QDTB®变压器官网

工业园区电力系统计算器

为工厂或工业园区进行配电容量计算 — 总设备负荷、需用系数、电机占比与谐波源占比,并完成变压器与开关柜选型、无功补偿及 BOM。

开始计算 工业制造解决方案
智能化与监控
在 BOM 与架构图中加入保护、计量与 SCADA(监控与二次)层。

为什么使用此计算器

工业厂房中电机、加热与电子负载混合运行,自然功率因数低于 0.9,且谐波显著。本计算器将连接设备负荷转化为选型后的变压器与开关柜方案,并按 GB 50052 与 GB 50055 进行无功补偿与谐波滤波。

Worked Examples

Example 1 — 2 MW Factory Load (Demand Factor, Motor & Harmonic Share) · FOB $257,923
Industrial park power system · 10kV/0.4kV
1,600 kVA transformer
S13-M-1600/10 · demand 1,200 kW · PF 0.95
Connected load
2,000 kW
Demand (Kd 0.6)
1,200 kW
Motor share
60%
Reactive comp.
443 kvar
Est. total (FOB)
POA
📦 Bill of Materials
EquipmentModelSpecQty
HV incoming panelKYN28A-12-630-315630 A / 31.5 kA · vacuum1
Main transformerS13-M-1600/101600 kVA · Oil-Immersed · Copper · S131
LV incoming panelGGD-25002500 A busbar · In 2309 A1
LV feeder panel (×2)GGD-2500distributes 8 circuits2
Cable branch box (LV)DFW-0.41-in / 4-out · 0.4 kV · 630 A1
Main feeder cable (TX→LV)YJV 0.6/1kV 300 mm² ×55× 300 mm² Cu · ΔU 1.20% @ 80 m · $154.0/m5
Feeder cable — Plant feeder 1 (×8)YJV 300 mm²300 mm² Cu · 440 A · ΔU 1.1% · $154.0/m8
Branch trunk cable (LV → branch box 1)YJV 300 mm² ×44× 300 mm² Cu · 1760 A · ΔU 1.1% · $154.0/m4
Main busbar (Cu)Cu 125×10125×10 · 2500 A rating · ref $147.8/mincluded
Grounding electrodeΦ20mm × 2.5m rodR₁ 39.6 Ω → 13 rod(s) ≤ 4 Ω13
Detuned PFC capacitor bank443 kvarautomatic · 7% detuned · 0.4 kV1
Series detuning reactor (7%)31.0 kvar189 Hz tuning · below 5th harmonic1
📐 Single-line diagram
CTCT 100/5APTPT 10kV/100V50/5151NHV incomingKYN28A-12-630-315630 A / 31.5 kA - vacuumS13-M-1600/101600 kVAZ = 4%Oil-Immersed - Copper - S13kWhmeteringLV incomingGGD-25000.4 kV LV busbar125x10 Cu - 2500 ASPDLV feeder panel x2 - 8 circuitsPlant feeder 1 - 440 AYJV 300 mm2Plant feeder 2 - 440 AYJV 300 mm2Plant feeder 3 - 440 AYJV 300 mm2Plant feeder 4 - 440 AYJV 300 mm2Plant feeder 5 - 440 AYJV 300 mm2Plant feeder 6 - 440 AYJV 300 mm2Plant feeder 7 - 440 AYJV 300 mm2Plant feeder 8 - 440 AYJV 300 mm2Grounding 13xdia20mmx2.5m rodCable branch box DFW-0.4 x1 (1-in / 4-out)
LEGENDBreaker (52)DisconnectorCTCT (current transformer)PTPT (voltage transformer)50/51Protection relay 50/51/51N/87kWhMeter (kWh)SPD (surge protection)Transformer
⚙️ Electrical schematic (protection & metering)
ELECTRICAL SCHEMATIC - PROTECTION & METERING10 kV / 0.4 kV - 1600 kVA - secondary circuits (schematic)INCOMING 10 kVCT100/5Aprotection CT5250/5151Novercurrent / earth-faultPT10kV/100Vbus PT (voltage)TRANSFORMER1600 kVAZ = 4%kWhrevenue meteringLV 520.4 kV LV BUSSPDCT.../5APlant feeder 1 - 440 A50/51CT.../5APlant feeder 2 - 440 A50/51CT.../5APlant feeder 3 - 440 A50/51CT.../5APlant feeder 4 - 440 A50/51CT.../5APlant feeder 5 - 440 A50/51CT.../5APlant feeder 6 - 440 A50/51CT.../5APlant feeder 7 - 440 A50/51CT.../5APlant feeder 8 - 440 A50/51
⛳ Grounding grid layout
SUBSTATION GROUNDING GRID LAYOUTsite 12 m x 8 m - ring earth electrode (schematic)TRANSFORMERR1R2R3R4R5R6R7R8R9R10R11R12R1312 mGround rods: 13 x dia 20 mm x 2.5 m copper-bonded steelRod spacing: 5 m (= 2 x rod length, ring electrode)Target resistance: <= 4 ohm (measure after installation)Standard: IEEE 80 / GB-T 50065 (earthing design) - indicative layout
