One-Stop Supply of Conventional & Solar Power Equipment · Power Distribution System Design

2 MW Petrochemical Power System Cost Breakdown (Q3 2026 China Supplier Pricing)

2 MW Petrochemical Power System Cost Breakdown (Q3 2026 China Supplier Pricing) — itemized bill of materials and FOB pricing for a typical configuration.

Last updated: 2026-09-12 · copper-linked items track the daily LME copper price

Estimated total (FOB): $382,021 · 2000 kVA transformer

Bill of materials

ItemSpecificationQtyPrice (USD)
HV incoming panel (KYN28A-12-630-315)630 A / 31.5 kA · vacuum2$4,896
HV bus-tie panel (KYN28A-12-630-315)630 A / 31.5 kA · vacuum1$2,448
Main transformer (each) (S13-M-2000/10)2000 kVA · Oil-Immersed · Copper · S132$44,662
LV incoming panel (GGD-3150)3150 A busbar · In 2887 A2$14,450
LV bus-tie panel (GGD-3150)3150 A busbar1$7,225
LV feeder panel (×2) (GGD-3150)distributes 10 circuits2$14,450
Cable branch box (LV) (DFW-0.4)1-in / 4-out · 0.4 kV · 630 A2$1,260
Busway trunking (LV main feeder) (Busway 4000 A)4000 A · Cu/Al busway · 80 m · $1329/m1$106,320
Feeder cable — Process feeder 1 (×10) (YJV 150 mm²)150 mm² Cu · 304 A · ΔU 1.6% · $86.0/m10$68,800
Branch trunk cable (LV → branch box 1) (YJV 240 mm² ×3)3× 240 mm² Cu · 1215 A · ΔU 1.3% · $123.0/m3$29,520
Branch trunk cable (LV → branch box 2) (YJV 150 mm² ×2)2× 150 mm² Cu · 608 A · ΔU 1.6% · $86.0/m2$13,760
Main busbar (Cu) (Cu 125×10)125×10 · 2500 A rating · ref $147.8/mincludedPOA
Grounding electrode (Φ20mm × 2.5m rod)R₁ 39.6 Ω → 13 rod(s) ≤ 4 Ω13$125
Detuned PFC capacitor bank (221 kvar)automatic · 7% detuned · 0.4 kV1$3,300
Series detuning reactor (7%) (15.5 kvar)189 Hz tuning · below 5th harmonic1$804
Explosion-proof (Ex) distribution board (Ex d Zone 2)Flameproof enclosure · IEC 60079 · quoted per project (POA — not included in estimate)1POA
Ex-rated motor control center (MCC) (Ex d Zone 2)Ex motor starters + VFD for pumps/compressors · IEC 60079 (POA — not included in estimate)1POA
Emergency / standby diesel generator (1000 kVA)life-safety / standby power · 600 kVA required1$70,000

Single-line diagram

CTCT50/5150/5187differentialFeed AFeed BKYN28A-12-630-315KYN28A-12-630-315HV bus-tieS13-M-2000/102000 kVA - Z=4%S13-M-2000/102000 kVA - Z=4%LV bus-tie0.4 kV0.4 kVProcess feeder 1 - 304 AYJV 150 mm2Process feeder 2 - 304 AYJV 150 mm2Process feeder 3 - 304 AYJV 150 mm2Process feeder 4 - 304 AYJV 150 mm2Process feeder 5 - 304 AYJV 150 mm2Process feeder 6 - 304 AYJV 150 mm2Process feeder 7 - 304 AYJV 150 mm2Process feeder 8 - 304 AYJV 150 mm2Process feeder 9 - 304 AYJV 150 mm2Process feeder 10 - 304 AYJV 150 mm2Grounding 13xdia20mmx2.5m rod
LEGENDBreaker (52)DisconnectorCTCT (current transformer)PTPT (voltage transformer)50/51Protection relay 50/51/51N/87kWhMeter (kWh)SPD (surge protection)Transformer

How it was calculated

What drives the cost

  • Equipment — the transformer/switchgear/inverter is the largest single line item.
  • Storage (where applicable) — batteries are the biggest swing factor.
  • Copper & freight — copper-linked cabling and freight shift landed cost ±5–10%.

Frequently asked questions

What does Ex-proof / explosion-proof zoning mean for electrical equipment?
Hazardous areas are zoned by the likelihood of explosive gas (Zone 0/1/2 per IEC 60079) or dust (Zone 20/21/22). Electrical equipment in Zone 1/2 must carry Ex certification (e.g. Ex d, Ex e, Ex n) matched to the gas group and temperature class. Choosing the right Ex rating adds 20-50% to switchgear cost; the calculator lets you select the zone and flags Ex-rated BOM.
Why do petrochemical plants need dual power supply?
Continuous process plants (refineries, ethylene, ammonia) cannot tolerate supply loss — a restart can take days and cost millions. They use dual independent feeds with automatic transfer (ATS) and N+1 or 2N redundancy for critical loads per GB 50052 load classification. The calculator models redundancy level and sizes the emergency/standby path accordingly.
How are rectifier harmonics managed in petrochemical plants?
Electrolyser and plating rectifiers inject 5th, 7th, 11th harmonics. If total harmonic distortion exceeds IEEE 519 limits (5% THD at the PCC for most systems), a detuned capacitor bank (7% series reactor) or an active harmonic filter (APF) is added. The calculator sizes compensation with a 7% detuning factor when THDi exceeds ~15-20%.
What transformer impedance is typical for petrochemical MV/LV units?
Distribution transformers in petrochemical plants usually have 6% impedance (uk) for LV networks, sometimes 8% for large motors to limit fault current. Higher impedance reduces short-circuit current but raises voltage regulation; 6% balances both for a 10/0.4 kV, 1000-2500 kVA unit. The calculator applies standard uk values when computing fault levels.
What load classification does GB 50052 define for continuous processes?
GB 50052 classifies loads into first, second and third class. Continuous petrochemical process units are first-class loads requiring two independent supplies; critical safety loads (emergency shutdown, fire pumps) are 'first-class important' loads needing an additional emergency source such as a diesel generator or EPS. The calculator's redundancy and emergency-power options map to these classes.
How is the process load demand factor set for a refinery?
Refinery process loads run near-continuously, so demand factor is high at 0.8-0.9 for main units, while utility and auxiliaries run 0.6-0.7. A 2000 kW connected process load with 0.85 demand and 0.95 pf needs about 1790 kVA, so select a 2000 kVA transformer. The calculator uses these factors to avoid both oversizing and undersizing.

Size your own configuration

Run the calculator for your exact load and get a full BOM + FOB price.

Open calculator Request a Quote

Related