (rack PDU) | per-rack power distribution + branch metering (POA — not included in estimate) | 13 | POA |
Single-line diagram
How it was calculated
- IT load = 1,000 kW (≈ 125 racks @ 8 kW/rack)
- Cooling + auxiliary = 600 kW (cooling 60%) + 80 kW (aux 8%)
- Total facility load P = 1,680 kW → PUE = P ÷ IT = 1.68
- UPS capacity = IT ÷ (PF × η) = 1,000 ÷ (0.95 × 0.92) = 1,144 kVA → 1250 kVA module
- UPS battery = 1,000 kW × 10 min ÷ 60 ÷ 0.92 = 181 kWh autonomy
- Tier Tier III requires N+1 minimum; selected 2N → 2 UPS module(s) · 2 path(s)
- Loads: P=1,680 kW, PF 0.95, 8 circuits
- Demand: 1,680 × 0.9 = 1,512 kW
- PFC: Qc = 1,512 × (0.329 − 0.329) = 0 kVAR → 0 kVAR bank
- Transformer: S = 1,512 ÷ 0.95 = 1591.6 kVA → 1,600 kVA standard
- Loading: 1,592 ÷ 1,600 = 99% (high — consider next size)
- Voltage regulation: 99% × 6% × sinφ ≈ 1.9% at full load
成本敏感因素
- 设备 — 变压器/开关柜/逆变器是最大单项。
- 储能 — 电池是最大变量。
- 铜价与运费 — 铜价联动线缆与运费使到岸成本 ±5–10% 波动。
常见问题
数据中心供电的 N+1 和 2N 冗余有什么区别?
N+1 是在最小配置外多加一个备用模块(如需要 3 台 UPS 时配 4 台),能承受单点故障。2N 是把整条供电路径复制成两路独立电源、各自能带满负荷,任何单点故障都不影响运行。2N 投资约为翻倍,N+1 增加约 25-35%。Tier III 常对应 N+1,Tier IV 对应 2N。
如何按 IT 负载选数据中心 UPS 容量?
以 IT 负载 kW 为起点,加冷却与机械负载(典型为 IT 负载的 50-70%),留 20-30% 扩容裕量,再按 0.9-0.95 功率因数折算 kVA。1000 kW IT + 60% 冷却 ≈ 1600 kW,约 1700-1780 kVA,故选 2000 kVA UPS。计算器按此流程并匹配标准 UPS 容量。
现代数据中心的 PUE 应做到多少?
PUE = 总设施功率 ÷ IT 功率。传统机房 1.6-1.8,现代风冷数据中心 1.3-1.4,带自然冷却的超大规模可到 1.1-1.2。PUE 每降 0.1,非 IT 能耗约降 10%。TIA-942 与 Uptime Institute 都将 PUE 作为关键效率指标;计算器输出设施/IT 负荷拆分。
数据中心的标准电压架构是怎样的?
典型架构:10 kV(或 35 kV)市电 → 中压开关柜 → 变压器降到 0.4 kV → UPS → PDU → 机柜。大中型机房用 10/0.4 kV 双中压进线 + 2N 或 N+1 拓扑。机柜密度 8-12 kW 为标准,高密度 AI 机柜达 30-100 kW,可能改用 48 V 直流或液冷。
UPS 电池应提供多长备电时间?
备电时间按桥接至柴发启动来定,典型 5-15 分钟(计算器默认 10 分钟)。柴发 30-60 秒即可带满负荷,更长电池只增加成本。无柴发的站点备电延长到 30-60 分钟以便有序关机。计算器按所选备电时间与放电深度计算电池组。
1000 kW 数据中心典型需要多大变压器?
IT 负载 1000 kW + 60% 冷却 + UPS 损耗与裕量后,总需量达 1800-2000 kW,0.95 功率因数下约 1900-2100 kVA,故 N+1 选两台 1250 kVA(2N 选 2×2000 kVA)。中低压变压器多用干式浇注 SCB13/SCB14、F 级绝缘以利消防。