🔌 Cable schedule & routing
CABLE SCHEDULEIDFromToCable (model / spec)LengthC0TransformerLV panelYJV 0.6/1kV 300 mm2 (2309 A)80 mC1LV panelPlant feeder 1YJV 300 mm2 (440 A)80 mC2LV panelPlant feeder 2YJV 300 mm2 (440 A)80 mC3LV panelPlant feeder 3YJV 300 mm2 (440 A)80 mC4LV panelPlant feeder 4YJV 300 mm2 (440 A)80 mC5Branch boxPlant feeder 5YJV 300 mm280 mC6Branch boxPlant feeder 6YJV 300 mm280 mC7Branch boxPlant feeder 7YJV 300 mm280 mC8Branch boxPlant feeder 8YJV 300 mm280 mROUTING (schematic)LV PANELL1L2L3L4L5L6L7L8... +1 feedersCable lengths are indicative (run-length based); confirm on site before installation.
🗄 Switchgear arrangement
SWITCHGEAR ARRANGEMENTpanel lineup (front view, schematic)HV INCOMINGKYN28A-12-630-315LV INCOMINGGGD-2500FEEDERGGD-2500FEEDERGGD-2500BRANCH BOXDFW-0.45 panel(s) - each 128 mm (typical)Clearance / aisle per IEC 61936-1 - layout indicative
🛡 Protection configuration
PROTECTION CONFIGURATION10 kV / 0.4 kV - 1600 kVA - protection zones (schematic)INCOMING 10 kVCTCT 100/5A505151Novercurrent / earth-fault52TRANSFORMER1600 kVA - Z=4%49thermal overloadCTCT 2500/5A505151NLV incoming protection520.4 kV LV BUSCTCT 500/5A50/5151NPlant feeder 1440 ACTCT 500/5A50/5151NPlant feeder 2440 ACTCT 500/5A50/5151NPlant feeder 3440 ACTCT 500/5A50/5151NPlant feeder 4440 ACTCT 500/5A50/5151NPlant feeder 5440 ACTCT 500/5A50/5151NPlant feeder 6440 ACTCT 500/5A50/5151NPlant feeder 7440 ACTCT 500/5A50/5151NPlant feeder 8440 AProtection layout & CT ratios are schematic / illustrative final settings per IEC 60255 / IEEE 242.
📋 Protection settings
CircuitProtectionSettingTimeStandard
HV incoming 10 kV50 instantaneous739 AinstIEC 60255-151 / IEEE 242
HV incoming 10 kV51 overcurrent111 A0.5 sIEC 60255-151 / IEEE 242
HV incoming 10 kV51N earth-fault18 A0.5 sIEC 60364-4-41
Transformer 1600 kVA49 thermal overload79% of ratedalarm 90%IEC 60076-7 / IEEE C57.91
LV incoming 0.4 kV50 instantaneous18475 AinstIEC 60947-2
LV incoming 0.4 kV51 overcurrent2771 A0.3 sIEC 60947-2 / IEC 60255
LV incoming 0.4 kV51N earth-fault462 A0.3 sIEC 60364-4-41
Plant feeder 150/51/51N (MCCB)Ir 484 A - Im 3520 A - Ig 88 A0.1 s (grading)IEC 60947-2 / IEC 60255
Plant feeder 250/51/51N (MCCB)Ir 484 A - Im 3520 A - Ig 88 A0.1 s (grading)IEC 60947-2 / IEC 60255
Plant feeder 350/51/51N (MCCB)Ir 484 A - Im 3520 A - Ig 88 A0.1 s (grading)IEC 60947-2 / IEC 60255
Plant feeder 450/51/51N (MCCB)Ir 484 A - Im 3520 A - Ig 88 A0.1 s (grading)IEC 60947-2 / IEC 60255
Plant feeder 550/51/51N (MCCB)Ir 484 A - Im 3520 A - Ig 88 A0.1 s (grading)IEC 60947-2 / IEC 60255
Plant feeder 650/51/51N (MCCB)Ir 484 A - Im 3520 A - Ig 88 A0.1 s (grading)IEC 60947-2 / IEC 60255
+2 more feeders50/51/51N (MCCB)per feeder load0.1 s (grading)IEC 60947-2
Settings are illustrative starting points — confirm with a protection coordination study per IEC 60255 / IEEE 242.
📚 Calculation book
CALCULATION BOOK
1600 kVA - 10kV/0.4kV - single - illustrative
1. Load calculation
Standard: IEC 60076 - IEC 60364-5-52
ParameterFormulaValue
