One-Stop Supply of Conventional & Solar Power Equipment · Power Distribution System Design

1.6 MW Mining Power System Cost Breakdown (Q3 2026 China Supplier Pricing)

1.6 MW Mining Power System Cost Breakdown (Q3 2026 China Supplier Pricing) — itemized bill of materials and FOB pricing for a typical configuration.

Last updated: 2026-09-12 · copper-linked items track the daily LME copper price

Estimated total (FOB): $313,963 · 1600 kVA transformer

Bill of materials

ItemSpecificationQtyPrice (USD)
HV incoming panel (KYN28A-12-630-315)630 A / 31.5 kA · vacuum1$2,448
Main transformer (S13-M-1600/10)1600 kVA · Oil-Immersed · Copper · S131$18,228
LV incoming panel (GGD-2500)2500 A busbar · In 2309 A1$6,155
LV feeder panel (×2) (GGD-2500)distributes 10 circuits2$12,310
Cable branch box (LV) (DFW-0.4)1-in / 4-out · 0.4 kV · 630 A2$1,260
Main feeder cable (TX→LV) (YJV 0.6/1kV 300 mm² ×5)5× 300 mm² Cu · ΔU 1.80% @ 120 m · $154.0/m5$92,400
Feeder cable — Crusher 1 (×10) (YJV 120 mm²)120 mm² Cu · 238 A · ΔU 2.3% · $68.8/m10$82,560
Branch trunk cable (LV → branch box 1) (YJV 300 mm² ×2)2× 300 mm² Cu · 953 A · ΔU 1.9% · $154.0/m2$36,960
Branch trunk cable (LV → branch box 2) (YJV 300 mm²)300 mm² Cu · 477 A · ΔU 1.9% · $154.0/m1$18,480
Main busbar (Cu) (Cu 125×10)125×10 · 2500 A rating · ref $147.8/mincludedPOA
Grounding electrode (Φ20mm × 2.5m rod)R₁ 39.6 Ω → 13 rod(s) ≤ 4 Ω13$125
Soft starter cabinet (largest motor) (500 kW)Soft starter (3.0× In) · start dip 5.0%1$6,600
Detuned PFC capacitor bank (626 kvar)automatic · 7% detuned · 0.4 kV1$8,300
Series detuning reactor (7%) (43.8 kvar)189 Hz tuning · below 5th harmonic1$2,788
Active harmonic filter (APF) (300 A)VFD harmonic mitigation (40% VFD load) · GB/T 145491$25,350

Single-line diagram

CTCT 100/5APTPT 10kV/100V50/5151NHV incomingKYN28A-12-630-315630 A / 31.5 kA - vacuumS13-M-1600/101600 kVAZ = 4%Oil-Immersed - Copper - S13kWhmeteringLV incomingGGD-25000.4 kV LV busbar125x10 Cu - 2500 ASPDLV feeder panel x2 - 10 circuitsCrusher 1 - 238 AYJV 120 mm2Crusher 2 - 238 AYJV 120 mm2Hoist 1 - 238 AYJV 120 mm2Vent fan 1 - 238 AYJV 120 mm2Vent fan 2 - 238 AYJV 120 mm2Vent fan 3 - 238 AYJV 120 mm2Conveyor 1 - 238 AYJV 120 mm2Conveyor 2 - 238 AYJV 120 mm2Conveyor 3 - 238 AYJV 120 mm2Conveyor 4 - 238 AYJV 120 mm2Grounding 13xdia20mmx2.5m rodCable branch box DFW-0.4 x2 (1-in / 4-out)
LEGENDBreaker (52)DisconnectorCTCT (current transformer)PTPT (voltage transformer)50/51Protection relay 50/51/51N/87kWhMeter (kWh)SPD (surge protection)Transformer

How it was calculated

What drives the cost

  • Equipment — the transformer/switchgear/inverter is the largest single line item.
  • Storage (where applicable) — batteries are the biggest swing factor.
  • Copper & freight — copper-linked cabling and freight shift landed cost ±5–10%.

Frequently asked questions

How does altitude affect transformer and switchgear rating?
Above 1000 m, thinner air reduces cooling and dielectric strength. Transformers derate about 0.5% per 100 m above 1000 m, and switchgear derates similarly. A 1500 m site needs roughly 2.5% derating; a 3000 m site about 10%. The calculator applies altitude derating to the selected transformer and panels per IEC 60076 and IEC 62271.
What is the typical voltage for underground mining power?
Underground mining uses 10 kV or 6 kV distribution into the mine, stepping down to 1.14 kV or 0.66 kV for crushers, hoists and conveyors, and 0.4 kV for auxiliaries. Long cable runs and motor starting favour the higher LV levels. The calculator models a 10/0.4 kV surface plant with motor-starting dip checks for the hoist and crusher.
Why do mine hoists need special starting consideration?
A mine hoist motor (often 500 kW-3 MW) draws 5-7 times rated current on DOL start, which can dip the mine bus below 85% and trip other drives. Soft-start or VFD limits the inrush, and the transformer must be sized for the starting kVA. The calculator checks the voltage dip of the largest motor and sizes supply accordingly.
How are VFD harmonics handled in a mining plant?
With 40% of load on VFDs, THDi can exceed 20%, so a detuned capacitor bank (7% reactor) or APF is needed to meet IEEE 519 (5% THD at PCC). The calculator sizes reactive compensation and detuning based on the VFD share; heavy-dust duty also calls for IP54 or higher enclosures.
What demand factor applies to a mining plant?
Crushers, hoists, fans and conveyors do not peak together; a demand factor of 0.6-0.75 is typical. A plant with 250 kW crushers, a 500 kW hoist, 160 kW fans and 90 kW conveyors rarely exceeds 60-70% of the 1,600+ kW nameplate simultaneously. The calculator applies kd before selecting transformer kVA.
What enclosure and protection does mining switchgear need?
Mining switchgear must resist dust and moisture: IP54 or IP55 for surface plants, flameproof Ex d for underground gassy mines (IEC 60079). Heavy-dust environments shorten creepage distances, so wider clearances and anti-tracking insulation are standard. The calculator flags dust level and applies the corresponding enclosure grade in the BOM.

Size your own configuration

Run the calculator for your exact load and get a full BOM + FOB price.

Open calculator Request a Quote

Related