Transformator QDTB®

Kalkulator Sistem Tenaga Infrastruktur Perkotaan

Rancang distribusi tenaga untuk infrastruktur perkotaan — penerangan jalan dan terowongan, jembatan/terowongan, pemompaan, dan beban pengisian EV, dengan gardu beton prefabrikasi, ring main unit SF6, dan distribusi tegangan rendah.

Mulai Menghitung Solusi Infrastruktur Perkotaan
Pemantauan dan kontrol cerdas
Tambahkan lapisan proteksi, pengukuran, dan SCADA ke BOM dan diagram arsitektur.

Mengapa kalkulator ini

Jaringan perkotaan bersifat kompak, rendah kebisingan, dan sangat andal. Kalkulator ini mengagregasi beban kota, menerapkan faktor simultanitas, dan mengukur gardu prefabrikasi (box) dengan ring main unit SF6 terintegrasi plus jaringan ring sesuai GB 50052, CJJ 45, dan GB 50054.

Worked Examples

Example 1 — Urban Ring Network (Lighting + Pumping + EV Charging) · FOB $897,825
Urban infrastructure power system · 12kV/0.4kV · dispersed
1,250 kVA box substation
YB-S13-1250/12 · demand 1,085 kW · SF6 ring main
Connected load
1,550 kW
Demand (Kd 0.7)
1,085 kW
Box substations
2 node(s)
Ring main units
2 × SF6
Est. total (FOB)
POA
📦 Bill of Materials
EquipmentModelSpecQty
Main substationYB-S13-1250/121250 kVA · Box-Type · oil internal · S131
LV feeder panelGGD-2000distributes 10 circuits1
PFC capacitor bank200 kVARautomatic · GCK LV cabinet1
Series reactor (detuned)CKSG-12.0/0.412.0 kVAR · 6% · 0.4 kV1
Main feeder cable (TX→LV)YJV 0.6/1kV 300 mm² ×44× 300 mm² Cu · ΔU 5.86% @ 400 m ⚠ · $154.0/m4
Feeder cable — Zone feeder 1 (×10)YJV 300 mm²300 mm² Cu · 249 A · ΔU 3.2% ⚠ · $154.0/m10
Main busbar (Cu)Cu 100×10100×10 · 2000 A rating · ref $118/mincluded
Grounding electrodeΦ20mm × 2.5m rodR₁ 39.6 Ω → 13 rod(s) ≤ 4 Ω13
Ring main unit (SF6, 环网柜)XGN15-1212 kV · SF6 · 3-way · ring main connection2
Pole-mounted switchgear (柱上开关)ZW32-12 / FZW28-1212 kV · pole-mounted vacuum load-break switch · overhead MV sectioning1
EV charging stations (充电桩)500 kW totalAC/DC charging piles · dedicated feeders1
Lighting control cabinet (照明控制柜)street/tunnel lightingtime + photo-electric control · energy metering1
Tunnel ventilation fan feeder (隧道风机)150 kWtunnel/bridge ventilation fan supply1
📐 Single-line diagram
CTCT 70/5APTPT 12kV/100V50/5151NHV incomingKYN28A-12-630-25630 A / 25 kA - vacuumYB-S13-1250/121250 kVAkWhmeteringLV incomingGGD-20000.4 kV LV busbar100x10 Cu - 2000 ASPDPFC 200 kVAR+ detuned reactorLV feeder panel x1 - 10 circuitsZone feeder 1 - 249 AYJV 300 mm2Zone feeder 2 - 249 AYJV 300 mm2Zone feeder 3 - 249 AYJV 300 mm2Zone feeder 4 - 249 AYJV 300 mm2Zone feeder 5 - 249 AYJV 300 mm2Zone feeder 6 - 249 AYJV 300 mm2Zone feeder 7 - 249 AYJV 300 mm2Zone feeder 8 - 249 AYJV 300 mm2Zone feeder 9 - 249 AYJV 300 mm2Zone feeder 10 - 249 AYJV 300 mm2Grounding 13xdia20mmx2.5m rod
LEGENDBreaker (52)DisconnectorCTCT (current transformer)PTPT (voltage transformer)50/51Protection relay 50/51/51N/87kWhMeter (kWh)SPD (surge protection)Transformer
⚙️ Electrical schematic (protection & metering)
ELECTRICAL SCHEMATIC - PROTECTION & METERING12 kV / 0.4 kV - 1250 kVA - secondary circuits (schematic)INCOMING 12 kVCT70/5Aprotection CT5250/5151Novercurrent / earth-faultPT12kV/100Vbus PT (voltage)BOX SUB1250 kVAZ = 4%kWhrevenue meteringLV 520.4 kV LV BUSSPDPFC200 kvarCT.../5AZone feeder 1 - 249 A50/51CT.../5AZone feeder 2 - 249 A50/51CT.../5AZone feeder 3 - 249 A50/51CT.../5AZone feeder 4 - 249 A50/51CT.../5AZone feeder 5 - 249 A50/51CT.../5AZone feeder 6 - 249 A50/51CT.../5AZone feeder 7 - 249 A50/51CT.../5AZone feeder 8 - 249 A50/51CT.../5AZone feeder 9 - 249 A50/51CT.../5AZone feeder 10 - 249 A50/51