Connected loadP = sum(kW)2,000 kW
Demand factorKd0.6
Demand powerPd = P x Kd1,200 kW
Power factorcos(phi) before -> after0.82 -> 0.95
Design apparent powerSd = Pd / cos(phi)1,263 kVA
Transformer loadingSd / Srated79%
2. Short-circuit calculation
Standard: IEC 60909
ParameterFormulaValue
System impedance (pu)Zs = S / Ssc0.32% (on 1600 kVA base)
Transformer impedanceZt = Z%4%
Total impedanceZ = Zt + Zs4.32%
LV prospective IscIsc = In / Z53.5 kA
HV prospective IscIsc = Ssc / (sqrt(3) x V)28.9 kA
Breaking checkIcu >= IscLV 65 kA (1.2x margin) PASS
3. Voltage drop
Standard: IEC 60364-5-52 Annex G
ParameterFormulaValue
Main feederdU = sqrt(3) x I x L x R / V300 mm2 - dU 1.20% @ 80 m
Limitmax 3%within limit
Transformer volt. reg.dU ~ loading x Z% x sin(phi)1.0% at full load
4. Reactive power / harmonics
Standard: IEC 61921 (PFC) - IEEE 519 (harmonics)
ParameterFormulaValue
Required compensationQc = Pd x (tan1 - tan2)0 kvar
PFC bankstandard step0 kvar
Detuned reactorp = 6%n/a
5. Grounding
Standard: IEC 60364-5-54 earthing arrangements and protective conductors LV earthing target 10 ohm (TN systems); 4 ohm used as a conservative design target - target 4 ohm
ParameterFormulaValue
Single rod resistanceR1 = rho/(2 x pi x L) x ln(4L/d)39.6 ohm
Rods requiredn = R1 / (target x 0.8)13 rod(s) <= 4 ohm
Rod specdia x length20 mm x 2.5 m
This calculation book is illustrative it consolidates the computed values with the referenced standards. A licensed engineer must verify and seal final design documents for construction.
🔧 Secondary schematic (control & signal)
SECONDARY CONTROL & SIGNAL CIRCUIT0.4 kV circuit breaker close/trip + indication + interlock (TYPICAL)+control supplyCS (close)interlock52Cclose coil-TC (trip)prot trip52Ttrip coilSIGNAL (indication)52a (closed)REDbreaker closed-TYPICAL CIRCUITStandard control/signal scheme for Plant feeder 1.Project detailing required (wiring, terminal assignment).
🔩 Terminal strip (typical)
TERMINAL STRIP (TYPICAL)X1 secondary wiring terminals (typical project detailing required)TerminalFunctionWireX1:1control supply L+1.5 mm2X1:2control supply L-1.5 mm2X1:3close command1.5 mm2X1:4trip command1.5 mm2X1:5breaker 52a status1.5 mm2X1:6breaker 52b status1.5 mm2X1:7trip circuit healthy1.5 mm2X1:8earth / shield2.5 mm2
🏭 Load profile
ParameterValue
Connected load2,000 kW
Demand factor0.6 → demand 1,200 kW
Motor share60% (720 kW)
Harmonic-source share25% (300 kW)
🌀 Power quality
ParameterValue
Reactive compensation443 kvar detuned bank (7% reactor)
Harmonic currentIh 137 A @ 30% THDi
APF requiredNo — below 30% threshold
📏 Standard basis (依据标准)
TopicStandard
Standard basisIEC · IEC 60364-5-52
Conductor ampacityIEC 60364-5-52 Table B.52.2–B.52.5 (copper, 3 loaded conductors, 30°C ambient, PVC) — typical/rounded values, conservative (±3%)
Voltage-drop limitIEC 60364-5-52 Annex G · max drop 3%
Winding temp riseIEC 60076-2 — winding temp rise 65 K (Class A insulation, ONAN)
kVA ratingsIEC 60076-1 R10 preferred numbers
Breaker framesIEC 60947-2 frame sizes (In)
