Transformator QDTB®

Kalkulator Sistem Tenaga Fasilitas Publik

Rancang pasokan listrik yang andal untuk rumah sakit, sekolah, stadion, dan bandara — ukuran transformator, redundansi N / N+1 / 2N, automatic transfer switch, penerangan darurat (EPS), dan diesel siaga, dengan BOM dan diagram satu garis.

Mulai Menghitung Solusi Fasilitas Umum
Pemantauan dan kontrol cerdas
Tambahkan lapisan proteksi, pengukuran, dan SCADA ke BOM dan diagram arsitektur.

Mengapa kalkulator ini

Fasilitas umum menanggung beban keselamatan jiwa yang tidak boleh kehilangan daya. Kalkulator ini menghitung ukuran pasokan transformator jenis kering untuk jenis bangunan, menerapkan redundansi N / N+1 / 2N, dan mengonfigurasi rantai daya darurat — ATS, EPS penerangan kebakaran dan diesel siaga — sesuai GB 50052, GB 51309 dan GB 50016.

Worked Examples

Example 1 — Hospital (2N, Critical Emergency Power) · FOB $310,667
Hospital power system · 2N · 10kV/0.4kV
1,600 kVA transformer
SCB13-1600/10 · critical emergency · 1,500 kW
Design load
1,500 kW × 1 → 1,500 kW
Redundancy
2N
Emergency level
critical
Transformer
SCB13-1600/10
Est. total (FOB)
POA
📦 Bill of Materials
EquipmentModelSpecQty
HV incoming panelKYN28A-12-630-315630 A / 31.5 kA · vacuum2
HV bus-tie panelKYN28A-12-630-315630 A / 31.5 kA · vacuum1
Main transformer (each)SCB13-1600/101600 kVA · Dry-Type · Copper · SCB132
LV incoming panelGGD-25002500 A busbar · In 2309 A2
LV bus-tie panelGGD-25002500 A busbar1
LV feeder panel (×3)GGD-2500distributes 13 circuits3
Cable branch box (LV)DFW-0.41-in / 4-out · 0.4 kV · 630 A3
Main feeder cable (TX→LV)YJV 0.6/1kV 300 mm² ×55× 300 mm² Cu · ΔU 0.90% @ 60 m · $154.0/m5
Feeder cable — Ward 1 (×13)YJV 70 mm²70 mm² Cu · 175 A · ΔU 1.5% · $37.0/m13
Branch trunk cable (LV → branch box 1)YJV 185 mm² ×22× 185 mm² Cu · 701 A · ΔU 1.1% · $103.0/m2
Branch trunk cable (LV → branch box 2)YJV 185 mm² ×22× 185 mm² Cu · 701 A · ΔU 1.1% · $103.0/m2
Branch trunk cable (LV → branch box 3)YJV 70 mm²70 mm² Cu · 175 A · ΔU 1.5% · $37.0/m1
Main busbar (Cu)Cu 125×10125×10 · 2500 A rating · ref $147.8/mincluded
Grounding electrodeΦ20mm × 2.5m rodR₁ 39.6 Ω → 13 rod(s) ≤ 4 Ω13
Automatic transfer switch (ATS)ATS 600 A (typ.)dual-source automatic transfer · GB 50052 load classification1
Emergency power supply (EPS)225 kW (typ.)emergency & fire lighting · GB 513091
Diesel generator set (standby)2000 kVA (typ.)standby power for life-safety & critical loads · GB 500161
Medical IT isolated power supply45 kVAoperating theatre / ICU isolated power · IEC 60364-7-7101
Operating-room UPS (online)75 kVAonline double-conversion · IEC 62040 · quoted per project1
Fire pump feeder (dedicated)120 kWdedicated fire pump supply · GB 500161
📐 Single-line diagram
