One-Stop Supply of Conventional & Solar Power Equipment · Power Distribution System Design

5 MW PV Grid Interconnection Cost Breakdown (Q3 2026 China Supplier Pricing)

5 MW PV Grid Interconnection Cost Breakdown (Q3 2026 China Supplier Pricing) — itemized bill of materials and FOB pricing for a typical configuration.

Last updated: 2026-09-12 · copper-linked items track the daily LME copper price

Estimated total (FOB): $1,607,744

Bill of materials

ItemSpecificationQtyPrice (USD)
PV Modules (550 Wp Mono PERC)550 Wp · 10455 pcs (DC/AC ≈ 1.15)10455$632,528
Central Inverter (2.5 MW string/central)utility-scale · 5.0 MW AC2$500,000
Ground Mounting Structure (Fixed tilt)tilt optimized for lat 30°1$400,000
Box-Type Substation (step-up) (0.8/10 kV)1600 kVA step-up4$67,600
HV Switchgear (collector) (KYN28A-12)collector switchgear · 1 feeders1$2,226
Ring Main Unit (XGN15-12)SF6 · 630 A · 4-way1$2,350
SVG (Static Var Generator) (SVG-1Mvar/10kV)dynamic reactive compensation1POA
Collector Cable (YJV 26/10 kV)240 mm² · radial feeders · 1 feeders1POA
Earthing System (flat bar + rods)plant grounding grid1$1,040
SCADA Monitoring (plant-level)power plant controller + SCADA1$2,000

Single-line diagram

POI (Point of Interconnection)Utility GridCTCT10 kV POI breaker50/5151NkWhmetering10 kV collector busPTPTSPDCollector feeder 1YJV 10 kV (radial)Box sub1600 kVABox sub1600 kVABox sub1600 kVABox sub1600 kVAPV array + string inverter0.8 kV DC/AC
LEGENDBreaker (52)CTCT (current transformer)PTPT (voltage transformer)50/51Protection relay 50/51/51NkWhMeter (kWh)SPD (surge protection)

How it was calculated

What drives the cost

  • Equipment — the transformer/switchgear/inverter is the largest single line item.
  • Storage (where applicable) — batteries are the biggest swing factor.
  • Copper & freight — copper-linked cabling and freight shift landed cost ±5–10%.

Frequently asked questions

At what voltage should a PV plant connect to the grid?
Connection voltage follows plant size: under ~250 kW use 0.4 kV, 250 kW-6 MW use 10 kV, and above 6 MW use 35 kV or 110 kV. A 50 MW plant typically connects at 110 kV. The choice balances transformer losses against interconnection cost; grid operators specify the exact point of connection. The calculator selects voltage and main-transformer rating automatically.
How much reactive compensation does a PV plant need?
Grid codes (GB/T 19964, IEEE 1547) require PV inverters to operate within a 0.95 leading to 0.95 lagging power-factor range and often to supply reactive support during faults. Large plants usually add a centralized SVG/SVC of 10-30% of plant capacity. A 50 MW plant commonly pairs a 10-15 Mvar dynamic compensator to meet grid-code voltage support.
What short-circuit contribution does a PV inverter add?
A grid-following PV inverter contributes roughly 1.0-1.2 times its rated current for a few cycles, far less than a synchronous generator (5-7 times rated). For a 50 MW plant the contribution is ~60-70 MVA. This matters when checking breaker and transformer fault ratings; the calculator folds PV short-circuit contribution into the interconnection study.
What is the typical collector system voltage in a PV plant?
Large PV plants gather strings through 800 V DC to central or string inverters, then step up through a 0.8 kV to 10 kV or 35 kV collector network. String inverters (up to 250 kW) feed a 10 kV collector; central inverters (500 kW-3 MW) feed 35 kV. Collector cable runs are typically 5-20 km, sized for under 2% voltage drop.
How is the main transformer sized for a PV plant?
The main transformer rating matches inverter AC capacity divided by power factor, with 5-10% margin and the next standard size (IEC 60076). A 50 MWac plant with 0.95 pf needs roughly 55 MVA, so select 63 MVA. Most PV main transformers are oil-immersed, ONAN, 35/110 kV, with a no-load loss limit set by GB/T 6451 efficiency grades.
What grid-code compliance checks does interconnection require?
Key checks per GB/T 19963/19964 and IEEE 1547 include: low/high-voltage ride-through, frequency ride-through (typically 47.5-51.5 Hz), power-factor capability, ramp-rate limits, and anti-islanding. The calculator verifies voltage-level fit, main-transformer sizing, reactive compensation and fault contribution, flagging parameters that fall outside the typical grid-code envelope.

Size your own configuration

Run the calculator for your exact load and get a full BOM + FOB price.

Open calculator Request a Quote

Related