QDTB®变压器官网

石化电力系统计算器

为炼油厂或化工厂设计高可靠性双电源电气系统 — 连续工艺负荷、N+1 / 2N 冗余、防爆分级和整流器谐波滤波,附 BOM 和单线图。

开始计算 石油化工与炼化解决方案
智能化与监控
在 BOM 与架构图中加入保护、计量与 SCADA(监控与二次)层。

为什么使用此计算器

连续工艺装置无法承受断电。本计算器为双电源、高可靠性配电系统进行选型,支持冗余配置,按 GB 50058 / IEC 60079 应用防爆(Ex)分级,并为整流器负荷选型失谐谐波滤波 — 满足 EPC 初步电力设计所需的一切。

Worked Examples

Example 1 — 2 MW Continuous Process (N+1, Zone 2, Rectifier Harmonics) · FOB $381,695
Petrochemical power system · N+1 · Zone 2 · 10kV/0.4kV
2,000 kVA transformer
S13-M-2000/10 · process 2,000 kW · THDi 25%
Process load
2,000 kW
Redundancy
N+1
Ex zone
Zone 2
Harmonic filter
221 kvar
Est. total (FOB)
POA
📦 Bill of Materials
EquipmentModelSpecQty
HV incoming panelKYN28A-12-630-315630 A / 31.5 kA · vacuum2
HV bus-tie panelKYN28A-12-630-315630 A / 31.5 kA · vacuum1
Main transformer (each)S13-M-2000/102000 kVA · Oil-Immersed · Copper · S132
LV incoming panelGGD-31503150 A busbar · In 2887 A2
LV bus-tie panelGGD-31503150 A busbar1
LV feeder panel (×2)GGD-3150distributes 10 circuits2
Cable branch box (LV)DFW-0.41-in / 4-out · 0.4 kV · 630 A2
Busway trunking (LV main feeder)Busway 4000 A4000 A · Cu/Al busway · 80 m · $1329/m1
Feeder cable — Process feeder 1 (×10)YJV 150 mm²150 mm² Cu · 304 A · ΔU 1.6% · $86.0/m10
Branch trunk cable (LV → branch box 1)YJV 240 mm² ×33× 240 mm² Cu · 1215 A · ΔU 1.3% · $123.0/m3
Branch trunk cable (LV → branch box 2)YJV 150 mm² ×22× 150 mm² Cu · 608 A · ΔU 1.6% · $86.0/m2
Main busbar (Cu)Cu 125×10125×10 · 2500 A rating · ref $147.8/mincluded
Grounding electrodeΦ20mm × 2.5m rodR₁ 39.6 Ω → 13 rod(s) ≤ 4 Ω13
Detuned PFC capacitor bank221 kvarautomatic · 7% detuned · 0.4 kV1
Series detuning reactor (7%)15.5 kvar189 Hz tuning · below 5th harmonic1
Explosion-proof (Ex) distribution boardEx d Zone 2Flameproof enclosure · IEC 60079 · quoted per project (POA — not included in estimate)1
Ex-rated motor control center (MCC)Ex d Zone 2Ex motor starters + VFD for pumps/compressors · IEC 60079 (POA — not included in estimate)1
Emergency / standby diesel generator1000 kVAlife-safety / standby power · 600 kVA required1
📐 Single-line diagram
CTCT50/5150/5187differentialFeed AFeed BKYN28A-12-630-315KYN28A-12-630-315HV bus-tieS13-M-2000/102000 kVA - Z=4%S13-M-2000/102000 kVA - Z=4%LV bus-tie0.4 kV0.4 kVProcess feeder 1 - 304 AYJV 150 mm2Process feeder 2 - 304 AYJV 150 mm2Process feeder 3 - 304 AYJV 150 mm2Process feeder 4 - 304 AYJV 150 mm2Process feeder 5 - 304 AYJV 150 mm2Process feeder 6 - 304 AYJV 150 mm2Process feeder 7 - 304 AYJV 150 mm2Process feeder 8 - 304 AYJV 150 mm2Process feeder 9 - 304 AYJV 150 mm2Process feeder 10 - 304 AYJV 150 mm2Grounding 13xdia20mmx2.5m rod
LEGENDBreaker (52)DisconnectorCTCT (current transformer)PTPT (voltage transformer)50/51Protection relay 50/51/51N/87kWhMeter (kWh)SPD (surge protection)Transformer
⚙️ Electrical schematic (protection & metering)
ELECTRICAL SCHEMATIC - PROTECTION & METERING10 kV / 0.4 kV - 2000 kVA - secondary circuits (schematic)INCOMING 10 kVCT120/5Aprotection CT5250/5151N87overcurrent / earth-fault / diffPT10kV/100Vbus PT (voltage)TRANSFORMER2000 kVAZ = 4%kWhrevenue meteringLV 520.4 kV LV BUSSPDCT.../5AProcess feeder 1 - 304 A50/51CT.../5AProcess feeder 2 - 304 A50/51CT.../5AProcess feeder 3 - 304 A50/51CT.../5AProcess feeder 4 - 304 A50/51CT.../5AProcess feeder 5 - 304 A50/51CT.../5AProcess feeder 6 - 304 A50/51CT.../5AProcess feeder 7 - 304 A50/51CT.../5AProcess feeder 8 - 304 A50/51CT.../5AProcess feeder 9 - 304 A50/51CT.../5AProcess feeder 10 - 304 A50/51