CTCT50/5150/5187differentialFeed AFeed BKYN28A-12-630-315KYN28A-12-630-315HV bus-tieSCB13-1600/101600 kVA - Z=6%SCB13-1600/101600 kVA - Z=6%LV bus-tie0.4 kV0.4 kVWard 1 - 175 AYJV 70 mm2Ward 2 - 175 AYJV 70 mm2Ward 3 - 175 AYJV 70 mm2Ward 4 - 175 AYJV 70 mm2Ward 5 - 175 AYJV 70 mm2Ward 6 - 175 AYJV 70 mm2Ward 7 - 175 AYJV 70 mm2Ward 8 - 175 AYJV 70 mm2Ward 9 - 175 AYJV 70 mm2Ward 10 - 175 AYJV 70 mm2Ward 11 - 175 AYJV 70 mm2Ward 12 - 175 AYJV 70 mm2Ward 13 - 175 AYJV 70 mm2Grounding 13xdia20mmx2.5m rod
LEGENDBreaker (52)DisconnectorCTCT (current transformer)PTPT (voltage transformer)50/51Protection relay 50/51/51N/87kWhMeter (kWh)SPD (surge protection)Transformer
⚙️ Electrical schematic (protection & metering)
ELECTRICAL SCHEMATIC - PROTECTION & METERING10 kV / 0.4 kV - 1600 kVA - secondary circuits (schematic)INCOMING 10 kVCT100/5Aprotection CT5250/5151N87overcurrent / earth-fault / diffPT10kV/100Vbus PT (voltage)TRANSFORMER1600 kVAZ = 6%kWhrevenue meteringLV 520.4 kV LV BUSSPDCT.../5AWard 1 - 175 A50/51CT.../5AWard 2 - 175 A50/51CT.../5AWard 3 - 175 A50/51CT.../5AWard 4 - 175 A50/51CT.../5AWard 5 - 175 A50/51CT.../5AWard 6 - 175 A50/51CT.../5AWard 7 - 175 A50/51CT.../5AWard 8 - 175 A50/51CT.../5AWard 9 - 175 A50/51CT.../5AWard 10 - 175 A50/51CT.../5AWard 11 - 175 A50/51CT.../5AWard 12 - 175 A50/51CT.../5AWard 13 - 175 A50/51
⛳ Grounding grid layout
SUBSTATION GROUNDING GRID LAYOUTsite 12 m x 8 m - ring earth electrode (schematic)TRANSFORMERR1R2R3R4R5R6R7R8R9R10R11R12R1312 mGround rods: 13 x dia 20 mm x 2.5 m copper-bonded steelRod spacing: 5 m (= 2 x rod length, ring electrode)Target resistance: <= 4 ohm (measure after installation)Standard: IEEE 80 / GB-T 50065 (earthing design) - indicative layout
🔌 Cable schedule & routing
CABLE SCHEDULEIDFromToCable (model / spec)LengthC0TransformerLV panelYJV 0.6/1kV 300 mm2 (2309 A)60 mC1LV panelWard 1YJV 70 mm2 (175 A)60 mC2LV panelWard 2YJV 70 mm2 (175 A)60 mC3LV panelWard 3YJV 70 mm2 (175 A)60 mC4LV panelWard 4YJV 70 mm2 (175 A)60 mC5Branch boxWard 5YJV 70 mm260 mC6Branch boxWard 6YJV 70 mm260 mC7Branch boxWard 7YJV 70 mm260 mC8Branch boxWard 8YJV 70 mm260 mC9Branch boxWard 9YJV 70 mm260 mC10Branch boxWard 10YJV 70 mm260 mC11Branch boxWard 11YJV 70 mm260 mROUTING (schematic)LV PANELL1L2L3L4L5L6L7L8... +4 feedersCable lengths are indicative (run-length based); confirm on site before installation.
🗄 Switchgear arrangement
SWITCHGEAR ARRANGEMENTpanel lineup (front view, schematic)HV INCOMINGKYN28A-12-630-315HV BUS-TIEKYN28A-12-630-315LV INCOMINGGGD-2500LV BUS-TIEGGD-2500FEEDERGGD-2500FEEDERGGD-2500FEEDERGGD-2500BRANCH BOXDFW-0.48 panel(s) - each 90 mm (typical)Clearance / aisle per IEC 61936-1 - layout indicative
🛡 Protection configuration
