Transformator QDTB®

Kalkulator Interkoneksi Pembangkit PV + Jaringan

Rancang interkoneksi pembangkit listrik tenaga surya berskala MW — tingkat tegangan, peningkatan gardu induk, kompensasi reaktif, kepatuhan terhadap peraturan jaringan listrik, dan keekonomian biaya penuh — dalam satu alat.

Mulai Menghitung

Rancang interkoneksi PV Anda

MW AC — drives the whole interconnection design.
Biarkan kosong untuk memperkirakan dari garis lintang
Economics (Module G)

Contoh referensi yang telah dihitung sebelumnya (dapat dirayapi, tidak memerlukan JavaScript). Masukkan parameter Anda sendiri di atas untuk desain langsung.

Example 1 — Contoh Pekerjaan — Pembangkit PV 50 MW, Interkoneksi 110 kV · FOB $9,400,000
PV Plant · 110 kV POI · 0.8 kV (inverter) → 35 kV (collector) → 110 kV (step-up) → 110 kV POI
63 MVA main transformer
40 arrays × 1600 kVA box sub · SVG 15 Mvar
Capacity
50 MW AC
Collector
7 feeder(s) · 95 mm²
P90 yield
54,994,346 kWh/yr
LCOE
$0.0793/kWh
Est. total (FOB)
⚡ Module A — Voltage level & interconnection
ParameterValue
Recommended POI voltage110 kV
Step-up chain0.8 kV (inverter) → 35 kV (collector) → 110 kV (step-up) → 110 kV POI
Basis> 30 MW: 110 kV interconnection with a step-up substation (typical utility-scale threshold).
🔌 Module B — Collector system
ParameterValue
Arrays / box substations40 × 1600 kVA (0.8/35 kV)
Collector feeders7 radial feeder(s) · 95 mm² YJV 35 kV
TopologyRadial collector (放射式)
🔩 Module C — Main transformer (step-up)
ParameterValue
Rating63 MVA 35/110 kV · YNd11
Impedance / coolingZ = 10.5% · ONAN/ONAF
Tap changerOn-load tap changer (OLTC) ±8×1.25%
StandardIEC 60076
🌀 Module D2 — Reactive power & voltage
ParameterValue
Dynamic reactive range±12.50 Mvar (25%)
CompensationSVG 15 Mvar + shunt reactor 2 Mvar
Cable charging1.74 Mvar (absorbed by shunt reactor)
StandardGB/T 29321-2026, GB/T 19964-2024
⚡ Module D4 — Short-circuit contribution
ParameterValue
Grid fault level10.50 kA at 110 kV
PV contribution (current-source)0.315 kA (1.2× rated)
Total POI fault level10.81 kA
✅ Module D3 — Grid-code compliance
RequirementStandardStatus
Low/High voltage ride-through (LVRT/HVRT)GB/T 19964-2024Design basis — configure inverter LVRT/HVRT curve
Frequency ride-through & primary frequency responseGB/T 19964-2024Design basis — enable frequency-watt / inertia response
Active power control (ramp rate / AGC-AVC)GB/T 19964-2024Design basis — plant controller with AGC/AVC
Reactive power capabilityGB/T 29321-2026, GB/T 19964-2024PASS — SVG 15 Mvar covers ±12.50 Mvar
Power quality (harmonics / flicker / unbalance)IEC 61000 / GB/T 14549Design basis — inverter THD < 5% (typical), verify at commissioning
Short-circuit contribution (PV inverter source)IEEE 1547 / IEC 60909PV contribution ≈ 0.31 kA (limited, current-source)
☀️ Module F — Generation (P50 / P75 / P90)
ParameterValue
GHI resource3.97 kWh/m²/day · PR 0.8
P50 yield57,962,000 kWh/yr
P75 yield56,399,344 kWh/yr
