500kW 学校供电系统(2026年第三季度中国供应商价格)
500 kW School Power System Cost Breakdown (Q3 2026 China Supplier Pricing) — itemized bill of materials and FOB pricing for a typical configuration.
Estimated total (FOB): $77,782 · 500 kVA transformer
Bill of materials
| Item | Specification | Qty | Price (USD) |
|---|---|---|---|
| HV incoming panel (KYN28A-12-630-315) | 630 A / 31.5 kA · vacuum | 2 | $4,896 |
| HV bus-tie panel (KYN28A-12-630-315) | 630 A / 31.5 kA · vacuum | 1 | $2,448 |
| Main transformer (each) (SCB13-500/10) | 500 kVA · Dry-Type · Copper · SCB13 | 2 | $21,861 |
| LV incoming panel (GGD-1000) | 1000 A busbar · In 722 A | 2 | $6,958 |
| LV bus-tie panel (GGD-1000) | 1000 A busbar | 1 | $3,479 |
| LV feeder panel (×2) (GGD-1000) | distributes 8 circuits | 2 | $6,958 |
| Cable branch box (LV) (DFW-0.4) | 1-in / 4-out · 0.4 kV · 630 A | 1 | $630 |
| Main feeder cable (TX→LV) (YJV 0.6/1kV 240 mm² ×2) | 2× 240 mm² Cu · ΔU 0.88% @ 60 m · $123.0/m | 2 | $14,760 |
| Feeder cable — Classroom 1 (×8) (YJV 16 mm²) | 16 mm² Cu · 76 A · ΔU 2.8% · $8.1/m | 8 | $3,888 |
| Branch trunk cable (LV → branch box 1) (YJV 150 mm²) | 150 mm² Cu · 304 A · ΔU 1.2% · $86.0/m | 1 | $5,160 |
| Main busbar (Cu) (Cu 63×6.3) | 63×6.3 · 900 A rating · ref $47/m | included | POA |
| Grounding electrode (Φ20mm × 2.5m rod) | R₁ 39.6 Ω → 13 rod(s) ≤ 4 Ω | 13 | $125 |
| Automatic transfer switch (ATS) (ATS 200 A (typ.)) | dual-source automatic transfer · GB 50052 load classification | 1 | $845 |
| Emergency power supply (EPS) (60 kW (typ.)) | emergency & fire lighting · GB 51309 | 1 | $5,775 |
Single-line diagram
How it was calculated
- School: total load 500 kW × design factor 0.8 = 400 kW (explicit coincidence factor — classroom/office occupancy diversity (0.8 coincidence factor))
- Redundancy N+1 → one spare unit, dual + tie
- Emergency level: standard → ATS, EPS (fire lighting),
- Loads: P=400 kW, PF 0.95, 8 circuits
- Demand: 400 × 0.9 = 360 kW
- PFC: Qc = 360 × (0.329 − 0.329) = 0 kVAR → 0 kVAR bank
- Transformer: S = 360 ÷ 0.95 = 378.9 kVA → 500 kVA standard
- Loading: 379 ÷ 500 = 76% (good range)
- Voltage regulation: 76% × 6% × sinφ ≈ 1.4% at full load
- HV: In 28.9 A, Isc 28.9 kA → KYN28A-12-630-315
- LV: In 722 A, Isc 11.8 kA (Xfmr Z 6% + system 0.1%) → GGD-1000, 2 feeder panel(s)
- Cable branch boxes: 1 × DFW-0.4 (1-in/4-out) for feeder grouping
成本敏感因素
- 设备 — 变压器/开关柜/逆变器是最大单项。
- 储能 — 电池是最大变量。
- 铜价与运费 — 铜价联动线缆与运费使到岸成本 ±5–10% 波动。
常见问题
医院供电需要什么冗余?
医院按 GB 50052 属一级重要负荷,需两路独立市电加应急电源(柴发或 EPS),数秒内恢复关键回路。生命维持和手术室用 2N + UPS。计算器按建筑类型、冗余等级(N+1/2N)与应急级别为整套供配电选型。
公共建筑的应急电源如何恢复?
双电源自动转换开关(ATS)检测失电后切到备用柴油发电机,柴发 30-60 秒启动并带满负荷。毫秒级关键负荷用 UPS 桥接。GB 50052 划分应急等级;计算器按建筑负荷类别选 ATS、柴发/EPS 与电池备电。
医院或体育场的典型负荷密度是多少?
医院约 60-120 W/m²(含影像可达 150 W/m²),学校 30-60 W/m²,办公 50-80 W/m²,体育场 60-100 W/m² 外加泛光照明峰值。计算器默认 1500 kW 模拟中型医院;总需量决定变压器与应急容量。
1500 kW 医院需要多大变压器?
1500 kW 医院、0.95 功率因数约需 1580 kVA,故 N+1/2N 选 2×800 kVA 或 2×1000 kVA。医院常设两台变压器带自动母联,任一都能带关键负荷。计算器按 IEC 60076 标准容量并套用所选冗余等级。
什么是 EPS?它和 UPS 有什么区别?
应急电源(EPS)是基于逆变器的照明和生命安全负荷备用电源,切换时间 0.25-5 s,比 UPS(0-10 ms)慢但每 kVA 更便宜,适合电机与照明负荷。UPS 用于不能容忍任何中断的电子设备。计算器为应急照明选 EPS、为关键 IT 选 UPS。
公共建筑适用哪些电能质量规定?
公共建筑须按 IEEE 519 限制谐波畸变(PCC 处 5-8% THD)并维持功率因数高于约 0.9 以免被罚款。LED 照明和变频暖通注入谐波,故常配去谐电容或 APF。计算器校核功率因数与谐波占比并配置补偿。