PROTECTION CONFIGURATION10 kV / 0.4 kV - 1600 kVA - protection zones (schematic)INCOMING 10 kVCTCT 100/5A505151Novercurrent / earth-fault52TRANSFORMER1600 kVA - Z=6%8749differential + thermalCTCT 2500/5A505151NLV incoming protection520.4 kV LV BUSCTCT 2500/5A50/51BUS-TIECTCT 200/5A50/5151NWard 1175 ACTCT 200/5A50/5151NWard 2175 ACTCT 200/5A50/5151NWard 3175 ACTCT 200/5A50/5151NWard 4175 ACTCT 200/5A50/5151NWard 5175 ACTCT 200/5A50/5151NWard 6175 ACTCT 200/5A50/5151NWard 7175 ACTCT 200/5A50/5151NWard 8175 ACTCT 200/5A50/5151NWard 9175 ACTCT 200/5A50/5151NWard 10175 ACTCT 200/5A50/5151NWard 11175 ACTCT 200/5A50/5151NWard 12175 ACTCT 200/5A50/5151NWard 13175 AProtection layout & CT ratios are schematic / illustrative final settings per IEC 60255 / IEEE 242.
📋 Protection settings
CircuitProtectionSettingTimeStandard
HV incoming 10 kV50 instantaneous739 AinstIEC 60255-151 / IEEE 242
HV incoming 10 kV51 overcurrent111 A0.5 sIEC 60255-151 / IEEE 242
HV incoming 10 kV51N earth-fault18 A0.5 sIEC 60364-4-41
Transformer 1600 kVA87 differential18 AinstIEEE C37.91 / GB/T 14285
Transformer 1600 kVA49 thermal overload89% of ratedalarm 90%IEC 60076-7 / IEEE C57.91
LV incoming 0.4 kV50 instantaneous18475 AinstIEC 60947-2
LV incoming 0.4 kV51 overcurrent2771 A0.3 sIEC 60947-2 / IEC 60255
LV incoming 0.4 kV51N earth-fault462 A0.3 sIEC 60364-4-41
LV bus-tie50/51 overcurrent2771 A0.3 sIEC 60947-2
Ward 150/51/51N (MCCB)Ir 193 A - Im 1402 A - Ig 35 A0.1 s (grading)IEC 60947-2 / IEC 60255
Ward 250/51/51N (MCCB)Ir 193 A - Im 1402 A - Ig 35 A0.1 s (grading)IEC 60947-2 / IEC 60255
Ward 350/51/51N (MCCB)Ir 193 A - Im 1402 A - Ig 35 A0.1 s (grading)IEC 60947-2 / IEC 60255
Ward 450/51/51N (MCCB)Ir 193 A - Im 1402 A - Ig 35 A0.1 s (grading)IEC 60947-2 / IEC 60255
Ward 550/51/51N (MCCB)Ir 193 A - Im 1402 A - Ig 35 A0.1 s (grading)IEC 60947-2 / IEC 60255
Ward 650/51/51N (MCCB)Ir 193 A - Im 1402 A - Ig 35 A0.1 s (grading)IEC 60947-2 / IEC 60255
+7 more feeders50/51/51N (MCCB)per feeder load0.1 s (grading)IEC 60947-2
Settings are illustrative starting points — confirm with a protection coordination study per IEC 60255 / IEEE 242.
📚 Calculation book
CALCULATION BOOK
1600 kVA - 10kV/0.4kV - N+1 - illustrative
1. Load calculation
Standard: IEC 60076 - IEC 60364-5-52
ParameterFormulaValue
Connected loadP = sum(kW)1,500 kW
Demand factorKd0.9
Demand powerPd = P x Kd1,350 kW
Power factorcos(phi) before -> after0.95 -> 0.95
Design apparent powerSd = Pd / cos(phi)1,421 kVA
Transformer loadingSd / Srated89%
2. Short-circuit calculation
Standard: IEC 60909
ParameterFormulaValue
System impedance (pu)Zs = S / Ssc0.32% (on 1600 kVA base)
Transformer impedanceZt = Z%6%
Total impedanceZ = Zt + Zs6.32%
LV prospective IscIsc = In / Z36.5 kA
HV prospective IscIsc = Ssc / (sqrt(3) x V)28.9 kA
Breaking checkIcu >= IscLV 50 kA (1.4x margin) PASS
3. Voltage drop
Standard: IEC 60364-5-52 Annex G
ParameterFormulaValue
Main feederdU = sqrt(3) x I x L x R / V300 mm2 - dU 0.90% @ 60 m
Limitmax 3%within limit
Transformer volt. reg.dU ~ loading x Z% x sin(phi)1.7% at full load
4. Reactive power / harmonics