P90 yield54,994,346 kWh/yr (bankable)
30-yr total (with degradation)1,365,350,056 kWh
💰 Module G — Full-cost economics (LCOE)
ParameterValue
LCOE (full-cost)$0.0793/kWh
Simple payback17.1 yr
IRR / NPV2.3% / $-17,380,111
DSCR0.65
Interconnection cost (separate)$9,400,000 (substation + collector + transmission)
Substation (step-up + GIS + SVG + control)$6,300,000
Collector network (cable + routing)$1,600,000
Transmission line to POI$1,500,000
📦 Bill of Materials
EquipmentModelSpecQtyPriceSubtotal
PV Modules550 Wp Mono PERC550 Wp · 104546 pcs (DC/AC ≈ 1.15)104546
Central Inverter2.5 MW string/centralutility-scale · 50.0 MW AC20
Ground Mounting StructureFixed tilttilt optimized for lat 30°1
Box-Type Substation (step-up)0.8/35 kV1600 kVA step-up40
HV Switchgear (collector)KYN61-40.5collector switchgear · 7 feeders7
Main Transformer (step-up)SZ11-63MVA/110kV63 MVA 35/110 kV · YNd11 · OLTC1POA
SVG (Static Var Generator)SVG-15Mvar/110kVdynamic reactive compensation1POA
Shunt Reactor2 Mvarabsorb collector cable charging1POA
Collector CableYJV 26/35 kV95 mm² · radial feeders · 7 feeders7POA
Earthing Systemflat bar + rodsplant grounding grid1
SCADA Monitoringplant-levelpower plant controller + SCADA1
Estimated total (FOB Qingdao, EXW) — priced equipment
📏 Standard basis (依据标准)
TopicStandard
Standard basisGB (China)
Grid interconnectionGB/T 19964-2024
Reactive power compensationGB/T 29321-2026 · GB/T 19964-2024
Power quality (harmonics / flicker)IEC 61000 · GB/T 14549
Short-circuitIEC 60909
Power transformerIEC 60076
HV switchgearIEC 62271
Cable ampacityIEC 60287
Earthing designGB/T 50065
📐 Single-line diagram (with POI)
POI (Point of Interconnection)Utility GridCTCT110 kV POI breaker50/5151NkWhmeteringMain transformer63 MVA 35/110 kVSZ11 - YNd11OLTC - ONAN/ONAFSVG 15 MvarShunt reactor 2 Mvar35 kV collector busPTPTSPDCollector feeder 1YJV 35 kV (radial)Collector feeder 2YJV 35 kV (radial)Collector feeder 3YJV 35 kV (radial)Collector feeder 4YJV 35 kV (radial)Collector feeder 5YJV 35 kV (radial)Collector feeder 6YJV 35 kV (radial)Collector feeder 7YJV 35 kV (radial)Box sub1600 kVABox sub1600 kVABox sub1600 kVABox sub1600 kVABox sub1600 kVABox sub1600 kVA + 34 more box substations (40 arrays total)PV array + string inverter0.8 kV DC/AC
LEGENDBreaker (52)CTCT (current transformer)PTPT (voltage transformer)50/51Protection relay 50/51/51NkWhMeter (kWh)SPD (surge protection)
⚙️ Electrical schematic (protection & metering)
ELECTRICAL SCHEMATIC - PROTECTION & METERING110 kV / 35 kV - 63000 kVA - secondary circuits (schematic)INCOMING 110 kVCT270/5Aprotection CT5250/5151N87overcurrent / earth-fault / diffPT110kV/100Vbus PT (voltage)TRANSFORMER63000 kVAZ = 10.5%kWhrevenue meteringLV 5235 kV LV BUSSPDCT.../5ACollector 1 - 37 A50/51CT.../5ACollector 2 - 37 A50/51CT.../5ACollector 3 - 37 A50/51CT.../5ACollector 4 - 37 A50/51CT.../5ACollector 5 - 37 A50/51CT.../5ACollector 6 - 37 A50/51CT.../5ACollector 7 - 37 A50/51
