One-Stop Supply of Conventional & Solar Power Equipment · Power Distribution System Design

2 MW Industrial Park Power System Cost Breakdown (Q3 2026 China Supplier Pricing)

2 MW Industrial Park Power System Cost Breakdown (Q3 2026 China Supplier Pricing) — itemized bill of materials and FOB pricing for a typical configuration.

Last updated: 2026-09-12 · copper-linked items track the daily LME copper price

Estimated total (FOB): $257,923 · 1600 kVA transformer

Bill of materials

ItemSpecificationQtyPrice (USD)
HV incoming panel (KYN28A-12-630-315)630 A / 31.5 kA · vacuum1$2,448
Main transformer (S13-M-1600/10)1600 kVA · Oil-Immersed · Copper · S131$18,228
LV incoming panel (GGD-2500)2500 A busbar · In 2309 A1$6,155
LV feeder panel (×2) (GGD-2500)distributes 8 circuits2$12,310
Cable branch box (LV) (DFW-0.4)1-in / 4-out · 0.4 kV · 630 A1$630
Main feeder cable (TX→LV) (YJV 0.6/1kV 300 mm² ×5)5× 300 mm² Cu · ΔU 1.20% @ 80 m · $154.0/m5$61,600
Feeder cable — Plant feeder 1 (×8) (YJV 300 mm²)300 mm² Cu · 440 A · ΔU 1.1% · $154.0/m8$98,560
Branch trunk cable (LV → branch box 1) (YJV 300 mm² ×4)4× 300 mm² Cu · 1760 A · ΔU 1.1% · $154.0/m4$49,280
Main busbar (Cu) (Cu 125×10)125×10 · 2500 A rating · ref $147.8/mincludedPOA
Grounding electrode (Φ20mm × 2.5m rod)R₁ 39.6 Ω → 13 rod(s) ≤ 4 Ω13$125
Detuned PFC capacitor bank (443 kvar)automatic · 7% detuned · 0.4 kV1$5,800
Series detuning reactor (7%) (31.0 kvar)189 Hz tuning · below 5th harmonic1$2,788

Single-line diagram

CTCT 100/5APTPT 10kV/100V50/5151NHV incomingKYN28A-12-630-315630 A / 31.5 kA - vacuumS13-M-1600/101600 kVAZ = 4%Oil-Immersed - Copper - S13kWhmeteringLV incomingGGD-25000.4 kV LV busbar125x10 Cu - 2500 ASPDLV feeder panel x2 - 8 circuitsPlant feeder 1 - 440 AYJV 300 mm2Plant feeder 2 - 440 AYJV 300 mm2Plant feeder 3 - 440 AYJV 300 mm2Plant feeder 4 - 440 AYJV 300 mm2Plant feeder 5 - 440 AYJV 300 mm2Plant feeder 6 - 440 AYJV 300 mm2Plant feeder 7 - 440 AYJV 300 mm2Plant feeder 8 - 440 AYJV 300 mm2Grounding 13xdia20mmx2.5m rodCable branch box DFW-0.4 x1 (1-in / 4-out)
LEGENDBreaker (52)DisconnectorCTCT (current transformer)PTPT (voltage transformer)50/51Protection relay 50/51/51N/87kWhMeter (kWh)SPD (surge protection)Transformer

How it was calculated

What drives the cost

  • Equipment — the transformer/switchgear/inverter is the largest single line item.
  • Storage (where applicable) — batteries are the biggest swing factor.
  • Copper & freight — copper-linked cabling and freight shift landed cost ±5–10%.

Frequently asked questions

What demand factor applies to an industrial park?
An industrial park with many factories never runs every machine simultaneously; a demand factor of 0.55-0.7 is typical. A 2000 kW connected load at 0.6 kd and 0.9 pf gives ~1330 kVA demand, so a 1600 kVA transformer or two 800 kVA units suit. The calculator uses demand factor and motor share to size the MV/LV plant.
How much harmonic filtering does a factory-heavy park need?
When 60% of load is motors on VFDs and 25% is non-linear (rectifiers, UPS), THDi can reach 15-25%. IEEE 519 limits THD to 5-8% at the point of common coupling, so a detuned capacitor bank (7% reactor) or APF is required. The calculator sizes compensation and detuning from the harmonic share.
What is the standard MV/LV architecture for an industrial park?
Typical architecture: 10 kV (or 35 kV) utility feed -> ring or radial MV switchgear -> one transformer per factory or block -> 0.4 kV switchboards -> motor control centers. A 10 kV ring with RMUs along the ring offers N-1 supply. The calculator sizes the transformers, switchgear and compensation for the aggregated park load.
How do I allocate transformer capacity per factory?
Give each factory its own transformer sized to its demand plus 20-25% headroom, or share one large transformer for small tenants. Separate transformers isolate faults and simplify metering, but shared units cost less. The calculator aggregates the park demand and shows the single-transformer and split-transformer options.
What power factor should an industrial park maintain?
Utilities usually require 0.9-0.95 power factor and levy penalties below ~0.9. Industrial parks with motor-heavy load typically start at 0.75-0.85 and add capacitor banks to reach 0.95. The calculator computes the required kvar compensation to correct from measured pf to target and sizes the LV capacitor bank.
What redundancy does a park MV network usually provide?
A ring-main MV network with normally-open tie provides N-1 redundancy: any cable or RMU fault is isolated and load restored from the other direction. Radial feeders are cheaper but lose supply on a fault. The calculator's architecture notes cover ring vs radial options and their reliability trade-off.

Size your own configuration

Run the calculator for your exact load and get a full BOM + FOB price.

Open calculator Request a Quote

Related