Standard: IEC 61921 (PFC) - IEEE 519 (harmonics)
ParameterFormulaValue
Required compensationQc = Pd x (tan1 - tan2)0 kvar
PFC bankstandard step0 kvar
Detuned reactorp = 6%n/a
5. Grounding
Standard: IEC 60364-5-54 earthing arrangements and protective conductors LV earthing target 10 ohm (TN systems); 4 ohm used as a conservative design target - target 4 ohm
ParameterFormulaValue
Single rod resistanceR1 = rho/(2 x pi x L) x ln(4L/d)39.6 ohm
Rods requiredn = R1 / (target x 0.8)13 rod(s) <= 4 ohm
Rod specdia x length20 mm x 2.5 m
This calculation book is illustrative it consolidates the computed values with the referenced standards. A licensed engineer must verify and seal final design documents for construction.
🔧 Secondary schematic (control & signal)
SECONDARY CONTROL & SIGNAL CIRCUIT0.4 kV circuit breaker close/trip + indication + interlock (TYPICAL)+control supplyCS (close)interlock52Cclose coil-TC (trip)prot trip52Ttrip coilSIGNAL (indication)52a (closed)REDbreaker closed-TYPICAL CIRCUITStandard control/signal scheme for Ward 1.Project detailing required (wiring, terminal assignment).
🔩 Terminal strip (typical)
TERMINAL STRIP (TYPICAL)X1 secondary wiring terminals (typical project detailing required)TerminalFunctionWireX1:1control supply L+1.5 mm2X1:2control supply L-1.5 mm2X1:3close command1.5 mm2X1:4trip command1.5 mm2X1:5breaker 52a status1.5 mm2X1:6breaker 52b status1.5 mm2X1:7trip circuit healthy1.5 mm2X1:8earth / shield2.5 mm2
🛡️ Redundancy & emergency power
ParameterValue
Building typeHospital
Design factor1× (life-safety + 100% medical load, no reduction)
Redundancy topology2N → 2 independent paths
Emergency levelcritical
ATSYes (dual-source transfer)
EPS (fire lighting)Yes (GB 51309)
Standby diesel gensetYes (GB 50016)
📏 Standard basis (依据标准)
TopicStandard
Standard basisIEC · IEC 60364-5-52
Conductor ampacityIEC 60364-5-52 Table B.52.2–B.52.5 (copper, 3 loaded conductors, 30°C ambient, PVC) — typical/rounded values, conservative (±3%)
Voltage-drop limitIEC 60364-5-52 Annex G · max drop 3%
Winding temp riseIEC 60076-11 — dry-type Class F 100 K rise
kVA ratingsIEC 60076-1 R10 preferred numbers
Breaker framesIEC 60947-2 frame sizes (In)
Grounding targetIEC 60364-5-54 earthing arrangements and protective conductors — LV earthing target ≤ 10 Ω (TN systems); 4 Ω used as a conservative design target · target 4 Ω
Power supply designGB 50052 — code for design of electric power supply systems (load classification)
Fire emergency lightingGB 51309 — technical standard for fire emergency lighting and evacuation indication
Building fire protectionGB 50016 — code for fire protection design of buildings
UPSIEC 62040 — UPS performance & test requirements (critical loads)
🧮 How it was calculated
1. Hospital: total load 1,500 kW × design factor 1 = 1,500 kW (explicit coincidence factor — life-safety + 100% medical load, no reduction)