⛳ Grounding grid layout
SUBSTATION GROUNDING GRID LAYOUTsite 12 m x 8 m - ring earth electrode (schematic)TRANSFORMERR1R2R3R4R5R6R7R8R9R10R11R12R1312 mGround rods: 13 x dia 20 mm x 2.5 m copper-bonded steelRod spacing: 5 m (= 2 x rod length, ring electrode)Target resistance: <= 4 ohm (measure after installation)Standard: IEEE 80 / GB-T 50065 (earthing design) - indicative layout
🔌 Cable schedule & routing
CABLE SCHEDULEIDFromToCable (model / spec)LengthC0TransformerLV panelYJV 0.6/1kV 240 mm2 (2887 A)80 mC1LV panelProcess feeder 1YJV 150 mm2 (304 A)80 mC2LV panelProcess feeder 2YJV 150 mm2 (304 A)80 mC3LV panelProcess feeder 3YJV 150 mm2 (304 A)80 mC4LV panelProcess feeder 4YJV 150 mm2 (304 A)80 mC5Branch boxProcess feeder 5YJV 150 mm280 mC6Branch boxProcess feeder 6YJV 150 mm280 mC7Branch boxProcess feeder 7YJV 150 mm280 mC8Branch boxProcess feeder 8YJV 150 mm280 mC9Branch boxProcess feeder 9YJV 150 mm280 mC10Branch boxProcess feeder 10YJV 150 mm280 mROUTING (schematic)LV PANELL1L2L3L4L5L6L7L8... +3 feedersCable lengths are indicative (run-length based); confirm on site before installation.
🗄 Switchgear arrangement
SWITCHGEAR ARRANGEMENTpanel lineup (front view, schematic)HV INCOMINGKYN28A-12-630-315HV BUS-TIEKYN28A-12-630-315LV INCOMINGGGD-3150LV BUS-TIEGGD-3150FEEDERGGD-3150FEEDERGGD-3150BRANCH BOXDFW-0.47 panel(s) - each 91 mm (typical)Clearance / aisle per IEC 61936-1 - layout indicative
🛡 Protection configuration
PROTECTION CONFIGURATION10 kV / 0.4 kV - 2000 kVA - protection zones (schematic)INCOMING 10 kVCTCT 150/5A505151Novercurrent / earth-fault52TRANSFORMER2000 kVA - Z=4%8749differential + thermalCTCT 3000/5A505151NLV incoming protection520.4 kV LV BUSCTCT 3000/5A50/51BUS-TIECTCT 400/5A50/5151NProcess feeder 1304 ACTCT 400/5A50/5151NProcess feeder 2304 ACTCT 400/5A50/5151NProcess feeder 3304 ACTCT 400/5A50/5151NProcess feeder 4304 ACTCT 400/5A50/5151NProcess feeder 5304 ACTCT 400/5A50/5151NProcess feeder 6304 ACTCT 400/5A50/5151NProcess feeder 7304 ACTCT 400/5A50/5151NProcess feeder 8304 ACTCT 400/5A50/5151NProcess feeder 9304 ACTCT 400/5A50/5151NProcess feeder 10304 AProtection layout & CT ratios are schematic / illustrative final settings per IEC 60255 / IEEE 242.
📋 Protection settings
CircuitProtectionSettingTimeStandard
HV incoming 10 kV50 instantaneous924 AinstIEC 60255-151 / IEEE 242
HV incoming 10 kV51 overcurrent139 A0.5 sIEC 60255-151 / IEEE 242
HV incoming 10 kV51N earth-fault23 A0.5 sIEC 60364-4-41
Transformer 2000 kVA87 differential23 AinstIEEE C37.91 / GB/T 14285
Transformer 2000 kVA49 thermal overload89% of ratedalarm 90%IEC 60076-7 / IEEE C57.91
LV incoming 0.4 kV50 instantaneous23094 AinstIEC 60947-2
LV incoming 0.4 kV51 overcurrent3464 A0.3 sIEC 60947-2 / IEC 60255
LV incoming 0.4 kV51N earth-fault577 A0.3 sIEC 60364-4-41
LV bus-tie50/51 overcurrent3464 A0.3 sIEC 60947-2
Process feeder 150/51/51N (MCCB)Ir 334 A - Im 2431 A - Ig 61 A0.1 s (grading)IEC 60947-2 / IEC 60255
Process feeder 250/51/51N (MCCB)Ir 334 A - Im 2431 A - Ig 61 A0.1 s (grading)IEC 60947-2 / IEC 60255
Process feeder 350/51/51N (MCCB)Ir 334 A - Im 2431 A - Ig 61 A0.1 s (grading)IEC 60947-2 / IEC 60255
Process feeder 450/51/51N (MCCB)Ir 334 A - Im 2431 A - Ig 61 A0.1 s (grading)IEC 60947-2 / IEC 60255
Process feeder 550/51/51N (MCCB)Ir 334 A - Im 2431 A - Ig 61 A0.1 s (grading)IEC 60947-2 / IEC 60255
Process feeder 650/51/51N (MCCB)Ir 334 A - Im 2431 A - Ig 61 A0.1 s (grading)IEC 60947-2 / IEC 60255
