One-Stop Supply of Conventional & Solar Power Equipment · Power Distribution System Design

2MW 石化供电系统(2026年第三季度中国供应商价格)

2 MW Petrochemical Power System Cost Breakdown (Q3 2026 China Supplier Pricing) — itemized bill of materials and FOB pricing for a typical configuration.

Last updated: 2026-09-12 · copper-linked items track the daily LME copper price

Estimated total (FOB): $382,021 · 2000 kVA transformer

Bill of materials

ItemSpecificationQtyPrice (USD)
HV incoming panel (KYN28A-12-630-315)630 A / 31.5 kA · vacuum2$4,896
HV bus-tie panel (KYN28A-12-630-315)630 A / 31.5 kA · vacuum1$2,448
Main transformer (each) (S13-M-2000/10)2000 kVA · Oil-Immersed · Copper · S132$44,662
LV incoming panel (GGD-3150)3150 A busbar · In 2887 A2$14,450
LV bus-tie panel (GGD-3150)3150 A busbar1$7,225
LV feeder panel (×2) (GGD-3150)distributes 10 circuits2$14,450
Cable branch box (LV) (DFW-0.4)1-in / 4-out · 0.4 kV · 630 A2$1,260
Busway trunking (LV main feeder) (Busway 4000 A)4000 A · Cu/Al busway · 80 m · $1329/m1$106,320
Feeder cable — Process feeder 1 (×10) (YJV 150 mm²)150 mm² Cu · 304 A · ΔU 1.6% · $86.0/m10$68,800
Branch trunk cable (LV → branch box 1) (YJV 240 mm² ×3)3× 240 mm² Cu · 1215 A · ΔU 1.3% · $123.0/m3$29,520
Branch trunk cable (LV → branch box 2) (YJV 150 mm² ×2)2× 150 mm² Cu · 608 A · ΔU 1.6% · $86.0/m2$13,760
Main busbar (Cu) (Cu 125×10)125×10 · 2500 A rating · ref $147.8/mincludedPOA
Grounding electrode (Φ20mm × 2.5m rod)R₁ 39.6 Ω → 13 rod(s) ≤ 4 Ω13$125
Detuned PFC capacitor bank (221 kvar)automatic · 7% detuned · 0.4 kV1$3,300
Series detuning reactor (7%) (15.5 kvar)189 Hz tuning · below 5th harmonic1$804
Explosion-proof (Ex) distribution board (Ex d Zone 2)Flameproof enclosure · IEC 60079 · quoted per project (POA — not included in estimate)1POA
Ex-rated motor control center (MCC) (Ex d Zone 2)Ex motor starters + VFD for pumps/compressors · IEC 60079 (POA — not included in estimate)1POA
Emergency / standby diesel generator (1000 kVA)life-safety / standby power · 600 kVA required1$70,000

Single-line diagram

CTCT50/5150/5187differentialFeed AFeed BKYN28A-12-630-315KYN28A-12-630-315HV bus-tieS13-M-2000/102000 kVA - Z=4%S13-M-2000/102000 kVA - Z=4%LV bus-tie0.4 kV0.4 kVProcess feeder 1 - 304 AYJV 150 mm2Process feeder 2 - 304 AYJV 150 mm2Process feeder 3 - 304 AYJV 150 mm2Process feeder 4 - 304 AYJV 150 mm2Process feeder 5 - 304 AYJV 150 mm2Process feeder 6 - 304 AYJV 150 mm2Process feeder 7 - 304 AYJV 150 mm2Process feeder 8 - 304 AYJV 150 mm2Process feeder 9 - 304 AYJV 150 mm2Process feeder 10 - 304 AYJV 150 mm2Grounding 13xdia20mmx2.5m rod
LEGENDBreaker (52)DisconnectorCTCT (current transformer)PTPT (voltage transformer)50/51Protection relay 50/51/51N/87kWhMeter (kWh)SPD (surge protection)Transformer

How it was calculated

成本敏感因素

  • 设备 — 变压器/开关柜/逆变器是最大单项。
  • 储能 — 电池是最大变量。
  • 铜价与运费 — 铜价联动线缆与运费使到岸成本 ±5–10% 波动。

常见问题

防爆(Ex)区域划分对电气设备意味着什么?
危险区按爆炸性气体(IEC 60079 的 Zone 0/1/2)或粉尘(Zone 20/21/22)出现的概率划分。Zone 1/2 内的电气设备须有与气体组别和温度等级匹配的 Ex 认证(如 Ex d、Ex e、Ex n)。正确选 Ex 等级会使开关柜成本增加 20-50%;计算器可选分区并标注 Ex 型 BOM。
石化厂为什么需要双电源供电?
连续流程装置(炼油、乙烯、合成氨)不能承受失电——重新开车可能需数天并损失数百万。按 GB 50052 负荷分级,关键负荷采用双路独立电源 + 自动转换(ATS)和 N+1 或 2N 冗余。计算器可设冗余等级并据此配置应急/备用回路。
石化厂的整流装置谐波如何处理?
电解和电镀整流器注入 5、7、11 次谐波。若公共连接点总谐波畸变超过 IEEE 519 限值(多数系统为 5% THD),需加装去谐电容器组(7% 串联电抗)或有源滤波器(APF)。计算器在 THDi 超过约 15-20% 时按 7% 去谐系数配置补偿。
石化中低压变压器典型阻抗是多少?
石化厂配电变压器阻抗通常 6%(uk),大型电机回路有时用 8% 以限制短路电流。阻抗越高短路电流越小但电压调整率越差,6% 对 10/0.4 kV、1000-2500 kVA 单元可兼顾两者。计算器计算故障水平时采用标准 uk 值。
GB 50052 对连续生产负荷如何分级?
GB 50052 将负荷分为一、二、三级。连续石化装置属一级负荷,需两路独立电源;关键安全负荷(紧急停车、消防泵)属『一级重要负荷』,还需柴发或 EPS 等应急电源。计算器的冗余与应急电源选项即对应这些分级。
炼厂工艺负荷的需用系数怎么定?
炼厂工艺负荷近乎连续运行,主装置需用系数高达 0.8-0.9,公用与辅助系统 0.6-0.7。2000 kW 装机工艺负荷、0.85 需用系数、0.95 功率因数约需 1790 kVA,取 2000 kVA 变压器。计算器用这些系数避免超配与欠配。

计算你自己的配置

输入你的实际负荷,获得完整 BOM 与 FOB 报价。

Open calculator Request a Quote