⛳ Grounding grid layout
SUBSTATION GROUNDING GRID LAYOUTsite 150 m x 100 m - ring earth electrode (schematic)PV SUBSTATIONR1R2R3R4R5R6R7R8R9R10R11R12R13R14R15R16R17R18R19R20R21R22R23R24R25R26R27R28R29R30R31R32R33R34R35R36R37R38R39R40R41R42R43R44R45R46R47R48R49R50R51R52R53R54R55R56R57R58R59R60R61R62R63R64R65R66R67R68R69R70R71R72R73R74R75R76R77R78R79R80R81R82R83R84R85R86R87R88R89R90R91R92R93R94R95R96R97R98R99R100150 mGround rods: 100 x dia 16 mm x 2.5 m copper-bonded steelRod spacing: 5 m (= 2 x rod length, ring electrode)Target resistance: <= 4 ohm (measure after installation)Standard: IEEE 80 / GB-T 50065 (earthing design) - indicative layout
🔌 Cable schedule & routing
CABLE SCHEDULE - PV INTERCONNECTIONIDFromToCable (model / spec)LengthC1Array box sub35 kV swgr95 mm2 YJV 35 kV10000 mC2Array box sub35 kV swgr95 mm2 YJV 35 kV10000 mC3Array box sub35 kV swgr95 mm2 YJV 35 kV10000 mC4Array box sub35 kV swgr95 mm2 YJV 35 kV10000 mC5Array box sub35 kV swgr95 mm2 YJV 35 kV10000 mC6Array box sub35 kV swgr95 mm2 YJV 35 kV10000 mC7Array box sub35 kV swgr95 mm2 YJV 35 kV10000 mPOIMain transformer110 kV POI110 kV XLPE20000 mROUTING (schematic)LV PANELL1L2L3L4L5L6L7L8Cable lengths are indicative (run-length based); confirm on site before installation.
🗄 Switchgear arrangement
SWITCHGEAR ARRANGEMENT - PV SUBSTATIONpanel lineup (front view, schematic)CB1collector feederCB2collector feederCB3collector feederCB4collector feederCB5collector feederCB6collector feederT163 MVAPOI110 kV8 panel(s) - each 90 mm (typical)Clearance / aisle per IEC 61936-1 - layout indicative
🛡 Protection configuration
PROTECTION CONFIGURATION - PV PLANT50000 kWp - 40 strings - protection zones (schematic)PV ARRAY 50000 kWpFDC fuse 20 A / stringDC SPD (Type 2)INV50000 kW50/51 + anti-islanding52 - 262 A - 110000 VSTEP-UP 63000 kVA8749differential + thermal50/51HV overcurrent52GRID (POI)110 kV POIearthingProtection layout is schematic / illustrative final settings per IEC 60255 / IEEE 1547 / IEC 60364.
📋 Protection settings
CircuitProtectionSettingTimeStandard
Collector feeder50/51 overcurrent45 A0.1 sIEC 60255-151
Main transformer 63 MVA87 differential0.2 x CTinstIEEE C37.91 / GB/T 14285
Main transformer 63 MVA50/51 overcurrent315 A0.3 sIEC 60255-151
Main transformer 63 MVA49 thermal100% ratedalarm 90%IEC 60076-7 / IEEE C57.91
POI 110 kVanti-islanding / ROCOFper grid codeper grid codeGB/T 19964-2024
PV fault contributionnotecurrent-limited ( 1.2x)-IEEE 1547 / IEC 60909
Settings are illustrative starting points — confirm with a protection coordination study per IEC 60255 / IEEE 242.
📚 Calculation book
CALCULATION BOOK
PV interconnection - 50.0 MW - 110 kV POI - illustrative
1. Voltage level & POI
Standard: GB/T 19964-2024
ParameterFormulaValue
Point of interconnectionvoltage chain110 kV (0.8 kV (inverter) -> 35 kV (collector) -> 110 kV (step-up) -> 110 kV POI)
AC capacityPac50.0 MW