+4 more feeders50/51/51N (MCCB)per feeder load0.1 s (grading)IEC 60947-2
Settings are illustrative starting points — confirm with a protection coordination study per IEC 60255 / IEEE 242.
📚 Calculation book
CALCULATION BOOK
2000 kVA - 10kV/0.4kV - N+1 - illustrative
1. Load calculation
Standard: IEC 60076 - IEC 60364-5-52
ParameterFormulaValue
Connected loadP = sum(kW)2,000 kW
Demand factorKd0.85
Demand powerPd = P x Kd1,700 kW
Power factorcos(phi) before -> after0.95 -> 0.95
Design apparent powerSd = Pd / cos(phi)1,789 kVA
Transformer loadingSd / Srated89%
2. Short-circuit calculation
Standard: IEC 60909
ParameterFormulaValue
System impedance (pu)Zs = S / Ssc0.40% (on 2000 kVA base)
Transformer impedanceZt = Z%4%
Total impedanceZ = Zt + Zs4.40%
LV prospective IscIsc = In / Z65.6 kA
HV prospective IscIsc = Ssc / (sqrt(3) x V)28.9 kA
Breaking checkIcu >= IscLV 80 kA (1.2x margin) PASS
3. Voltage drop
Standard: IEC 60364-5-52 Annex G
ParameterFormulaValue
Main feederdU = sqrt(3) x I x L x R / V240 mm2 - dU 1.34% @ 80 m
Limitmax 3%within limit
Transformer volt. reg.dU ~ loading x Z% x sin(phi)1.1% at full load
4. Reactive power / harmonics
Standard: IEC 61921 (PFC) - IEEE 519 (harmonics)
ParameterFormulaValue
Required compensationQc = Pd x (tan1 - tan2)0 kvar
PFC bankstandard step0 kvar
Detuned reactorp = 6%n/a
5. Grounding
Standard: IEC 60364-5-54 earthing arrangements and protective conductors LV earthing target 10 ohm (TN systems); 4 ohm used as a conservative design target - target 4 ohm
ParameterFormulaValue
Single rod resistanceR1 = rho/(2 x pi x L) x ln(4L/d)39.6 ohm
Rods requiredn = R1 / (target x 0.8)13 rod(s) <= 4 ohm
Rod specdia x length20 mm x 2.5 m
This calculation book is illustrative it consolidates the computed values with the referenced standards. A licensed engineer must verify and seal final design documents for construction.
🔧 Secondary schematic (control & signal)
SECONDARY CONTROL & SIGNAL CIRCUIT0.4 kV circuit breaker close/trip + indication + interlock (TYPICAL)+control supplyCS (close)interlock52Cclose coil-TC (trip)prot trip52Ttrip coilSIGNAL (indication)52a (closed)REDbreaker closed-TYPICAL CIRCUITStandard control/signal scheme for Process feeder 1.Project detailing required (wiring, terminal assignment).
🔩 Terminal strip (typical)
TERMINAL STRIP (TYPICAL)X1 secondary wiring terminals (typical project detailing required)TerminalFunctionWireX1:1control supply L+1.5 mm2X1:2control supply L-1.5 mm2X1:3close command1.5 mm2X1:4trip command1.5 mm2X1:5breaker 52a status1.5 mm2X1:6breaker 52b status1.5 mm2X1:7trip circuit healthy1.5 mm2X1:8earth / shield2.5 mm2
🌀 Rectifier harmonic mitigation
ParameterValue
Rectifier load400 kW · THDi 25%
Fundamental current770 A · harmonic current 192 A
Compensation221 kvar bank + 7% reactor (15.5 kvar)
Resonance check5th harmonic 250 Hz > 189 Hz → safe ✓
📏 Standard basis (依据标准)
TopicStandard
Standard basisIEC · IEC 60364-5-52
Conductor ampacityIEC 60364-5-52 Table B.52.2–B.52.5 (copper, 3 loaded conductors, 30°C ambient, PVC) — typical/rounded values, conservative (±3%)
Voltage-drop limitIEC 60364-5-52 Annex G · max drop 3%
Winding temp riseIEC 60076-2 — winding temp rise 65 K (Class A insulation, ONAN)
kVA ratingsIEC 60076-1 R10 preferred numbers
Breaker framesIEC 60947-2 frame sizes (In)
Grounding targetIEC 60364-5-54 earthing arrangements and protective conductors — LV earthing target ≤ 10 Ω (TN systems); 4 Ω used as a conservative design target · target 4 Ω