⛳ Grounding grid layout
SUBSTATION GROUNDING GRID LAYOUTsite 12 m x 8 m - ring earth electrode (schematic)TRANSFORMERR1R2R3R4R5R6R7R8R9R10R11R12R1312 mGround rods: 13 x dia 20 mm x 2.5 m copper-bonded steelRod spacing: 5 m (= 2 x rod length, ring electrode)Target resistance: <= 4 ohm (measure after installation)Standard: IEEE 80 / GB-T 50065 (earthing design) - indicative layout
🔌 Cable schedule & routing
CABLE SCHEDULEIDFromToCable (model / spec)LengthC0TransformerLV panelYJV 0.6/1kV 300 mm2 (1804 A)400 mC1LV panelZone feeder 1YJV 300 mm2 (249 A)400 mC2LV panelZone feeder 2YJV 300 mm2 (249 A)400 mC3LV panelZone feeder 3YJV 300 mm2 (249 A)400 mC4LV panelZone feeder 4YJV 300 mm2 (249 A)400 mC5LV panelZone feeder 5YJV 300 mm2 (249 A)400 mC6LV panelZone feeder 6YJV 300 mm2 (249 A)400 mC7LV panelZone feeder 7YJV 300 mm2 (249 A)400 mC8LV panelZone feeder 8YJV 300 mm2 (249 A)400 mC9LV panelZone feeder 9YJV 300 mm2 (249 A)400 mC10LV panelZone feeder 10YJV 300 mm2 (249 A)400 mROUTING (schematic)LV PANELL1L2L3L4L5L6L7L8... +3 feedersCable lengths are indicative (run-length based); confirm on site before installation.
🗄 Switchgear arrangement
SWITCHGEAR ARRANGEMENTpanel lineup (front view, schematic)FEEDERGGD-2000PFC200 kvar2 panel(s) - each 320 mm (typical)Clearance / aisle per IEC 61936-1 - layout indicative
🛡 Protection configuration
PROTECTION CONFIGURATION12 kV / 0.4 kV - 1250 kVA - protection zones (schematic)INCOMING 12 kVCTCT 75/5A505151Novercurrent / earth-fault52TRANSFORMER1250 kVA - Z=4%49thermal overloadCTCT 2000/5A505151NLV incoming protection520.4 kV LV BUSCTCT 250/5A50/5151NZone feeder 1249 ACTCT 250/5A50/5151NZone feeder 2249 ACTCT 250/5A50/5151NZone feeder 3249 ACTCT 250/5A50/5151NZone feeder 4249 ACTCT 250/5A50/5151NZone feeder 5249 ACTCT 250/5A50/5151NZone feeder 6249 ACTCT 250/5A50/5151NZone feeder 7249 ACTCT 250/5A50/5151NZone feeder 8249 ACTCT 250/5A50/5151NZone feeder 9249 ACTCT 250/5A50/5151NZone feeder 10249 AProtection layout & CT ratios are schematic / illustrative final settings per IEC 60255 / IEEE 242.
📋 Protection settings
CircuitProtectionSettingTimeStandard
Transformer 1250 kVA49 thermal overload91% of ratedalarm/tripIEC 60076-7 / IEEE C57.91
LV incoming 0.4 kV50 instantaneous14434 AinstIEC 60947-2
LV incoming 0.4 kV51 overcurrent2165 A0.3 sIEC 60947-2 / IEC 60255
LV incoming 0.4 kV51N earth-fault361 A0.3 sIEC 60364-4-41
Zone feeder 150/51/51N (MCCB)Ir 273 A - Im 1989 A - Ig 50 A0.1 s (grading)IEC 60947-2 / IEC 60255
Zone feeder 250/51/51N (MCCB)Ir 273 A - Im 1989 A - Ig 50 A0.1 s (grading)IEC 60947-2 / IEC 60255
Zone feeder 350/51/51N (MCCB)Ir 273 A - Im 1989 A - Ig 50 A0.1 s (grading)IEC 60947-2 / IEC 60255
Zone feeder 450/51/51N (MCCB)Ir 273 A - Im 1989 A - Ig 50 A0.1 s (grading)IEC 60947-2 / IEC 60255
Zone feeder 550/51/51N (MCCB)Ir 273 A - Im 1989 A - Ig 50 A0.1 s (grading)IEC 60947-2 / IEC 60255
Zone feeder 650/51/51N (MCCB)Ir 273 A - Im 1989 A - Ig 50 A0.1 s (grading)IEC 60947-2 / IEC 60255
+4 more feeders50/51/51N (MCCB)per feeder load0.1 s (grading)IEC 60947-2
Settings are illustrative starting points — confirm with a protection coordination study per IEC 60255 / IEEE 242.