POI currentI = P / (sqrt(3) x V)262 A
2. Collector system
Standard: IEC 60287 (cable ampacity)
ParameterFormulaValue
ArraysnArrays40 arrays x 1600 kVA box sub
FeedersnFeeders7 feeder(s) - 95 mm2 cable
3. Main transformer
Standard: IEC 60076
ParameterFormulaValue
RatingMVA63 MVA - YNd11
ImpedanceZ%10.5%
4. Reactive power
Standard: GB/T 29321-2026, GB/T 19964-2024
ParameterFormulaValue
RequirementQ = x% of Pac 25% -> 12.50 Mvar
CompensationSVG / shuntSVG 15 Mvar + shunt 2 Mvar
5. Short-circuit
Standard: IEC 60909
ParameterFormulaValue
Grid contributionIsc_grid10.50 kA
PV contributionIsc_pv (current-source)0.31 kA
TotalIsc = grid + PV10.81 kA at 110 kV
6. Generation & economics
Standard: IEC 61724 / NREL ATB
ParameterFormulaValue
P50 yieldGHI x PR57,962,000 kWh/yr
P90 (bankable)P50 x (1-1.282 )54,994,346 kWh/yr
LCOEfull-cost$0.0793/kWh
This calculation book is illustrative it consolidates the computed results with the referenced standards. A licensed engineer and the grid operator must verify final interconnection design.
🔧 Secondary schematic (control & signal)
SECONDARY CONTROL & SIGNAL CIRCUIT35 kV circuit breaker close/trip + indication + interlock (TYPICAL)+control supplyCS (close)interlock52Cclose coil-TC (trip)prot trip52Ttrip coilSIGNAL (indication)52a (closed)REDbreaker closed-TYPICAL CIRCUITStandard control/signal scheme for COLLECTOR FEEDER 1.Project detailing required (wiring, terminal assignment).
🔩 Terminal strip (typical)
TERMINAL STRIP (TYPICAL)X1 secondary wiring terminals (typical project detailing required)TerminalFunctionWireX1:1control supply L+1.5 mm2X1:2control supply L-1.5 mm2X1:3close command1.5 mm2X1:4trip command1.5 mm2X1:5breaker 52a status1.5 mm2X1:6breaker 52b status1.5 mm2X1:7trip circuit healthy1.5 mm2X1:8earth / shield2.5 mm2
🧮 How it was calculated
1. Voltage level (Module A): 50.0 MW → 110 kV POI (0.8 kV (inverter) → 35 kV (collector) → 110 kV (step-up) → 110 kV POI)
2. Collector (Module B): 40 arrays × 1600 kVA box sub · 7 feeder(s) · 95 mm² cable
3. Main transformer (Module C): 63 MVA YNd11 · Z=10.5% · ONAN/ONAF
4. Reactive power (Module D2): requirement ±12.50 Mvar → SVG 15 Mvar + shunt reactor 2 Mvar
5. Short-circuit (Module D4): grid 10.50 kA + PV 0.31 kA (current-source) = 10.81 kA at 110 kV POI
6. Generation (Module F): GHI 3.97 kWh/m²/day · PR 0.8 → P50 57,962,000 kWh/yr
7. Probability (Module F): P75 56,399,344 · P90 54,994,346 kWh/yr (σ=4% interannual)
8. LCOE (Module G): $0.0793/kWh full-cost (O&M + WACC + inverter replacement + degradation)
9. Economics (Module G): payback 17.1 yr · IRR 2.3% · NPV $-17,380,111 · DSCR 0.65
Example 2 — Contoh — Pembangkit PV 10 MW, Interkoneksi 35 kV · FOB $640,000
PV Plant · 35 kV POI · 0.8 kV (inverter) → 35 kV (collector) → 35 kV POI
35 kV direct interconnection
8 arrays × 1600 kVA box sub · SVG 2 Mvar
Capacity
10 MW AC
Collector
2 feeder(s) · 70 mm²
P90 yield
13,993,775 kWh/yr
LCOE
$0.0541/kWh
