QDTB®变压器官网

风光储混合配置器

配置风电 + 光伏 + 储能混合电站 — 容量匹配与互补性分析、P50/P90 发电量、全成本 LCOE,以及带单线图的设备报价 BOM。

开始计算 可再生能源解决方案

为什么使用此计算器

风电与光伏具有互补性 — 风电在夜间和冬季达到峰值,光伏在正午和夏季达到峰值。本计算器将三种技术统筹选型,根据您的风光资源估算年发电量,并计算透明、保守的全成本 LCOE。

Worked Examples

Example 1 — 20 MW Wind + 30 MW PV + 20 MWh Storage (Grid) · FOB $54,500,000
Wind + Solar + Storage hybrid · 35kV · grid-connected
91,980 MWh/yr
P50 91,980 · P90 78,183 MWh/yr · LCOE $61.7/MWh
Wind
20 MW
Solar
30 MWp
Storage
20 MWh / 4 h
LCOE (P50)
$61.7/MWh
Est. BOM (FOB)
POA
📦 Bill of Materials
EquipmentModelSpecQty
Wind turbine generators20 MW totalonshore · turbine only $282/kW (FOB reference; tower & BOP quoted per project)1
Wind farm box transformer22000 kVA> 1600 kVA — outside catalogue, quoted per project1
Wind collector cable (集电电缆)35 kV MVradial collector feeders + trenching · quoted per project1
Site access roads & crane pads (场内道路)civilturbine access roads, hardstands & foundations · quoted per project1
Wind turbine erection & crane (吊装)installationheavy-lift crane + erection crew · quoted per project1
PV modules54545 × 550 Wpmono PERC · 30 MWp DC1
String inverters30 MW ACthree-phase · grid-tied1
PV mounting structure30 MWpground-mount1
Battery energy storage (BESS)20 MWhLFP · 90% DoD · 90% RTE1
Power conversion system (PCS)5000 kW4 h duration · bidirectional1
Battery management system (BMS)clustercell monitoring & balancing1
Step-up power transformer52.6 MVAMV/35 kV grid connection · outside distribution catalogue1
📐 Single-line diagram
Wind farm20 MW - 30% CFPV plant30 MWp - 4.5 kWh/m2/dBattery (BESS)20 MWh / 4 hStep-up transformer52.6 MVA (POA)Grid35 kV connection
LEGENDBreaker (52)CTCT (current transformer)PTPT (voltage transformer)50/51Protection relay 50/51/51NkWhMeter (kWh)SPD (surge protection)
⚙️ Electrical schematic (protection & metering)
ELECTRICAL SCHEMATIC - PROTECTION & METERING35 kV / 35 kV - 52632 kVA - secondary circuits (schematic)INCOMING 35 kVCT.../5Aprotection CT5250/5151Novercurrent / earth-faultPT35kV/100Vbus PT (voltage)TRANSFORMER52632 kVAZ = 10%kWhrevenue meteringLV 5235 kV LV BUSSPDCT.../5AWind farm - 330 A50/51CT.../5APV plant - 495 A50/51CT.../5ABESS - 82 A50/51
⛳ Grounding grid layout
SUBSTATION GROUNDING GRID LAYOUTsite 40 m x 30 m - ring earth electrode (schematic)HYBRID PLANTR1R2R3R4R5R6R7R840 mGround rods: 8 x dia 16 mm x 2.5 m copper-bonded steelRod spacing: 5 m (= 2 x rod length, ring electrode)Target resistance: <= 4 ohm (measure after installation)Standard: IEEE 80 / GB-T 50065 (earthing design) - indicative layout
🔌 Cable schedule & routing
CABLE SCHEDULE - HYBRID PLANTIDFromToCable (model / spec)LengthC1Wind farm35 kV collector busYJV 26/35kV - 330 A11000 mC2PV plant35 kV collector busYJV 26/35kV - 495 A11000 mC3BESS35 kV collector busYJV 26/35kV - 82 A11000 mPOI35 kV bus35 kV POI (step-up 52632 kVA)35 kV XLPE16500 mROUTING (schematic)LV PANELL1L2L3L4Cable lengths are indicative (run-length based); confirm on site before installation.
🗄 Switchgear arrangement
SWITCHGEAR ARRANGEMENT - HYBRID PLANTpanel lineup (front view, schematic)CB1Wind farmCB2PV plantCB3BESSTR52632 kVAPOI35 kV5 panel(s) - each 128 mm (typical)Clearance / aisle per IEC 61936-1 - layout indicative
🛡 Protection configuration
PROTECTION CONFIGURATION35 kV / 35 kV - 52632 kVA - protection zones (schematic)INCOMING 35 kVCTCT 900/5A505151Novercurrent / earth-fault52TRANSFORMER52632 kVA - Z=10%8749differential + thermalCTCT 900/5A505151NLV incoming protection5235 kV LV BUSCTCT .../5A50/5151NWind farm330 ACTCT .../5A50/5151NPV plant495 ACTCT .../5A50/5151NBESS82 AProtection layout & CT ratios are schematic / illustrative final settings per IEC 60255 / IEEE 242.
📋 Protection settings
CircuitProtectionSettingTimeStandard
Wind farm collector50/51 overcurrent396 A0.1 sIEC 60255-151
PV plant collector50/51 overcurrent594 A0.1 sIEC 60255-151
