regenerative VFD (energy feedback on lowering) · per crane
4
Shore power supply (岸电)
300 kVA
50/60 Hz frequency converter + shore connection panel · IEC/ISO 80005-1 · quoted per project
1
📐 Single-line diagram
⚙️ Electrical schematic (protection & metering)
⛳ Grounding grid layout
🔌 Cable schedule & routing
🗄 Switchgear arrangement
🛡 Protection configuration
📋 Protection settings
Circuit
Protection
Setting
Time
Standard
HV incoming 35 kV
50 instantaneous
211 A
inst
IEC 60255-151 / IEEE 242
HV incoming 35 kV
51 overcurrent
32 A
0.5 s
IEC 60255-151 / IEEE 242
HV incoming 35 kV
51N earth-fault
5 A
0.5 s
IEC 60364-4-41
Transformer 1600 kVA
49 thermal overload
79% of rated
alarm 90%
IEC 60076-7 / IEEE C57.91
LV incoming 0.4 kV
50 instantaneous
18475 A
inst
IEC 60947-2
LV incoming 0.4 kV
51 overcurrent
2771 A
0.3 s
IEC 60947-2 / IEC 60255
LV incoming 0.4 kV
51N earth-fault
462 A
0.3 s
IEC 60364-4-41
Quay crane 1
50/51/51N (MCCB)
Ir 1134 A - Im 8248 A - Ig 206 A
0.1 s (grading)
IEC 60947-2 / IEC 60255
Quay crane 2
50/51/51N (MCCB)
Ir 1134 A - Im 8248 A - Ig 206 A
0.1 s (grading)
IEC 60947-2 / IEC 60255
Quay crane 3
50/51/51N (MCCB)
Ir 1134 A - Im 8248 A - Ig 206 A
0.1 s (grading)
IEC 60947-2 / IEC 60255
Quay crane 4
50/51/51N (MCCB)
Ir 1134 A - Im 8248 A - Ig 206 A
0.1 s (grading)
IEC 60947-2 / IEC 60255
Settings are illustrative starting points — confirm with a protection coordination study per IEC 60255 / IEEE 242.
📚 Calculation book
CALCULATION BOOK
1600 kVA - 35kV/0.4kV - single - illustrative
1. Load calculation
Standard: IEC 60076 - IEC 60364-5-52
Parameter
Formula
Value
Connected load
P = sum(kW)
2,000 kW
Demand factor
Kd
0.6
Demand power
Pd = P x Kd
1,200 kW
Power factor
cos(phi) before -> after
0.70 -> 0.95
Design apparent power
Sd = Pd / cos(phi)
1,263 kVA
Transformer loading
Sd / Srated
79%
2. Short-circuit calculation
Standard: IEC 60909
Parameter
Formula
Value
System impedance (pu)
Zs = S / Ssc
0.32% (on 1600 kVA base)
Transformer impedance
Zt = Z%
4%
Total impedance
Z = Zt + Zs
4.32%
LV prospective Isc
Isc = In / Z
53.5 kA
HV prospective Isc
Isc = Ssc / (sqrt(3) x V)
8.2 kA
Breaking check
Icu >= Isc
LV 65 kA (1.2x margin) PASS
3. Voltage drop
Standard: IEC 60364-5-52 Annex G
Parameter
Formula
Value
Main feeder
dU = sqrt(3) x I x L x R / V
300 mm2 - dU 1.50% @ 100 m
Limit
max 3%
within limit
Transformer volt. reg.
dU ~ loading x Z% x sin(phi)
1.0% at full load
4. Reactive power / harmonics
Standard: IEC 61921 (PFC) - IEEE 519 (harmonics)
Parameter
Formula
Value
Required compensation
Qc = Pd x (tan1 - tan2)
0 kvar
PFC bank
standard step
0 kvar
Detuned reactor
p = 6%
n/a
5. Grounding
Standard: IEC 60364-5-54 earthing arrangements and protective conductors LV earthing target 10 ohm (TN systems); 4 ohm used as a conservative design target - target 4 ohm
Parameter
Formula
Value
Single rod resistance
R1 = rho/(2 x pi x L) x ln(4L/d)
39.6 ohm
Rods required
n = R1 / (target x 0.8)
13 rod(s) <= 4 ohm
Rod spec
dia x length
20 mm x 2.5 m
This calculation book is illustrative it consolidates the computed values with the referenced standards. A licensed engineer must verify and seal final design documents for construction.
Cable & grounding pricing:Cable conductors and grounding are priced from the confirmed cables-trays-grounding price reference (per-metre copper YJV; aluminium remains POA). The main copper busbar is POA — its length is project-specific.
Busway (high-current feeders):For LV feeders above ~2500 A, a busway (母线槽) trunking system is recommended instead of parallel cables.
Impact load:Impact factor 1.3× — rapid load swings from cranes/arc furnaces cause voltage flicker; dynamic SVC/SVG compensation is required.
Starting:Largest 500 kW drive started via VFD draws a 2.2% bus dip (within the 10% limit).
Harmonics:30% THDi from VFD/rectifier loads — a 7% detuned filter keeps the branch inductive below the 5th harmonic.
SVC/SVG pricing:Dynamic reactive compensation is priced at $183,000/unit (±5 Mvar, FOB reference).
Crane regenerative drive:Quay cranes use four-quadrant (regenerative) VFDs that feed lowering energy back to the bus — this reduces energy consumption and DC-bus overvoltage, quoted per project.
Shore power (岸电):A shore power supply converts the port grid to the vessel’s voltage/frequency (IEC/ISO 80005-1) so berthed ships shut down their auxiliary engines — quoted per project.
计算过程说明
选型计算方式
冲击峰值 = 连接负载 × 冲击系数。无功补偿 Qc = P × (tanφ₁ − tanφ₂) 用于校正较低的自然功率因数,采用快速 SVC/SVG 抑制闪变,并配置失谐滤波组抑制谐波。最大驱动启动 kVA 需对照电压跌落限值进行校验(对闪变敏感母线通常为 10%)。