Est. total (FOB)
⚡ Module A — Voltage level & interconnection
ParameterValue
Recommended POI voltage35 kV
Step-up chain0.8 kV (inverter) → 35 kV (collector) → 35 kV POI
Basis6–30 MW: 35 kV interconnection (typical regional PV threshold).
🔌 Module B — Collector system
ParameterValue
Arrays / box substations8 × 1600 kVA (0.8/35 kV)
Collector feeders2 radial feeder(s) · 70 mm² YJV 35 kV
TopologyRadial collector (放射式)
🔩 Module C — Main transformer (step-up)
ParameterValue
No separate main transformer — collector voltage connects directly to the POI.
🌀 Module D2 — Reactive power & voltage
ParameterValue
Dynamic reactive range±2.00 Mvar (20%)
CompensationSVG 2 Mvar
Cable charging0.56 Mvar (absorbed by shunt reactor)
StandardGB/T 29321-2026, GB/T 19964-2024
⚡ Module D4 — Short-circuit contribution
ParameterValue
Grid fault level16.50 kA at 35 kV
PV contribution (current-source)0.198 kA (1.2× rated)
Total POI fault level16.69 kA
✅ Module D3 — Grid-code compliance
RequirementStandardStatus
Low/High voltage ride-through (LVRT/HVRT)GB/T 19964-2024Design basis — configure inverter LVRT/HVRT curve
Frequency ride-through & primary frequency responseGB/T 19964-2024Design basis — enable frequency-watt / inertia response
Active power control (ramp rate / AGC-AVC)GB/T 19964-2024Design basis — plant controller with AGC/AVC
Reactive power capabilityGB/T 29321-2026, GB/T 19964-2024PASS — SVG 2 Mvar covers ±2.00 Mvar
Power quality (harmonics / flicker / unbalance)IEC 61000 / GB/T 14549Design basis — inverter THD < 5% (typical), verify at commissioning
Short-circuit contribution (PV inverter source)IEEE 1547 / IEC 60909PV contribution ≈ 0.20 kA (limited, current-source)
☀️ Module F — Generation (P50 / P75 / P90)
ParameterValue
GHI resource5.05 kWh/m²/day · PR 0.8
P50 yield14,748,920 kWh/yr
P75 yield14,351,289 kWh/yr
P90 yield13,993,775 kWh/yr (bankable)
30-yr total (with degradation)347,424,843 kWh
💰 Module G — Full-cost economics (LCOE)
ParameterValue
LCOE (full-cost)$0.0541/kWh
Simple payback10.9 yr
IRR / NPV6.9% / $-618,878
DSCR1.03
Interconnection cost (separate)$640,000 (substation + collector + transmission)
Substation (step-up + GIS + SVG + control)$0
Collector network (cable + routing)$640,000
Transmission line to POI$0
📦 Bill of Materials
EquipmentModelSpecQtyPriceSubtotal
PV Modules550 Wp Mono PERC550 Wp · 20910 pcs (DC/AC ≈ 1.15)20910
Central Inverter2.5 MW string/centralutility-scale · 10.0 MW AC4
Ground Mounting StructureFixed tilttilt optimized for lat 6.5°1
Box-Type Substation (step-up)0.8/35 kV1600 kVA step-up8
HV Switchgear (collector)KYN61-40.5collector switchgear · 2 feeders2
SVG (Static Var Generator)SVG-2Mvar/35kVdynamic reactive compensation1POA
Collector CableYJV 26/35 kV70 mm² · radial feeders · 2 feeders2POA
Earthing Systemflat bar + rodsplant grounding grid1
SCADA Monitoringplant-levelpower plant controller + SCADA1
Estimated total (FOB Qingdao, EXW) — priced equipment
