QDTB® Transformer
All figures are configurator-generated feasibility-level estimates; drawings are schematic deliverables pending refinement by a licensed design institute, not construction documents.
All Solutions

700 kW / 630 kVA Mine Power: 250 kW Four-Quadrant Hoist + SVG + Diesel Deep-Read

2×S13-M-630/10 N+1 · 250 kW four-quadrant hoist VFD · SVG · 500 kW diesel

1 · TL;DR Conclusion

Conclusion: this 700 kW mine uses 2×S13-M-630/10 oil transformers (N+1) + a 250 kW four-quadrant hoist VFD + SVG + a 500 kW standby diesel — configurator total ≈ $269,595, 94% N-1 loading (near limit), 250 kW hoist dip 2.7% on VFD vs 12.2% DOL (DOL fails), THDi 36% (feasibility-level).

  • •2×630 kVA S13-M-630/10 (N+1), 94% loading after one-unit loss (pass, near limit — watch headroom)
  • •250 kW four-quadrant hoist VFD: 2.7% dip; DOL would sag 12.2% and fail the 10% limit
  • •SVG ($32,200) + 500 kW standby diesel keep hoist/ventilation/drainage continuous
  • •THDi 36% from VFDs → detuned reactor + SVG/APF
  • •Economics: $269,595 total; SH15 upgrade $336/yr, ~3 yr payback; losses 173,812 kWh/yr ≈ $20,857

2 · Solution Overview

A mine's electrical lifeline is the hoist, ventilation and dewatering: the hoist is four-quadrant (lifts on the way up, regenerates on the way down), ventilation and drainage run continuously, and a power loss endangers people underground. This scheme uses N+1 transformers, a four-quadrant hoist VFD, SVG and a standby diesel to keep the shaft safe.

2×630 kVA (S13-M, N+1)
Transformer
10 kV (dual N+1)
Feed
250 kW (four-quadrant)
Hoist VFD
560 kW (700 kW installed)
Demand
500 kW standby
Diesel
350 kW
Impact load
36%
THDi
94%
N-1 loading
SourceRoleShare kWShare
Grid 10 kVbase560 kW100%
Diesel 500 kWbackup0 kW0%

Mining Power System Calculator

Size the power distribution for your mine - crusher, hoist, fan and conveyor loads, motor-starting voltage-dip check, VFD harmonic filtering and altitude derating, with BOM and single-line diagram.

Open the Calculator
Smart Monitoring & Control
Add the protection, metering and SCADA (monitoring & secondary) layer to the BOM and architecture diagram.

3 · Design Process & Rationale

1. Requirement identification

700 kW mine: 250 kW four-quadrant hoist, continuous ventilation/drainage, grade-1 250 kW (hoist), grade-2 300 kW (vent/drainage).

2. Load & grading

Hoist grade-1 250 kW (personnel safety); ventilation/drainage grade-2 300 kW; impact 350 kW, nonlinear 250 kW.

3. Source

10 kV grid + 500 kW standby diesel; diesel covers grade-1 250 kW (V9 pass), 20 ft container, 3-day autonomy.

4. Transformer sizing

560 kW ≈ 589 kVA → 630 kVA tier; N+1 → 2×S13-M-630/10, 94% loading after one-unit loss (near limit).

5. Hoist drive

250 kW four-quadrant VFD (2.7% dip); DOL would sag 12.2% and fail — VFD is mandatory; regenerative braking returns to the DC bus.

6. SVG & harmonics

36% THDi + 350 kW impact → SVG dynamic compensation + detuned reactor.

7. Protection

LV 22 kA / MV 28.9 kA, breaking LV 36 kA / MV 31.5 kA; selectivity 9.18×; modbus SCADA.

Pain Points → Solution → Evidence

Pain

DOL starting the hoist sags the bus 12.2% and trips other feeders

Solution

250 kW four-quadrant VFD, 2.7% dip

Evidence

V5: DOL 12.2% ok=false, VFD 2.7% ok=true

Pain

Power loss traps miners underground

Solution

Standby diesel + ATS to hoist/ventilation

Evidence

V9 pass (diesel 500 ≥ grade-1 250); 20 ft container, 3-day

Pain

VFD harmonics + regenerating hoist distort the bus

Solution

SVG + detuned reactor

Evidence

THDi 36% (V6 warn), SVG $32,200

4 · Key Parameter Deep-Read

ParameterValueBasisImpact & Boundary
Transformer capacity630 kVA ×2 (S13-M)589 kVA → 630 tier; N+1 → 2 units94% after one-unit loss, near limit
consider 800 kVA for headroom
Hoist drive250 kW four-quadrant VFD, 2.7% dipVFD kst 1.3 vs DOL 6.5DOL 12.2% fails; VFD is mandatory
four-quadrant regen needs braking resistor/feedback unit
Diesel500 kW standbycovers grade-1 250 kW (hoist)3-day autonomy, <15 s auto-start
full-mine backup needs a larger set
Impact load350 kWhoist acceleration surgesets SVG size & start dip
vent/drainage simultaneous start to verify
HarmonicsTHDi 36%nonlinear 250 kW / 700 kWneeds SVG active filtering
target THDi ≤8%
Demand factor0.8 → 560 kWinstalled 700 kW × Kd 0.8sizes transformer at real demand
verify against hoist/vent duty cycle