2. Redundancy 2N → two independent power paths
3. Emergency level: critical → ATS, EPS (fire lighting), standby diesel genset
4. Loads: P=1,500 kW, PF 0.95, 13 circuits
5. Demand: 1,500 × 0.9 = 1,350 kW
6. PFC: Qc = 1,350 × (0.329 − 0.329) = 0 kVAR → 0 kVAR bank
7. Transformer: S = 1,350 ÷ 0.95 = 1421.1 kVA → 1,600 kVA standard
8. Loading: 1,421 ÷ 1,600 = 89% (good range)
9. Voltage regulation: 89% × 6% × sinφ ≈ 1.7% at full load
10. HV: In 92.4 A, Isc 28.9 kA → KYN28A-12-630-315
11. LV: In 2309 A, Isc 36.5 kA (Xfmr Z 6% + system 0.3%) → GGD-2500, 3 feeder panel(s)
12. Cable branch boxes: 3 × DFW-0.4 (1-in/4-out) for feeder grouping
13. Grounding: R₁ 39.6 Ω → 13 rod(s)
14. Main feeder: 5× 300 mm² · ΔU 0.90% — OK
Summary
Estimated total (FOB Qingdao, EXW) — priced equipment$310,667
📋 Design notes
Pricing basis: FOB Qingdao (EXW) equipment price. Freight, duty and installation are not included — add for landed economics.
Transformer loading: 89% at design demand — good range.
Short-circuit check: HV 28.9 kA vs 31.5 kA (1.1× margin) · LV 36.5 kA vs 50 kA (1.4× margin).
Voltage regulation: ≈ 1.7% at full load (typical limit 5%).
Copper price linkage: Copper-wound transformer price tracks LME copper (current $14,219/t · 2026-09-12 · LME Copper (Sina hf_CAD)).
Parallel conductors: Single-cable ampacity exceeded — parallel conductors specified: main feeder 5× 300 mm², branch trunk 1 2× 185 mm², branch trunk 2 2× 185 mm² (per IEC 60364-5-52 / GB 50054).
Cable & grounding pricing: Cable conductors and grounding are priced from the confirmed cables-trays-grounding price reference (per-metre copper YJV; aluminium remains POA). The main copper busbar is POA — its length is project-specific.
Busway (high-current feeders): For LV feeders above ~2500 A, a busway (母线槽) trunking system is recommended instead of parallel cables.
Design factor (explicit): Hospital applies a 1× design/coincidence factor to the entered load (life-safety + 100% medical load, no reduction) — entered 1,500 kW becomes 1,500 kW design load.
Redundancy: 2N topology — two independent paths, each sized for 100% load (fault-tolerant).
Emergency power: critical level: automatic transfer switch for dual source; EPS for fire/emergency lighting (GB 51309); standby diesel genset for life-safety loads (GB 50016).
Load classification: Hospitals and airports carry life-safety (first-class) loads requiring dual independent sources — GB 50052 classifies load by importance.
Hospital critical loads: Operating theatres and ICU need a medical IT isolated power supply (IEC 60364-7-710) and an online UPS; the fire pump has a dedicated feeder (GB 50016). These are included as separate line items for hospitals.
Pricing: ATS, EPS and standby diesel gensets are priced from the catalogue price reference; medical IT panels, OR UPS and fire pumps remain quoted per project (POA).