📏 Standard basis (依据标准)
TopicStandard
Standard basisGB (China)
Grid interconnectionGB/T 19964-2024
Reactive power compensationGB/T 29321-2026 · GB/T 19964-2024
Power quality (harmonics / flicker)IEC 61000 · GB/T 14549
Short-circuitIEC 60909
Power transformerIEC 60076
HV switchgearIEC 62271
Cable ampacityIEC 60287
Earthing designGB/T 50065
📐 Single-line diagram (with POI)
POI (Point of Interconnection)Utility GridCTCT35 kV POI breaker50/5151NkWhmetering35 kV collector busPTPTSPDCollector feeder 1YJV 35 kV (radial)Collector feeder 2YJV 35 kV (radial)Box sub1600 kVABox sub1600 kVABox sub1600 kVABox sub1600 kVABox sub1600 kVABox sub1600 kVA + 2 more box substations (8 arrays total)PV array + string inverter0.8 kV DC/AC
LEGENDBreaker (52)CTCT (current transformer)PTPT (voltage transformer)50/51Protection relay 50/51/51NkWhMeter (kWh)SPD (surge protection)
⚙️ Electrical schematic (protection & metering)
ELECTRICAL SCHEMATIC - PROTECTION & METERING35 kV / 35 kV - 1600 kVA - secondary circuits (schematic)INCOMING 35 kVCT170/5Aprotection CT5250/5151Novercurrent / earth-faultPT35kV/100Vbus PT (voltage)TRANSFORMER1600 kVAZ = 6%kWhrevenue meteringLV 5235 kV LV BUSSPDCT.../5ACollector 1 - 82 A50/51CT.../5ACollector 2 - 82 A50/51
⛳ Grounding grid layout
SUBSTATION GROUNDING GRID LAYOUTsite 30 m x 20 m - ring earth electrode (schematic)PV SUBSTATIONR1R2R3R4R5R6R7R8R9R10R11R12R13R14R15R16R17R18R19R2030 mGround rods: 20 x dia 16 mm x 2.5 m copper-bonded steelRod spacing: 5 m (= 2 x rod length, ring electrode)Target resistance: <= 4 ohm (measure after installation)Standard: IEEE 80 / GB-T 50065 (earthing design) - indicative layout
🔌 Cable schedule & routing
CABLE SCHEDULE - PV INTERCONNECTIONIDFromToCable (model / spec)LengthC1Array box sub35 kV swgr70 mm2 YJV 35 kV2000 mC2Array box sub35 kV swgr70 mm2 YJV 35 kV2000 mPOI35 kV swgr35 kV POI35 kV XLPE4000 mROUTING (schematic)LV PANELL1L2L3Cable lengths are indicative (run-length based); confirm on site before installation.
🗄 Switchgear arrangement
SWITCHGEAR ARRANGEMENT - PV SUBSTATIONpanel lineup (front view, schematic)CB1collector feederCB2collector feederPOI35 kV3 panel(s) - each 213 mm (typical)Clearance / aisle per IEC 61936-1 - layout indicative
🛡 Protection configuration
PROTECTION CONFIGURATION - PV PLANT10000 kWp - 8 strings - protection zones (schematic)PV ARRAY 10000 kWpFDC fuse 20 A / stringDC SPD (Type 2)INV10000 kW50/51 + anti-islanding52 - 165 A - 35000 VSTEP-UP 1600 kVA8749differential + thermal50/51HV overcurrent52GRID (POI)35 kV POIearthingProtection layout is schematic / illustrative final settings per IEC 60255 / IEEE 1547 / IEC 60364.
📋 Protection settings
CircuitProtectionSettingTimeStandard
Collector feeder50/51 overcurrent99 A0.1 sIEC 60255-151
POI 35 kVanti-islanding / ROCOFper grid codeper grid codeGB/T 19964-2024
PV fault contributionnotecurrent-limited ( 1.2x)-IEEE 1547 / IEC 60909
