2MW 工业园区供电系统(2026年第三季度中国供应商价格)
2 MW Industrial Park Power System Cost Breakdown (Q3 2026 China Supplier Pricing) — itemized bill of materials and FOB pricing for a typical configuration.
Estimated total (FOB): $257,923 · 1600 kVA transformer
Bill of materials
| Item | Specification | Qty | Price (USD) |
|---|---|---|---|
| HV incoming panel (KYN28A-12-630-315) | 630 A / 31.5 kA · vacuum | 1 | $2,448 |
| Main transformer (S13-M-1600/10) | 1600 kVA · Oil-Immersed · Copper · S13 | 1 | $18,228 |
| LV incoming panel (GGD-2500) | 2500 A busbar · In 2309 A | 1 | $6,155 |
| LV feeder panel (×2) (GGD-2500) | distributes 8 circuits | 2 | $12,310 |
| Cable branch box (LV) (DFW-0.4) | 1-in / 4-out · 0.4 kV · 630 A | 1 | $630 |
| Main feeder cable (TX→LV) (YJV 0.6/1kV 300 mm² ×5) | 5× 300 mm² Cu · ΔU 1.20% @ 80 m · $154.0/m | 5 | $61,600 |
| Feeder cable — Plant feeder 1 (×8) (YJV 300 mm²) | 300 mm² Cu · 440 A · ΔU 1.1% · $154.0/m | 8 | $98,560 |
| Branch trunk cable (LV → branch box 1) (YJV 300 mm² ×4) | 4× 300 mm² Cu · 1760 A · ΔU 1.1% · $154.0/m | 4 | $49,280 |
| Main busbar (Cu) (Cu 125×10) | 125×10 · 2500 A rating · ref $147.8/m | included | POA |
| Grounding electrode (Φ20mm × 2.5m rod) | R₁ 39.6 Ω → 13 rod(s) ≤ 4 Ω | 13 | $125 |
| Detuned PFC capacitor bank (443 kvar) | automatic · 7% detuned · 0.4 kV | 1 | $5,800 |
| Series detuning reactor (7%) (31.0 kvar) | 189 Hz tuning · below 5th harmonic | 1 | $2,788 |
Single-line diagram
How it was calculated
- Connected equipment load = 2,000 kW
- Demand = 2,000 × 0.6 = 1,200 kW
- Motor share = 60% → 720 kW (drives natural PF 0.82)
- Reactive compensation: Qc = 1,200 × (tanφ₁ − tanφ₂) = 443 kvar
- Harmonic-source share = 25% → 300 kW → Ih = 137 A (30% THDi)
- Loads: P=2,000 kW, PF 0.82, 8 circuits
- Demand: 2,000 × 0.6 = 1,200 kW
- Transformer: S = 1,200 ÷ 0.95 = 1263.2 kVA → 1,600 kVA standard
- Loading: 1,263 ÷ 1,600 = 79% (good range)
- Voltage regulation: 79% × 4% × sinφ ≈ 1.0% at full load
- HV: In 92.4 A, Isc 28.9 kA → KYN28A-12-630-315
- LV: In 2309 A, Isc 53.5 kA (Xfmr Z 4% + system 0.3%) → GGD-2500, 2 feeder panel(s)
成本敏感因素
- 设备 — 变压器/开关柜/逆变器是最大单项。
- 储能 — 电池是最大变量。
- 铜价与运费 — 铜价联动线缆与运费使到岸成本 ±5–10% 波动。
常见问题
工业园区该取多大的需用系数?
园区多家工厂不会同时开满设备,需用系数典型 0.55-0.7。2000 kW 装机、0.6 需用系数、0.9 功率因数得约 1330 kVA,宜配 1600 kVA 或两台 800 kVA。计算器用需用系数与电机占比为中低压厂区选型。
工厂密集的园区需要多少谐波治理?
当 60% 负荷为变频电机、25% 为非线性(整流、UPS)时,THDi 可达 15-25%。IEEE 519 要求公共连接点 THD 限 5-8%,故需 7% 去谐电容器组或 APF。计算器按谐波占比配置补偿与去谐。
工业园区的标准中低压架构是怎样的?
典型架构:10 kV(或 35 kV)市电 → 环网或放射式中压开关柜 → 每厂/每区块一台变压器 → 0.4 kV 开关柜 → 电机控制中心。沿环网布置环网柜的 10 kV 环网可提供 N-1 供电。计算器为园区聚合负荷选变压器、开关柜与补偿。
如何为每家工厂分配变压器容量?
每家工厂配一台按需用容量加 20-25% 裕量的独立变压器,小租户可合用一台大变压器。独立变压器隔离故障、便于计量,但共享方案成本更低。计算器聚合园区需量并给出单台与分拆方案。
工业园区应维持多大功率因数?
供电公司通常要求 0.9-0.95 功率因数,低于约 0.9 收取罚金。电机为主的园区初始功率因数 0.75-0.85,加电容器组可提到 0.95。计算器算出从实测 pf 到目标所需的 kvar 补偿并选低压电容柜。
园区中压网络通常提供什么冗余?
带常开联络的环网中压网络提供 N-1 冗余:任一段电缆或环网柜故障可被隔离并从另一方向恢复供电。放射式馈线更便宜但故障即失电。计算器的架构说明覆盖环网与放射式的可靠性和成本权衡。