Grounding targetIEC 60364-5-54 earthing arrangements and protective conductors — LV earthing target ≤ 10 Ω (TN systems); 4 Ω used as a conservative design target · target 4 Ω
Power supply designGB 50052 — code for design of electric power supply systems
Low-voltage distributionGB 50055 — code for design of electric equipment for industrial facilities
HarmonicsGB/T 14549 — quality of electric energy supply: harmonics in public supply network
TransformersIEC 60076 — power transformers
🧮 How it was calculated
1. Connected equipment load = 2,000 kW
2. Demand = 2,000 × 0.6 = 1,200 kW
3. Motor share = 60% → 720 kW (drives natural PF 0.82)
4. Reactive compensation: Qc = 1,200 × (tanφ₁ − tanφ₂) = 443 kvar
5. Harmonic-source share = 25% → 300 kW → Ih = 137 A (30% THDi)
6. Loads: P=2,000 kW, PF 0.82, 8 circuits
7. Demand: 2,000 × 0.6 = 1,200 kW
8. Transformer: S = 1,200 ÷ 0.95 = 1263.2 kVA → 1,600 kVA standard
9. Loading: 1,263 ÷ 1,600 = 79% (good range)
10. Voltage regulation: 79% × 4% × sinφ ≈ 1.0% at full load
11. HV: In 92.4 A, Isc 28.9 kA → KYN28A-12-630-315
12. LV: In 2309 A, Isc 53.5 kA (Xfmr Z 4% + system 0.3%) → GGD-2500, 2 feeder panel(s)
13. Cable branch boxes: 1 × DFW-0.4 (1-in/4-out) for feeder grouping
14. Grounding: R₁ 39.6 Ω → 13 rod(s)
15. Main feeder: 5× 300 mm² · ΔU 1.20% — OK
Summary
Estimated total (FOB Qingdao, EXW) — priced equipment$257,923
📋 Design notes
Pricing basis: FOB Qingdao (EXW) equipment price. Freight, duty and installation are not included — add for landed economics.
Transformer loading: 79% at design demand — good range.
Short-circuit check: HV 28.9 kA vs 31.5 kA (1.1× margin) · LV 53.5 kA vs 65 kA (1.2× margin).
Voltage regulation: ≈ 1.0% at full load (typical limit 5%).
Copper price linkage: Copper-wound transformer price tracks LME copper (current $14,219/t · 2026-09-12 · LME Copper (Sina hf_CAD)).
Parallel conductors: Single-cable ampacity exceeded — parallel conductors specified: main feeder 5× 300 mm², branch trunk 1 4× 300 mm² (per IEC 60364-5-52 / GB 50054).
Cable & grounding pricing: Cable conductors and grounding are priced from the confirmed cables-trays-grounding price reference (per-metre copper YJV; aluminium remains POA). The main copper busbar is POA — its length is project-specific.
Busway (high-current feeders): For LV feeders above ~2500 A, a busway (母线槽) trunking system is recommended instead of parallel cables.
Demand factor: 0.6 demand factor avoids oversizing — not all plant equipment runs simultaneously at full load.
Motor & harmonic load: 60% motor load (natural PF 0.82); 25% harmonic-source load (detuned PFC is sufficient.)
Zone / plant metering: For multi-tenant parks, per-zone / per-plant revenue-grade metering (分区分厂计量) at the LV feeder enables sub-billing and energy accountability — quoted per project.
Harmonic sources: Typical harmonic sources: VFD drives (THDi ~30%), rectifiers / electroplating (~25–35%), UPS (~10–20%), welding machines and LED lighting. The 25% share is applied as an aggregate — a detailed equipment list refines APF sizing.
Transformer loading: Transformer sized at the target PF 0.95; final capacity must be confirmed against the actual equipment schedule.