📚 Calculation book
CALCULATION BOOK
1250 kVA - 12kV/0.4kV - single - illustrative
1. Load calculation
Standard: IEC 60076 - IEC 60364-5-52
ParameterFormulaValue
Connected loadP = sum(kW)1,550 kW
Demand factorKd0.7
Demand powerPd = P x Kd1,085 kW
Power factorcos(phi) before -> after0.90 -> 0.95
Design apparent powerSd = Pd / cos(phi)1,142 kVA
Transformer loadingSd / Srated91%
2. Short-circuit calculation
Standard: IEC 60909
ParameterFormulaValue
System impedance (pu)Zs = S / Ssc0.42% (on 1250 kVA base)
Transformer impedanceZt = Z%4%
Total impedanceZ = Zt + Zs4.42%
LV prospective IscIsc = In / Z40.9 kA
HV prospective IscIsc = Ssc / (sqrt(3) x V)14.4 kA
Breaking checkIcu >= IscLV 50 kA (1.2x margin) PASS
3. Voltage drop
Standard: IEC 60364-5-52 Annex G
ParameterFormulaValue
Main feederdU = sqrt(3) x I x L x R / V300 mm2 - dU 5.86% @ 400 m
Limitmax 3%EXCEEDS limit
Transformer volt. reg.dU ~ loading x Z% x sin(phi)1.1% at full load
4. Reactive power / harmonics
Standard: IEC 61921 (PFC) - IEEE 519 (harmonics)
ParameterFormulaValue
Required compensationQc = Pd x (tan1 - tan2)169 kvar
PFC bankstandard step200 kvar
Detuned reactorp = 6%12.0 kvar @ 6% (anti-resonance)
5. Grounding
Standard: IEC 60364-5-54 earthing arrangements and protective conductors LV earthing target 10 ohm (TN systems); 4 ohm used as a conservative design target - target 4 ohm
ParameterFormulaValue
Single rod resistanceR1 = rho/(2 x pi x L) x ln(4L/d)39.6 ohm
Rods requiredn = R1 / (target x 0.8)13 rod(s) <= 4 ohm
Rod specdia x length20 mm x 2.5 m
This calculation book is illustrative it consolidates the computed values with the referenced standards. A licensed engineer must verify and seal final design documents for construction.
🔧 Secondary schematic (control & signal)
SECONDARY CONTROL & SIGNAL CIRCUIT0.4 kV circuit breaker close/trip + indication + interlock (TYPICAL)+control supplyCS (close)interlock52Cclose coil-TC (trip)prot trip52Ttrip coilSIGNAL (indication)52a (closed)REDbreaker closed-TYPICAL CIRCUITStandard control/signal scheme for Zone feeder 1.Project detailing required (wiring, terminal assignment).
🔩 Terminal strip (typical)
TERMINAL STRIP (TYPICAL)X1 secondary wiring terminals (typical project detailing required)TerminalFunctionWireX1:1control supply L+1.5 mm2X1:2control supply L-1.5 mm2X1:3close command1.5 mm2X1:4trip command1.5 mm2X1:5breaker 52a status1.5 mm2X1:6breaker 52b status1.5 mm2X1:7trip circuit healthy1.5 mm2X1:8earth / shield2.5 mm2
🏙️ Load profile
ParameterValue
Road lighting300 kW
Tunnel lighting200 kW
Bridge/tunnel150 kW
Pumping stations400 kW
EV charging500 kW
🔁 Ring network
ParameterValue
Distributiondispersed (800 m radius)
Box substations2 node(s)
Ring main units2 × XGN15-12 SF6 (3-way)
📏 Standard basis (依据标准)
TopicStandard
Standard basisIEC · IEC 60364-5-52
Conductor ampacityIEC 60364-5-52 Table B.52.2–B.52.5 (copper, 3 loaded conductors, 30°C ambient, PVC) — typical/rounded values, conservative (±3%)
Voltage-drop limitIEC 60364-5-52 Annex G · max drop 3%
Winding temp riseIEC 60076-2 — winding temp rise 65 K (Class A insulation, ONAN)
kVA ratingsIEC 60076-1 R10 preferred numbers
Breaker framesIEC 60947-2 frame sizes (In)
Grounding targetIEC 60364-5-54 earthing arrangements and protective conductors — LV earthing target ≤ 10 Ω (TN systems); 4 Ω used as a conservative design target · target 4 Ω