Settings are illustrative starting points — confirm with a protection coordination study per IEC 60255 / IEEE 242.
📚 Calculation book
CALCULATION BOOK
PV interconnection - 10.0 MW - 35 kV POI - illustrative
1. Voltage level & POI
Standard: GB/T 19964-2024
ParameterFormulaValue
Point of interconnectionvoltage chain35 kV (0.8 kV (inverter) -> 35 kV (collector) -> 35 kV POI)
AC capacityPac10.0 MW
POI currentI = P / (sqrt(3) x V)165 A
2. Collector system
Standard: IEC 60287 (cable ampacity)
ParameterFormulaValue
ArraysnArrays8 arrays x 1600 kVA box sub
FeedersnFeeders2 feeder(s) - 70 mm2 cable
3. Main transformer
Standard: IEC 60076
ParameterFormulaValue
RatingMVAnone (direct collector to POI)
ImpedanceZ%-
4. Reactive power
Standard: GB/T 29321-2026, GB/T 19964-2024
ParameterFormulaValue
RequirementQ = x% of Pac 20% -> 2.00 Mvar
CompensationSVG / shuntSVG 2 Mvar
5. Short-circuit
Standard: IEC 60909
ParameterFormulaValue
Grid contributionIsc_grid16.50 kA
PV contributionIsc_pv (current-source)0.20 kA
TotalIsc = grid + PV16.69 kA at 35 kV
6. Generation & economics
Standard: IEC 61724 / NREL ATB
ParameterFormulaValue
P50 yieldGHI x PR14,748,920 kWh/yr
P90 (bankable)P50 x (1-1.282 )13,993,775 kWh/yr
LCOEfull-cost$0.0541/kWh
This calculation book is illustrative it consolidates the computed results with the referenced standards. A licensed engineer and the grid operator must verify final interconnection design.
🔧 Secondary schematic (control & signal)
SECONDARY CONTROL & SIGNAL CIRCUIT35 kV circuit breaker close/trip + indication + interlock (TYPICAL)+control supplyCS (close)interlock52Cclose coil-TC (trip)prot trip52Ttrip coilSIGNAL (indication)52a (closed)REDbreaker closed-TYPICAL CIRCUITStandard control/signal scheme for COLLECTOR FEEDER 1.Project detailing required (wiring, terminal assignment).
🔩 Terminal strip (typical)
TERMINAL STRIP (TYPICAL)X1 secondary wiring terminals (typical project detailing required)TerminalFunctionWireX1:1control supply L+1.5 mm2X1:2control supply L-1.5 mm2X1:3close command1.5 mm2X1:4trip command1.5 mm2X1:5breaker 52a status1.5 mm2X1:6breaker 52b status1.5 mm2X1:7trip circuit healthy1.5 mm2X1:8earth / shield2.5 mm2
🧮 How it was calculated
1. Voltage level (Module A): 10.0 MW → 35 kV POI (0.8 kV (inverter) → 35 kV (collector) → 35 kV POI)
2. Collector (Module B): 8 arrays × 1600 kVA box sub · 2 feeder(s) · 70 mm² cable
3. Main transformer (Module C): none (collector connects directly to POI)
4. Reactive power (Module D2): requirement ±2.00 Mvar → SVG 2 Mvar
5. Short-circuit (Module D4): grid 16.50 kA + PV 0.20 kA (current-source) = 16.69 kA at 35 kV POI
6. Generation (Module F): GHI 5.05 kWh/m²/day · PR 0.8 → P50 14,748,920 kWh/yr
7. Probability (Module F): P75 14,351,289 · P90 13,993,775 kWh/yr (σ=4% interannual)
8. LCOE (Module G): $0.0541/kWh full-cost (O&M + WACC + inverter replacement + degradation)
9. Economics (Module G): payback 10.9 yr · IRR 6.9% · NPV $-618,878 · DSCR 1.03