计算过程说明

选型计算原理

计算功率 P = 连接负荷 × 需用系数 Kd(并非所有设备同时运行)。电机占比决定自然功率因数;无功补偿 Qc = P × (tanφ₁ − tanφ₂) 将其校正至目标 PF。谐波源占比给出谐波电流 Ih = I₁ × THDi,由调谐电容器组滤波。

适用标准

选型参考 GB 50052(供配电设计)、GB 50055(工业低压配电设计)、GB/T 14549(谐波)及 IEC 60076(变压器)。

常见问题

工业园区该取多大的需用系数?

园区多家工厂不会同时开满设备,需用系数典型 0.55-0.7。2000 kW 装机、0.6 需用系数、0.9 功率因数得约 1330 kVA,宜配 1600 kVA 或两台 800 kVA。计算器用需用系数与电机占比为中低压厂区选型。

工厂密集的园区需要多少谐波治理?

当 60% 负荷为变频电机、25% 为非线性(整流、UPS)时,THDi 可达 15-25%。IEEE 519 要求公共连接点 THD 限 5-8%,故需 7% 去谐电容器组或 APF。计算器按谐波占比配置补偿与去谐。

工业园区的标准中低压架构是怎样的?

典型架构:10 kV(或 35 kV)市电 → 环网或放射式中压开关柜 → 每厂/每区块一台变压器 → 0.4 kV 开关柜 → 电机控制中心。沿环网布置环网柜的 10 kV 环网可提供 N-1 供电。计算器为园区聚合负荷选变压器、开关柜与补偿。

如何为每家工厂分配变压器容量?

每家工厂配一台按需用容量加 20-25% 裕量的独立变压器,小租户可合用一台大变压器。独立变压器隔离故障、便于计量,但共享方案成本更低。计算器聚合园区需量并给出单台与分拆方案。

工业园区应维持多大功率因数?

供电公司通常要求 0.9-0.95 功率因数,低于约 0.9 收取罚金。电机为主的园区初始功率因数 0.75-0.85,加电容器组可提到 0.95。计算器算出从实测 pf 到目标所需的 kvar 补偿并选低压电容柜。

园区中压网络通常提供什么冗余?

带常开联络的环网中压网络提供 N-1 冗余:任一段电缆或环网柜故障可被隔离并从另一方向恢复供电。放射式馈线更便宜但故障即失电。计算器的架构说明覆盖环网与放射式的可靠性和成本权衡。

嵌入此计算器

复制下方 iframe 代码,即可将此计算器嵌入任何网站。嵌入页面为 noindex,适配任意宽度。

相关计算器

结果为工程估算,仅供参考。最终设计须由当地持证工程师根据现场条件和适用规范确认。价格为青岛交货价 FOB(EXW),不含运费、关税及安装费。

发送我的完整设计报告

免费获取完整设备清单(BOM)、单线图、计算步骤与 FOB 报价的 PDF 报告,无需注册。

💬 WhatsApp 咨询

您的信息仅用于回复询盘,不用于任何其他用途。