One-Stop Supply of Conventional & Solar Power Equipment · Power Distribution System Design

5 MW Mining Power System Cost Breakdown (Q3 2026 China Supplier Pricing)

5 MW Mining Power System Cost Breakdown (Q3 2026 China Supplier Pricing) — itemized bill of materials and FOB pricing for a typical configuration.

Last updated: 2026-09-12 · copper-linked items track the daily LME copper price

Estimated total (FOB): $805,825 · 5000 kVA transformer

Bill of materials

ItemSpecificationQtyPrice (USD)
HV incoming panel (KYN28A-12-630-315)630 A / 31.5 kA · vacuum1$2,448
Main transformer (S13-M-5000/10)5000 kVA · Oil-Immersed · Copper · S131$51,399
LV incoming panel (MNS (drawer type))4000 A busbar · In 7217 A1$13,273
LV feeder panel (×4) (MNS (drawer type))distributes 19 circuits4$53,092
Cable branch box (LV) (DFW-0.4)1-in / 4-out · 0.4 kV · 630 A4$2,520
Main feeder cable (TX→LV) (YJV 0.6/1kV 300 mm² ×16)16× 300 mm² Cu · ΔU 1.76% @ 120 m · $154.0/m16$295,680
Main feeder (custom/dual busway) (Busway > 6300 A)LV current 7217 A exceeds the largest standard busway (6300 A) — custom busway or dual-run busway required; shown as parallel cables below1POA
Feeder cable — Crusher 1 (×19) (YJV 150 mm²)150 mm² Cu · 285 A · ΔU 2.2% · $86.0/m19$196,080
Branch trunk cable (LV → branch box 1) (YJV 240 mm² ×3)3× 240 mm² Cu · 1140 A · ΔU 1.9% · $123.0/m3$44,280
Branch trunk cable (LV → branch box 2) (YJV 240 mm² ×3)3× 240 mm² Cu · 1140 A · ΔU 1.9% · $123.0/m3$44,280
Branch trunk cable (LV → branch box 3) (YJV 240 mm² ×3)3× 240 mm² Cu · 1140 A · ΔU 1.9% · $123.0/m3$44,280
Branch trunk cable (LV → branch box 4) (YJV 300 mm² ×2)2× 300 mm² Cu · 855 A · ΔU 1.7% · $154.0/m2$36,960
Main busbar (Cu) (Cu 125×10)125×10 · 2500 A rating · ref $147.8/mincludedPOA
Grounding electrode (Φ20mm × 2.5m rod)R₁ 39.6 Ω → 13 rod(s) ≤ 4 Ω13$125
Soft starter cabinet (largest motor) (1500 kW)Soft starter (3.0× In) · start dip 5.6%1$6,600
Detuned PFC capacitor bank (1421 kvar)automatic · 7% detuned · 0.4 kV1$10,800
Series detuning reactor (7%) (99.5 kvar)189 Hz tuning · below 5th harmonic1$4,009
Active harmonic filter (APF) (547 A)VFD harmonic mitigation (40% VFD load) · GB/T 145491POA

Single-line diagram

CTCT 290/5APTPT 10kV/100V50/5151NHV incomingKYN28A-12-630-315630 A / 31.5 kA - vacuumS13-M-5000/105000 kVAZ = 4%Oil-Immersed - Copper - S13kWhmeteringLV incomingMNS (drawer type)0.4 kV LV busbar125x10 Cu - 2500 ASPDLV feeder panel x4 - 19 circuitsCrusher 1 - 285 AYJV 150 mm2Crusher 2 - 285 AYJV 150 mm2Crusher 3 - 285 AYJV 150 mm2Crusher 4 - 285 AYJV 150 mm2Hoist 1 - 285 AYJV 150 mm2Vent fan 1 - 285 AYJV 150 mm2Vent fan 2 - 285 AYJV 150 mm2Vent fan 3 - 285 AYJV 150 mm2Vent fan 4 - 285 AYJV 150 mm2Vent fan 5 - 285 AYJV 150 mm2Vent fan 6 - 285 AYJV 150 mm2Conveyor 1 - 285 AYJV 150 mm2Conveyor 2 - 285 AYJV 150 mm2Conveyor 3 - 285 AYJV 150 mm2Conveyor 4 - 285 AYJV 150 mm2Conveyor 5 - 285 AYJV 150 mm2Conveyor 6 - 285 AYJV 150 mm2Conveyor 7 - 285 AYJV 150 mm2Conveyor 8 - 285 AYJV 150 mm2Grounding 13xdia20mmx2.5m rodCable branch box DFW-0.4 x4 (1-in / 4-out)
LEGENDBreaker (52)DisconnectorCTCT (current transformer)PTPT (voltage transformer)50/51Protection relay 50/51/51N/87kWhMeter (kWh)SPD (surge protection)Transformer

How it was calculated

What drives the cost

  • Equipment — the transformer/switchgear/inverter is the largest single line item.
  • Storage (where applicable) — batteries are the biggest swing factor.
  • Copper & freight — copper-linked cabling and freight shift landed cost ±5–10%.

Frequently asked questions

How does altitude affect transformer and switchgear rating?
Above 1000 m, thinner air reduces cooling and dielectric strength. Transformers derate about 0.5% per 100 m above 1000 m, and switchgear derates similarly. A 1500 m site needs roughly 2.5% derating; a 3000 m site about 10%. The calculator applies altitude derating to the selected transformer and panels per IEC 60076 and IEC 62271.
What is the typical voltage for underground mining power?
Underground mining uses 10 kV or 6 kV distribution into the mine, stepping down to 1.14 kV or 0.66 kV for crushers, hoists and conveyors, and 0.4 kV for auxiliaries. Long cable runs and motor starting favour the higher LV levels. The calculator models a 10/0.4 kV surface plant with motor-starting dip checks for the hoist and crusher.
Why do mine hoists need special starting consideration?
A mine hoist motor (often 500 kW-3 MW) draws 5-7 times rated current on DOL start, which can dip the mine bus below 85% and trip other drives. Soft-start or VFD limits the inrush, and the transformer must be sized for the starting kVA. The calculator checks the voltage dip of the largest motor and sizes supply accordingly.
How are VFD harmonics handled in a mining plant?
With 40% of load on VFDs, THDi can exceed 20%, so a detuned capacitor bank (7% reactor) or APF is needed to meet IEEE 519 (5% THD at PCC). The calculator sizes reactive compensation and detuning based on the VFD share; heavy-dust duty also calls for IP54 or higher enclosures.
What demand factor applies to a mining plant?
Crushers, hoists, fans and conveyors do not peak together; a demand factor of 0.6-0.75 is typical. A plant with 250 kW crushers, a 500 kW hoist, 160 kW fans and 90 kW conveyors rarely exceeds 60-70% of the 1,600+ kW nameplate simultaneously. The calculator applies kd before selecting transformer kVA.
What enclosure and protection does mining switchgear need?
Mining switchgear must resist dust and moisture: IP54 or IP55 for surface plants, flameproof Ex d for underground gassy mines (IEC 60079). Heavy-dust environments shorten creepage distances, so wider clearances and anti-tracking insulation are standard. The calculator flags dust level and applies the corresponding enclosure grade in the BOM.

Size your own configuration

Run the calculator for your exact load and get a full BOM + FOB price.

Open calculator Request a Quote

Related