5 · Drawing Deep-Read

Dwg 3/26Single-line diagram — 10 kV → 2×S13-M-630/10 → MNS LV bus → hoist drive + ventilation + dewatering + diesel ATS + SVG
Why: The SLD gives the mine's electrical skeleton: N+1 dual transformers + hoist/vent/drainage feeders + diesel auto-transfer + SVG — the structural source of 'shaft safety stays powered'.
Dwg 8/26Short-circuit calculation — LV 22 kA · breaking LV 36 kA (1.3× margin)
Why: The LV fault level of 22 kA forces 36 kA breaking on the LV switchgear — the underground equipment safety red line.
Dwg 19/26Reactive & harmonic compensation — THDi 36% · SVG dynamic compensation + detuned reactor
Why: Hoist VFD + regeneration push THDi to 36%; the PFC/SVG drawing specifies dynamic compensation to keep the bus clean and the transformer cool.
Dwg 15/26TCC protection coordination curve — Incomer → transformer → LV incomer → feeder, selectivity 9.18×
Why: A mine fears one fault stopping the hoist and trapping people; TCC verifies selectivity so a downstream fault trips only its feeder.
Dwg 25/26Diesel fuel oil system — 500 kW standby · 20 ft container · 3-day autonomy
Why: The standby diesel is the last line for hoisting people and ventilation on outage; the fuel drawing quantifies 3-day autonomy.

The following drawings are shown for reference (full set in the configurator “View design document”):

Dwg 4 · System topologyDwg 5 · Distribution systemDwg 6 · MV distribution systemDwg 7 · LV distribution systemDwg 9 · Applicable codes & standardsDwg 10 · Main equipment technical dataDwg 11 · Construction & testingDwg 12 · Power quality assessmentDwg 13 · SCADA architectureDwg 14 · Protection configurationDwg 16 · Grounding systemDwg 17 · Lightning & surge protectionDwg 18 · Equipment layoutDwg 20 · Grid-tied / islanding transferDwg 21 · Secondary control & signalDwg 22 · Terminal stripDwg 23 · Panel layoutDwg 24 · DC auxiliary powerDwg 26 · Diesel earthing system

6 · Operation Demo (Deep-Read)

Reliability

N+1 94% after one-unit loss (near limit) + diesel auto-transfer ≤15 s covering grade-1 hoist 250 kW, keeping the shaft safe.

Fault & protection

LV 22 kA / MV 28.9 kA, breaking LV 36 kA / MV 31.5 kA; selectivity 9.18×, a downstream fault trips only its feeder.

Power quality

THDi 36% mitigated by SVG; hoist VFD dip 2.7% (DOL 12.2% fails), bus 0.981 pu.

Economics

$269,595 total; SH15 upgrade ~3 yr payback ($336/yr); losses 173,812 kWh/yr ≈ $20,857.

Other views (shown): LCC (life-cycle cost) · Power quality & harmonics · Voltage profile · Scheme features · Arc flash

7 · Economics & Payback

Equipment total ≈ $269,595 (2×S13-M-630/10 + hoist drive + ventilation/dewatering feeders + SVG + 500 kW diesel + modbus SCADA). No PV/BESS, so economics = capex + losses + transformer TCO: S13→SH15 amorphous upgrade saves ≈2,803 kWh/yr (≈$336/yr), ~3 yr payback; annual transformer+line losses ≈173,812 kWh (≈$20,857/yr). Diesel is standby-only. Hoist/ventilation/dewatering motors are POA.

$269,595
Equipment total
2×630 kVA S13-M
Transformer
$32,200
SVG dynamic compensation
~3 yr
SH15 upgrade payback
$20,857
Annual losses
500 kW standby
Diesel

8 · FAQ

What transformer for a 700 kW mine?
560 kW ≈ 589 kVA → 630 kVA tier; N+1 uses 2×S13-M-630/10, 94% loading after one-unit loss (consider 800 kVA for headroom).
Why must the hoist be on a VFD?
DOL starting the 250 kW hoist sags 12.2% (>10% limit); the four-quadrant VFD gives 2.7% dip plus regenerative braking.
What does four-quadrant mean?
The hoist motor works lifting and regenerates on lowering, feeding energy back to the DC bus — handled by the four-quadrant VFD + braking resistor/feedback unit.
How big a diesel?
500 kW standby covers grade-1 hoist 250 kW (V9 pass); 20 ft container, 3-day autonomy, <15 s auto-start.
How are ventilation and drainage powered?
As grade-2 loads on LV feeders, covered by N+1 dual-transformer redundancy; add a larger diesel only for continuous duty.
How is 36% THDi handled?
Stacked hoist VFDs push THDi to 36%; use SVG active filtering + detuned reactor, target ≤8%.
What happens to miners on an outage?
The diesel auto-transfers ≤15 s to the hoist to bring personnel up; ventilation keeps running on 3-day autonomy.
What's the payback on a better transformer?
SH15 amorphous vs S13 saves ≈2,803 kWh/yr ($336/yr), ~3 yr payback.
Is the price final?
No — $269,595 is a feasibility-level estimate; hoist/ventilation/dewatering motors are POA, and grid Ssc must be confirmed.

Special Considerations

  • N-1 94% loading after one-unit loss is near the limit — consider stepping the transformer to 800 kVA for headroom (V4/V13).
  • DOL starting the hoist would sag 12.2% (>10% limit) — the four-quadrant VFD is mandatory, with braking resistor/feedback unit.
  • If underground sections need explosion-proofing, add Ex equipment per hazardous zone separately (this scheme feeds the surface substation).
  • 500 kW diesel covers grade-1 hoist 250 kW (V9 pass); full vent/drainage backup needs a larger set.
  • Feasibility-level estimate; drawings pending a licensed design institute; confirm grid Ssc (500 MVA assumed).

Turn this into your project

Open this exact scenario pre-loaded in the Power System Configurator, then generate the full design document or the operation & techno-economic assessment.

Open in Power System Configurator →

One-Stop Supply of Conventional & Solar Power Equipment

From power distribution system design to solar energy — transformers, switchgear, substations and solar equipment, sized and quoted in one place. Use our calculators to get a complete bill of materials and FOB price.