Power supply designGB 50052 — code for design of electric power supply systems
Urban road lightingCJJ 45 — standard for lighting design of urban road
Low-voltage distributionGB 50054 — code for design of low-voltage electric installations
Prefabricated substationGB/T 17467 · IEC 62271 — high-voltage/low-voltage prefabricated substations
🧮 How it was calculated
1. Road lighting: 300 kW
2. Tunnel lighting: 200 kW
3. Bridge/tunnel: 150 kW
4. Pumping stations: 400 kW
5. EV charging: 500 kW
6. Connected load = 1,550 kW → demand = 1,550 × 0.7 = 1,085 kW
7. Dispersed load (800 m radius) → 2 box substation node(s) recommended
8. Ring main units: 2 × XGN15-12 SF6 (ring main connection)
9. Loads: P=1,550 kW, PF 0.90, 10 circuits
10. Demand: 1,550 × 0.7 = 1,085 kW
11. PFC: Qc = 1,085 × (0.484 − 0.329) = 169 kVAR → 200 kVAR bank
12. Transformer: S = 1,085 ÷ 0.95 = 1142.1 kVA → 1,250 kVA standard
13. Loading: 1,142 ÷ 1,250 = 91% (high — consider next size)
14. Voltage regulation: 91% × 4% × sinφ ≈ 1.1% at full load
15. HV unit integrated in substation (In 60.1 A)
16. LV: In 1804 A, Isc 40.9 kA (Xfmr Z 4% + system 0.4%) → GGD-2000 (integrated), 1 feeder panel(s)
17. Grounding: R₁ 39.6 Ω → 13 rod(s)
18. Main feeder: 4× 300 mm² · ΔU 5.86% — FAIL (exceeds 3% limit)
Summary
Estimated total (FOB Qingdao, EXW) — priced equipment$897,825
📋 Design notes
Pricing basis: FOB Qingdao (EXW) equipment price. Freight, duty and installation are not included — add for landed economics.
Transformer loading: 91% at design demand — high, consider the next size up.
Short-circuit check: HV 14.4 kA vs 25 kA (1.7× margin) · LV 40.9 kA vs 50 kA (1.2× margin).
Voltage regulation: ≈ 1.1% at full load (typical limit 5%).
Power factor correction: 200 kVAR automatic bank corrects PF to 0.95.
Voltage-drop check — FAIL: ΔU exceeds the 3% limit on: main feeder 5.9%, Zone feeder 1 3.2%, Zone feeder 2 3.2%, Zone feeder 3 3.2%, Zone feeder 4 3.2% … +6 more — increase cross-section or add a parallel run.
Parallel conductors: Single-cable ampacity exceeded — parallel conductors specified: main feeder 4× 300 mm² (per IEC 60364-5-52 / GB 50054).
Cable & grounding pricing: Cable conductors and grounding are priced from the confirmed cables-trays-grounding price reference (per-metre copper YJV; aluminium remains POA). The main copper busbar is POA — its length is project-specific.
Busway (high-current feeders): For LV feeders above ~2500 A, a busway (母线槽) trunking system is recommended instead of parallel cables.
Prefabricated (box) substation: A factory-assembled box substation integrates the SF6 ring main unit, transformer and LV panel — compact, low-noise and quick to energize for urban sites (GB/T 17467).
Ring main network: The MV ring main unit (XGN15-12) keeps supply continuous: a fault on one feeder can be isolated while the ring feeds from the other side.
Load distribution: Dispersed load over a 800 m radius — 2 box substation node(s) keep LV feeders short and reduce cable loss.
EV charging: EV charging is a growing, highly intermittent urban load; size for simultaneous charging diversity and consider dedicated feeders.
Pole-mounted switchgear: For overhead MV sections, a pole-mounted vacuum load-break switch (ZW32/FZW28-12) provides line sectioning and fault isolation — priced at $1,183/unit (FOB reference).