Power supply reliabilityGB 50052 — code for design of electric power supply systems (dual-source for critical loads)
Explosive atmospheresGB 50058 · IEC 60079 — electrical apparatus for explosive gas atmospheres (Ex)
Power quality (harmonics)GB/T 14549 · IEC 61642 — harmonics in public/industrial networks & detuned filters
Power transformersIEC 60076 — power transformers
🧮 How it was calculated
1. Continuous process load = 2,000 kW (N-1 continuity)
2. Redundancy N+1 → 2 transformers + bus-tie (100% backup)
3. Rectifier harmonic source: 400 kW · THDi 25% → Ih = 770 × 25% = 192 A
4. Detuned filter: Qc = 400 × (tanφ₁ − tanφ₂) = 221 kvar · 7% reactor (f_res 189 Hz)
5. Resonance check: 5th harmonic 250 Hz above 189 Hz → detuned (safe)
6. Loads: P=2,000 kW, PF 0.95, 10 circuits
7. Demand: 2,000 × 0.85 = 1,700 kW
8. PFC: Qc = 1,700 × (0.329 − 0.329) = 0 kVAR → 0 kVAR bank
9. Transformer: S = 1,700 ÷ 0.95 = 1789.5 kVA → 2,000 kVA standard
10. Loading: 1,789 ÷ 2,000 = 89% (good range)
11. Voltage regulation: 89% × 4% × sinφ ≈ 1.1% at full load
12. HV: In 115.5 A, Isc 28.9 kA → KYN28A-12-630-315
13. LV: In 2887 A, Isc 65.6 kA (Xfmr Z 4% + system 0.4%) → GGD-3150, 2 feeder panel(s)
14. Cable branch boxes: 2 × DFW-0.4 (1-in/4-out) for feeder grouping
15. Grounding: R₁ 39.6 Ω → 13 rod(s)
16. Main feeder: 7× 240 mm² · ΔU 1.34% — OK · busway 4000 A
Summary
Estimated total (FOB Qingdao, EXW) — priced equipment$381,695
📋 Design notes
Pricing basis: FOB Qingdao (EXW) equipment price. Freight, duty and installation are not included — add for landed economics.
Transformer loading: 89% at design demand — good range.
Short-circuit check: HV 28.9 kA vs 31.5 kA (1.1× margin) · LV 65.6 kA vs 80 kA (1.2× margin).
Voltage regulation: ≈ 1.1% at full load (typical limit 5%).
Copper price linkage: Copper-wound transformer price tracks LME copper (current $14,115/t · 2026-09-14 · LME Copper (Sina hf_CAD)).
Parallel conductors: Single-cable ampacity exceeded — parallel conductors specified: main feeder 7× 240 mm², branch trunk 1 3× 240 mm², branch trunk 2 2× 150 mm² (per IEC 60364-5-52 / GB 50054).
Cable & grounding pricing: Cable conductors and grounding are priced from the confirmed cables-trays-grounding price reference (per-metre copper YJV; aluminium remains POA). The main copper busbar is POA — its length is project-specific.
Busway (high-current feeders): LV current 2887 A exceeds the 2500 A busbar limit — a 4000 A busway trunking system is specified instead of parallel cables.
Reliability: N+1 topology provides concurrent maintainability — required for continuous process plants.
Explosion protection: Zone classification Zone 2: switchgear and motors must be Ex-certified per GB 50058 / IEC 60079 (quoted per project).
Ex motors & VFD: Process pumps and compressors in Zone 2 need Ex-certified motors with VFD (or soft-start) control via an Ex-rated MCC — quoted per project.
Emergency / standby power: A standby diesel generator (≈600 kVA) covers critical process loads on loss of the normal supply — sized per project and the plant’s safety-instrumented-system (SIS) requirements.
Process loads: Continuous process load typically splits into compressors (~40%), pumps (~25%), heaters (~20%) and utilities/instrumentation (~15%) — adjust per your actual process list.
Harmonics: Rectifier load generates 25% THDi — a 7% detuned filter keeps the branch inductive at the 5th harmonic (safe).