Cara perhitungannya

Cara perhitungan ukuran bekerja

Beban total adalah beban bangunan yang disesuaikan untuk pendinginan dan auxiliar. Transformator diukur pada faktor daya target; redundansi N+1 / 2N menetapkan jumlah unit paralel dan jalur independen. Tingkat darurat (dasar / standar / kritis) menentukan apakah ATS, EPS dan/atau generator diesel siaga ditambahkan.

Standar yang berlaku

Perhitungan ukuran mengacu pada GB 50052 (desain pasokan daya dan klasifikasi beban), GB 51309 (penerangan darurat kebakaran), GB 50016 (perlindungan kebakaran bangunan) dan IEC 62040 (UPS untuk beban kritis).

Pertanyaan yang sering diajukan

What redundancy do hospitals require for power supply?

Hospitals are first-class important loads under GB 50052 and need two independent utility supplies plus an emergency source (diesel or EPS) that restores critical circuits in seconds. Life-support and operating rooms use 2N topology with UPS. The calculator models building type, redundancy (N+1/2N) and emergency level to size the full plant.

How is emergency power restored in public buildings?

An automatic transfer switch (ATS) detects supply loss and transfers to a standby diesel generator, which starts and reaches full load in 30-60 seconds. For millisecond-critical loads, a UPS bridges the gap. GB 50052 classifies the emergency level; the calculator sizes ATS, diesel/EPS and battery backup per the building's load class.

What is the typical load density of a hospital or stadium?

Hospitals run 60-120 W/m2 (up to 150 W/m2 with imaging), schools 30-60 W/m2, offices 50-80 W/m2, and stadiums 60-100 W/m2 plus floodlighting peaks. The calculator's 1500 kW default models a mid-size hospital; total demand sets the Transformer and emergency ratings.

What transformer size does a 1500 kW hospital need?

A 1500 kW hospital at 0.95 pf needs about 1580 kVA, so select 2x800 kVA or 2x1000 kVA for N+1/2N redundancy. Hospitals often run two transformers with automatic bus-tie so either can carry critical load. The calculator selects standard IEC 60076 ratings and applies the chosen redundancy level.

What is an EPS and how does it differ from a UPS?

An emergency power supply (EPS) is an inverter-based backup for lighting and life-safety loads, transferring within 0.25-5 seconds — slower than a UPS (0-10 ms) but cheaper per kVA and built for motor and lighting duty. UPS serves electronics that cannot tolerate any interruption. The calculator selects EPS for emergency lighting and UPS for critical IT.

What power quality rules apply to public buildings?

Public buildings must limit harmonic distortion per IEEE 519 (5-8% THD at PCC) and maintain Power Factor above ~0.9 to avoid utility penalties. LED lighting and VFD HVAC drives inject Harmonics, so detuned capacitors or APFs are common. The calculator checks pf and harmonic share and sizes compensation accordingly.

Sematkan kalkulator ini

Salin kode iframe di bawah untuk menyematkan kalkulator ini di situs mana pun. Halaman sematan bersifat noindex dan menyesuaikan lebar apa pun.

Kalkulator terkait

Hasil adalah estimasi teknik untuk referensi. Desain akhir harus dikonfirmasi oleh insinyur lokal berlisensi terhadap kondisi lokasi dan kode yang berlaku. Harga adalah FOB Qingdao (EXW) dan tidak termasuk pengiriman, bea masuk, atau instalasi.

Send my complete design report

Get the full bill of materials, single-line diagram, calculation steps and FOB pricing as a PDF — free, no sign-up.

💬 Chat on WhatsApp

Your data stays private. No spam — only a reply to your enquiry.