2MW 工业园区供电系统(2026年第三季度中国供应商价格)

2 MW Industrial Park Power System Cost Breakdown (Q3 2026 China Supplier Pricing) — itemized bill of materials and FOB pricing for a typical configuration.

Last updated: 2026-09-12 · copper-linked items track the daily LME copper price

Estimated total (FOB): $257,923 · 1600 kVA transformer

Bill of materials

ItemSpecificationQtyPrice (USD)
HV incoming panel (KYN28A-12-630-315)630 A / 31.5 kA · vacuum1$2,448
Main transformer (S13-M-1600/10)1600 kVA · Oil-Immersed · Copper · S131$18,228
LV incoming panel (GGD-2500)2500 A busbar · In 2309 A1$6,155
LV feeder panel (×2) (GGD-2500)distributes 8 circuits2$12,310
Cable branch box (LV) (DFW-0.4)1-in / 4-out · 0.4 kV · 630 A1$630
Main feeder cable (TX→LV) (YJV 0.6/1kV 300 mm² ×5)5× 300 mm² Cu · ΔU 1.20% @ 80 m · $154.0/m5$61,600
Feeder cable — Plant feeder 1 (×8) (YJV 300 mm²)300 mm² Cu · 440 A · ΔU 1.1% · $154.0/m8$98,560
Branch trunk cable (LV → branch box 1) (YJV 300 mm² ×4)4× 300 mm² Cu · 1760 A · ΔU 1.1% · $154.0/m4$49,280
Main busbar (Cu) (Cu 125×10)125×10 · 2500 A rating · ref $147.8/mincludedPOA
Grounding electrode (Φ20mm × 2.5m rod)R₁ 39.6 Ω → 13 rod(s) ≤ 4 Ω13$125
Detuned PFC capacitor bank (443 kvar)automatic · 7% detuned · 0.4 kV1$5,800
Series detuning reactor (7%) (31.0 kvar)189 Hz tuning · below 5th harmonic1$2,788

Single-line diagram

CTCT 100/5APTPT 10kV/100V50/5151NHV incomingKYN28A-12-630-315630 A / 31.5 kA - vacuumS13-M-1600/101600 kVAZ = 4%Oil-Immersed - Copper - S13kWhmeteringLV incomingGGD-25000.4 kV LV busbar125x10 Cu - 2500 ASPDLV feeder panel x2 - 8 circuitsPlant feeder 1 - 440 AYJV 300 mm2Plant feeder 2 - 440 AYJV 300 mm2Plant feeder 3 - 440 AYJV 300 mm2Plant feeder 4 - 440 AYJV 300 mm2Plant feeder 5 - 440 AYJV 300 mm2Plant feeder 6 - 440 AYJV 300 mm2Plant feeder 7 - 440 AYJV 300 mm2Plant feeder 8 - 440 AYJV 300 mm2Grounding 13xdia20mmx2.5m rodCable branch box DFW-0.4 x1 (1-in / 4-out)
LEGENDBreaker (52)DisconnectorCTCT (current transformer)PTPT (voltage transformer)50/51Protection relay 50/51/51N/87kWhMeter (kWh)SPD (surge protection)Transformer

How it was calculated

成本敏感因素

  • 设备 — 变压器/开关柜/逆变器是最大单项。
  • 储能 — 电池是最大变量。
  • 铜价与运费 — 铜价联动线缆与运费使到岸成本 ±5–10% 波动。

常见问题

工业园区该取多大的需用系数?
园区多家工厂不会同时开满设备,需用系数典型 0.55-0.7。2000 kW 装机、0.6 需用系数、0.9 功率因数得约 1330 kVA,宜配 1600 kVA 或两台 800 kVA。计算器用需用系数与电机占比为中低压厂区选型。
工厂密集的园区需要多少谐波治理?
当 60% 负荷为变频电机、25% 为非线性(整流、UPS)时,THDi 可达 15-25%。IEEE 519 要求公共连接点 THD 限 5-8%,故需 7% 去谐电容器组或 APF。计算器按谐波占比配置补偿与去谐。
工业园区的标准中低压架构是怎样的?
典型架构:10 kV(或 35 kV)市电 → 环网或放射式中压开关柜 → 每厂/每区块一台变压器 → 0.4 kV 开关柜 → 电机控制中心。沿环网布置环网柜的 10 kV 环网可提供 N-1 供电。计算器为园区聚合负荷选变压器、开关柜与补偿。
如何为每家工厂分配变压器容量?
每家工厂配一台按需用容量加 20-25% 裕量的独立变压器,小租户可合用一台大变压器。独立变压器隔离故障、便于计量,但共享方案成本更低。计算器聚合园区需量并给出单台与分拆方案。
工业园区应维持多大功率因数?
供电公司通常要求 0.9-0.95 功率因数,低于约 0.9 收取罚金。电机为主的园区初始功率因数 0.75-0.85,加电容器组可提到 0.95。计算器算出从实测 pf 到目标所需的 kvar 补偿并选低压电容柜。
园区中压网络通常提供什么冗余?
带常开联络的环网中压网络提供 N-1 冗余:任一段电缆或环网柜故障可被隔离并从另一方向恢复供电。放射式馈线更便宜但故障即失电。计算器的架构说明覆盖环网与放射式的可靠性和成本权衡。

计算你自己的配置

输入你的实际负荷,获得完整 BOM 与 FOB 报价。

Open calculator Request a Quote