One-Stop Supply of Conventional & Solar Power Equipment · Power Distribution System Design

200 MW PV Grid Interconnection Cost Breakdown (Q3 2026 China Supplier Pricing)

200 MW PV Grid Interconnection Cost Breakdown (Q3 2026 China Supplier Pricing) — itemized bill of materials and FOB pricing for a typical configuration.

Last updated: 2026-09-12 · copper-linked items track the daily LME copper price

Estimated total (FOB): $51,067,153

Bill of materials

ItemSpecificationQtyPrice (USD)
PV Modules (550 Wp Mono PERC)550 Wp · 418182 pcs (DC/AC ≈ 1.15)418182$25,300,011
Central Inverter (2.5 MW string/central)utility-scale · 200.0 MW AC80$7,000,000
Ground Mounting Structure (Fixed tilt)tilt optimized for lat 30°1$16,000,000
Box-Type Substation (step-up) (0.8/35 kV)1600 kVA step-up160$2,704,000
HV Switchgear (collector) (KYN61-40.5)collector switchgear · 27 feeders27$60,102
Main Transformer (step-up) (SZ11-232MVA/110kV)232 MVA 35/110 kV · YNd11 · OLTC1POA
SVG (Static Var Generator) (SVG-50Mvar/110kV)dynamic reactive compensation1POA
Shunt Reactor (5 Mvar)absorb collector cable charging1POA
Collector Cable (YJV 26/35 kV)95 mm² · radial feeders · 27 feeders27POA
Earthing System (flat bar + rods)plant grounding grid1$1,040
SCADA Monitoring (plant-level)power plant controller + SCADA1$2,000

Single-line diagram

POI (Point of Interconnection)Utility GridCTCT110 kV POI breaker50/5151NkWhmeteringMain transformer232 MVA 35/110 kVSZ11 - YNd11OLTC - ONAN/ONAFSVG 50 MvarShunt reactor 5 Mvar35 kV collector busPTPTSPDCollector feeder 1YJV 35 kV (radial)Collector feeder 2YJV 35 kV (radial)Collector feeder 3YJV 35 kV (radial)Collector feeder 4YJV 35 kV (radial)Collector feeder 5YJV 35 kV (radial)Collector feeder 6YJV 35 kV (radial)Collector feeder 7YJV 35 kV (radial)Collector feeder 8YJV 35 kV (radial)Collector feeder 9YJV 35 kV (radial)Collector feeder 10YJV 35 kV (radial)Collector feeder 11YJV 35 kV (radial)Collector feeder 12YJV 35 kV (radial)Collector feeder 13YJV 35 kV (radial)Collector feeder 14YJV 35 kV (radial)Collector feeder 15YJV 35 kV (radial)Collector feeder 16YJV 35 kV (radial)Collector feeder 17YJV 35 kV (radial)Collector feeder 18YJV 35 kV (radial)Collector feeder 19YJV 35 kV (radial)Collector feeder 20YJV 35 kV (radial)Collector feeder 21YJV 35 kV (radial)Collector feeder 22YJV 35 kV (radial)Collector feeder 23YJV 35 kV (radial)Collector feeder 24YJV 35 kV (radial)Collector feeder 25YJV 35 kV (radial)Collector feeder 26YJV 35 kV (radial)Collector feeder 27YJV 35 kV (radial)Box sub1600 kVABox sub1600 kVABox sub1600 kVABox sub1600 kVABox sub1600 kVABox sub1600 kVA + 154 more box substations (160 arrays total)PV array + string inverter0.8 kV DC/AC
LEGENDBreaker (52)CTCT (current transformer)PTPT (voltage transformer)50/51Protection relay 50/51/51NkWhMeter (kWh)SPD (surge protection)

How it was calculated

What drives the cost

  • Equipment — the transformer/switchgear/inverter is the largest single line item.
  • Storage (where applicable) — batteries are the biggest swing factor.
  • Copper & freight — copper-linked cabling and freight shift landed cost ±5–10%.

Frequently asked questions

At what voltage should a PV plant connect to the grid?
Connection voltage follows plant size: under ~250 kW use 0.4 kV, 250 kW-6 MW use 10 kV, and above 6 MW use 35 kV or 110 kV. A 50 MW plant typically connects at 110 kV. The choice balances transformer losses against interconnection cost; grid operators specify the exact point of connection. The calculator selects voltage and main-transformer rating automatically.
How much reactive compensation does a PV plant need?
Grid codes (GB/T 19964, IEEE 1547) require PV inverters to operate within a 0.95 leading to 0.95 lagging power-factor range and often to supply reactive support during faults. Large plants usually add a centralized SVG/SVC of 10-30% of plant capacity. A 50 MW plant commonly pairs a 10-15 Mvar dynamic compensator to meet grid-code voltage support.
What short-circuit contribution does a PV inverter add?
A grid-following PV inverter contributes roughly 1.0-1.2 times its rated current for a few cycles, far less than a synchronous generator (5-7 times rated). For a 50 MW plant the contribution is ~60-70 MVA. This matters when checking breaker and transformer fault ratings; the calculator folds PV short-circuit contribution into the interconnection study.
What is the typical collector system voltage in a PV plant?
Large PV plants gather strings through 800 V DC to central or string inverters, then step up through a 0.8 kV to 10 kV or 35 kV collector network. String inverters (up to 250 kW) feed a 10 kV collector; central inverters (500 kW-3 MW) feed 35 kV. Collector cable runs are typically 5-20 km, sized for under 2% voltage drop.
How is the main transformer sized for a PV plant?
The main transformer rating matches inverter AC capacity divided by power factor, with 5-10% margin and the next standard size (IEC 60076). A 50 MWac plant with 0.95 pf needs roughly 55 MVA, so select 63 MVA. Most PV main transformers are oil-immersed, ONAN, 35/110 kV, with a no-load loss limit set by GB/T 6451 efficiency grades.
What grid-code compliance checks does interconnection require?
Key checks per GB/T 19963/19964 and IEEE 1547 include: low/high-voltage ride-through, frequency ride-through (typically 47.5-51.5 Hz), power-factor capability, ramp-rate limits, and anti-islanding. The calculator verifies voltage-level fit, main-transformer sizing, reactive compensation and fault contribution, flagging parameters that fall outside the typical grid-code envelope.

Size your own configuration

Run the calculator for your exact load and get a full BOM + FOB price.

Open calculator Request a Quote

Related