计算过程说明

选型计算方式

变压器按目标功率因数下的连续工艺负荷选型;N+1 / 2N 冗余决定并联变压器数量和独立供电路径。整流器谐波电流 Ih = I₁ × THDi;带 p% 串联电抗器的失谐电容器组 Qc = P × (tanφ₁ − tanφ₂),使支路在主要谐波以下保持感性。

适用标准

选型参考 GB 50052(供电设计)、GB 50058 和 IEC 60079(爆炸性环境)、GB/T 14549 和 IEC 61642(谐波)以及 IEC 60076(变压器)。

常见问题

防爆(Ex)区域划分对电气设备意味着什么?

危险区按爆炸性气体(IEC 60079 的 Zone 0/1/2)或粉尘(Zone 20/21/22)出现的概率划分。Zone 1/2 内的电气设备须有与气体组别和温度等级匹配的 Ex 认证(如 Ex d、Ex e、Ex n)。正确选 Ex 等级会使开关柜成本增加 20-50%;计算器可选分区并标注 Ex 型 BOM。

石化厂为什么需要双电源供电?

连续流程装置(炼油、乙烯、合成氨)不能承受失电——重新开车可能需数天并损失数百万。按 GB 50052 负荷分级,关键负荷采用双路独立电源 + 自动转换(ATS)和 N+1 或 2N 冗余。计算器可设冗余等级并据此配置应急/备用回路。

石化厂的整流装置谐波如何处理?

电解和电镀整流器注入 5、7、11 次谐波。若公共连接点总谐波畸变超过 IEEE 519 限值(多数系统为 5% THD),需加装去谐电容器组(7% 串联电抗)或有源滤波器(APF)。计算器在 THDi 超过约 15-20% 时按 7% 去谐系数配置补偿。

石化中低压变压器典型阻抗是多少?

石化厂配电变压器阻抗通常 6%(uk),大型电机回路有时用 8% 以限制短路电流。阻抗越高短路电流越小但电压调整率越差,6% 对 10/0.4 kV、1000-2500 kVA 单元可兼顾两者。计算器计算故障水平时采用标准 uk 值。

GB 50052 对连续生产负荷如何分级?

GB 50052 将负荷分为一、二、三级。连续石化装置属一级负荷,需两路独立电源;关键安全负荷(紧急停车、消防泵)属『一级重要负荷』,还需柴发或 EPS 等应急电源。计算器的冗余与应急电源选项即对应这些分级。

炼厂工艺负荷的需用系数怎么定?

炼厂工艺负荷近乎连续运行,主装置需用系数高达 0.8-0.9,公用与辅助系统 0.6-0.7。2000 kW 装机工艺负荷、0.85 需用系数、0.95 功率因数约需 1790 kVA,取 2000 kVA 变压器。计算器用这些系数避免超配与欠配。

嵌入此计算器

复制下方 iframe 代码,即可将此计算器嵌入任何网站。嵌入页面为 noindex,适配任意宽度。

相关计算器

结果为工程估算,仅供参考。最终设计须由当地持证工程师根据现场条件和适用规范确认。价格为 FOB 青岛(EXW),不含运费、关税及安装费。

Design the complete system

Move to the full Power System Configurator — 4 layers, 13 drawings, protection schedule, BOM and price.

Open Power System Configurator →

发送我的完整设计报告

免费获取完整设备清单(BOM)、单线图、计算步骤与 FOB 报价的 PDF 报告,无需注册。

💬 WhatsApp 咨询

您的信息仅用于回复询盘,不用于任何其他用途。