Bagaimana cara menghitungnya

· Voltage level (A): capacity → 10/35/110 kV POI by typical threshold (≤6 / 6–30 / >30 MW).

· Main transformer (C): MVA = P/0.95 × 1.1 → next standard; vector group YNd11, OLTC (IEC 60076).

· Reactive (D2): dynamic range ±(15–25)% of rating → SVG; shunt reactor absorbs cable/OHL charging (GB/T 29321-2026).

· PV short-circuit (D4): inverter current-source contribution ≈ 1.2 × rated (IEEE 1547 / IEC 60909).

· Generation (F): P50 = PAC × GHI × 365 × PR; P75/P90 = P50 × (1 − 0.674σ / 1.28σ), σ = 4%.

· LCOE (G): full-cost = (CAPEX + Σ(O&M + inverter replacement) discounted) ÷ Σ(generation discounted), WACC discounting, degradation included.

Standar yang direferensikan

StandardScope
GB/T 19964光伏发电站接入电力系统技术规定 — PV power-station grid interconnection technical requirements: voltage/frequency ride-through, active-power control, reactive-power capability and power-quality limits at the point of interconnection.
GB/T 29321-2026光伏发电站无功补偿技术规范 — Reactive-power compensation for PV power stations — dynamic reactive range and compensation equipment (SVG, shunt reactor/capacitor).
GB/T 50065交流电气装置的接地设计规范 — Earthing design for AC electrical installations, including substation grounding grids and step/touch voltage verification.
GB/T 14549电能质量 公用电网谐波 — Harmonic current limits for equipment connected to the public supply network.
IEC 60076Power transformers — Power-transformer ratings, impedance, vector groups, tap-changers and cooling (basis for main-transformer selection).
IEC 62271High-voltage switchgear and controlgear — HV switchgear ratings — breaking current, busbar and GIS/AIS (basis for collector/substation switchgear).
IEC 60287Electric cables — calculation of the current rating — Cable ampacity calculation (basis for collector cable sizing).
IEC 60364Low-voltage electrical installations — LV installation and protection requirements.
IEC 60909Short-circuit currents in three-phase AC systems — Short-circuit current calculation (basis for POI fault level and protection grading).
IEC 61727Photovoltaic (PV) systems — characteristics of the utility interface — PV utility-interface characteristics, including power quality and protection requirements.
IEC 61000Electromagnetic compatibility (EMC) — EMC and power-quality (harmonics/flicker) limits.
IEEE 1547Standard for interconnection and interoperability of distributed energy resources — DER interconnection requirements: voltage/frequency ride-through, power control and anti-islanding.
EN 50549Requirements for generating plants connected in parallel with distribution networks — European grid-code requirements for generating plants at the distribution level.
VDE-AR-N 4105/4110/4120German technical connection rules (low / medium / high voltage) — German grid-connection codes for generators at LV/MV/HV.
SGCC 接入设计深度规定国网《光伏发电站接入系统设计内容深度规定》 — State Grid Corporation of China regulation on the required depth/content of PV power-station interconnection-system design.

Pertanyaan yang sering diajukan

At what voltage should a PV plant connect to the grid?

Connection voltage follows plant size: under ~250 kW use 0.4 kV, 250 kW-6 MW use 10 kV, and above 6 MW use 35 kV or 110 kV. A 50 MW plant typically connects at 110 kV. The choice balances Transformer losses against interconnection cost; grid operators specify the exact point of connection. The calculator selects voltage and main-transformer rating automatically.

How much reactive compensation does a PV plant need?

Grid codes (GB/T 19964, IEEE 1547) require PV inverters to operate within a 0.95 leading to 0.95 lagging power-factor range and often to supply reactive support during faults. Large plants usually add a centralized SVG/SVC of 10-30% of plant capacity. A 50 MW plant commonly pairs a 10-15 Mvar dynamic compensator to meet grid-code voltage support.

What short-circuit contribution does a PV inverter add?

A grid-following PV inverter contributes roughly 1.0-1.2 times its rated current for a few cycles, far less than a synchronous generator (5-7 times rated). For a 50 MW plant the contribution is ~60-70 MVA. This matters when checking breaker and transformer fault ratings; the calculator folds PV short-circuit contribution into the interconnection study.

What is the typical collector system voltage in a PV plant?

Large PV plants gather strings through 800 V DC to central or string inverters, then step up through a 0.8 kV to 10 kV or 35 kV collector network. String inverters (up to 250 kW) feed a 10 kV collector; central inverters (500 kW-3 MW) feed 35 kV. Collector cable runs are typically 5-20 km, sized for under 2% voltage drop.

How is the main transformer sized for a PV plant?

The main transformer rating matches inverter AC capacity divided by Power Factor, with 5-10% margin and the next standard size (IEC 60076). A 50 MWac plant with 0.95 pf needs roughly 55 MVA, so select 63 MVA. Most PV main transformers are oil-immersed, ONAN, 35/110 kV, with a No-Load Loss limit set by GB/T 6451 efficiency grades.

What grid-code compliance checks does interconnection require?

Key checks per GB/T 19963/19964 and IEEE 1547 include: low/high-voltage ride-through, frequency ride-through (typically 47.5-51.5 Hz), power-factor capability, ramp-rate limits, and anti-islanding. The calculator verifies voltage-level fit, main-transformer sizing, reactive compensation and fault contribution, flagging parameters that fall outside the typical grid-code envelope.

Sematkan kalkulator ini

Tambahkan kalkulator interkoneksi PV ini ke situs Anda — tautan atribusi membuat teks tautan tetap bervariasi.

Kalkulator terkait

Referensi desain dan perkiraan harga (FOB Qingdao, EXW) hanya untuk perencanaan awal — bukan penawaran akhir. Konfirmasikan desain dengan teknisi lokal berlisensi terhadap kode jaringan yang berlaku.

Send my complete design report

Get the full bill of materials, single-line diagram, calculation steps and FOB pricing as a PDF — free, no sign-up.

💬 Chat on WhatsApp

Your data stays private. No spam — only a reply to your enquiry.