Cara perhitungannya

Cara perhitungan ukurannya

Beban terhubung = penerangan jalan + penerangan terowongan + jembatan/terowongan + pemompaan + pengisian EV. Kebutuhan = terhubung × simultanitas (0,7 tipikal). Beban tersebar pada radius suplai tertentu dilayani oleh beberapa node gardu box, masing-masing mengintegrasikan ring main unit SF6, transformator, dan panel LV (GB/T 17467).

Standar yang berlaku

Perhitungan ukuran mengacu pada GB 50052 (desain pasokan tenaga), CJJ 45 (desain penerangan jalan perkotaan), GB 50054 (desain instalasi tegangan rendah), GB/T 17467, dan IEC 62271 (gardu prefabrikasi).

Pertanyaan yang sering diajukan

What is a prefabricated box substation and when is it used?

A box Substation (compact/Prefabricated Substation) packages Transformer, HV and LV Switchgear in one weatherproof enclosure, following GB/T 17467 and IEC 62271-202. Urban infrastructure uses them for road lighting, tunnels, pumping and EV charging where a brick substation is too costly or too large. Ratings typically run 100-1600 kVA at 12/0.4 kV.

How is road and tunnel lighting power distributed?

Road lighting uses a TT or TN-S system fed from a dedicated transformer or a lighting box substation, with feeder lengths up to 1 km and voltage drop limited to 5% per CJJ 45. Tunnel lighting is a safety load requiring dual supply or emergency power. The calculator models dispersed loads and feeder radius to size the substation.

What is an SF6 ring main unit and why is it used in cities?

An SF6 ring main unit (RMU) is a compact, sealed 12-24 kV switchgear using SF6 gas for insulation and arc quenching, needing little maintenance and fitting in small vaults. Cities use RMUs on 10-12 kV ring networks to feed box substations, giving N-1 supply in dense areas. The calculator includes RMU selection for the urban feed.

What load profile does an EV charging station add to city infrastructure?

EV charging is a sharp, clustered load: a 120 kW DC fast charger can draw 120 kVA and a 10-charger station peaks near 500-1200 kVA. Demand is highly time-correlated, so diversity is low and transformer sizing must account for coincidence. IEC 61851 and GB/T 51313 govern the installation; the calculator includes charging load in the urban mix.

What cable type is used for urban 12 kV distribution?

Urban 12 kV networks use XLPE-insulated cables (YJV/YJV22 in China, IEC 60502) in cross-sections of 120-400 mm2, buried or in ducts. XLPE replaces paper-insulated PILC cables, allowing higher operating temperature (90 deg C) and lower maintenance. The calculator selects feeder cable and checks ampacity and voltage drop.

What emergency power does a city tunnel need?

Tunnels are safety-critical: lighting, ventilation and fire systems need dual supply plus a diesel generator or EPS for evacuation (GB 50052 first-class important load). Emergency lighting must restore within 0.5-15 s per GB 51309. The calculator models the emergency level and sizes the standby path for the urban loads.

Sematkan kalkulator ini

Salin kode iframe di bawah untuk menyematkan kalkulator ini di situs mana pun. Halaman sematan bersifat noindex dan menyesuaikan lebar apa pun.

Kalkulator terkait

Hasil adalah estimasi teknik untuk referensi. Desain akhir harus dikonfirmasi oleh insinyur lokal berlisensi terhadap kondisi lokasi dan kode yang berlaku. Harga adalah FOB Qingdao (EXW) dan tidak termasuk pengiriman, bea masuk, atau instalasi.

Send my complete design report

Get the full bill of materials, single-line diagram, calculation steps and FOB pricing as a PDF — free, no sign-up.

💬 Chat on WhatsApp

Your data stays private. No spam — only a reply to your enquiry.