BESS collector50/51 overcurrent99 A0.1 sIEC 60255-151
Step-up transformer 52632 kVA87 differential0.2 x CTinstIEEE C37.91 / GB/T 14285
Step-up transformer 52632 kVA50/51 overcurrent1042 A0.3 sIEC 60255-151
Step-up transformer 52632 kVA49 thermal100% ratedalarm 90%IEC 60076-7 / IEEE C57.91
Grid interconnection 35 kVanti-islanding / ROCOFper grid codeper grid codeIEEE 1547 / GB/T 19964-2024
Grid interconnection 35 kVAGC / AVC dispatch interfaceper grid codeper grid codeGB/T 19963 / IEEE 1547
Dispatch data networkIEC 60870-5-104 telecontrolRTU + comm linkper grid codeIEC 60870-5-104
Power forecastPV / wind power forecast interface15-min resolutionper grid codeGB/T 19964-2024
Settings are illustrative starting points — confirm with a protection coordination study per IEC 60255 / IEEE 242.
📚 Calculation book
CALCULATION BOOK
Wind-solar-storage hybrid - 35 kV - grid-tied - illustrative
1. Wind resource
Standard: IEC 61400 (wind energy)
ParameterFormulaValue
CapacityPwind20 MW
Capacity factorcf @ 7 m/s30%
Annual energyE = P x cf x 876052,560 MWh/yr
2. PV resource
Standard: IEC 61724
ParameterFormulaValue
CapacityPpv30 MWp
Specific yieldGHI x 365 x PR1314 kWh/kWp/yr
Annual energyE = P x specific yield39,420 MWh/yr
3. Storage
Standard: IEC 62933 (EES)
ParameterFormulaValue
Energy capacityMWh20 MWh / 4 h
PowerP = MWh / h5.0 MW
Round-trip efficiencyrte90% - DoD 90%
4. Generation & complementarity
Standard: resource assessment (illustrative)
ParameterFormulaValue
Total energy (P50)E_wind + E_pv91,980 MWh/yr
P90P50 x 0.8578,183 MWh/yr
Complementaritywind sharestrong (balanced wind + solar)
5. Step-up & economics
Standard: IEC 60076 - NREL ATB
ParameterFormulaValue
Step-up transformerkVA52632 kVA (52.6 MVA)
Installed CAPEXwind + PV + storage$54,500,000
LCOE (P50)full-cost$61.7/MWh
This calculation book is illustrative resource factors and costs are typical assumptions. A licensed engineer must verify and seal final design documents.
🔧 Secondary schematic (control & signal)
SECONDARY CONTROL & SIGNAL CIRCUIT35 kV circuit breaker close/trip + indication + interlock (TYPICAL)+control supplyCS (close)interlock52Cclose coil-TC (trip)prot trip52Ttrip coilSIGNAL (indication)52a (closed)REDbreaker closed-TYPICAL CIRCUITStandard control/signal scheme for COLLECTOR FEEDER 1.Project detailing required (wiring, terminal assignment).
🔩 Terminal strip (typical)
TERMINAL STRIP (TYPICAL)X1 secondary wiring terminals (typical project detailing required)TerminalFunctionWireX1:1control supply L+1.5 mm2X1:2control supply L-1.5 mm2X1:3close command1.5 mm2X1:4trip command1.5 mm2X1:5breaker 52a status1.5 mm2X1:6breaker 52b status1.5 mm2X1:7trip circuit healthy1.5 mm2X1:8earth / shield2.5 mm2
🌬️☀️ Resource & generation
ParameterValue
Wind capacity factor30% at 7 m/s (illustrative)
Wind energy52,560 MWh/yr
PV specific yield1,314 kWh/kWp/yr (4.5 kWh/m²/day, PR 0.8)
PV energy39,420 MWh/yr
Complementaritystrong (balanced wind + solar)
💰 Economics (full-cost, illustrative)
ParameterValue
Installed CAPEX$54,500,000 (wind $1,150/kW · PV $850/kW · storage $300/kWh)
Annual OPEX$1,000,000
P50 generation91,980 MWh/yr
P90 generation78,183 MWh/yr
LCOE (P50)$61.7/MWh
LCOE (P90)$72.6/MWh
📏 Standard basis (依据标准)
TopicStandard
Wind grid connectionGB/T 19963 — technical rule for connecting wind farm to power system
PV grid connectionGB/T 19964-2024 — technical rule for connecting photovoltaic power station to power system
Wind turbinesIEC 61400 — wind turbines (design requirements)
Battery storageGB/T 36547 — technical rule for electrochemical energy storage connecting to power grid
🧮 How it was calculated
1. Wind: 20 MW × CF 0.30 (at 7 m/s) × 8760 h = 52,560 MWh/yr
2. PV: 30 MWp × 4.5 kWh/m²/day × 365 × PR 0.8 = 39,420 MWh/yr
3. Combined P50 = 91,980 MWh/yr · P90 = 78,183 MWh/yr (0.85 × P50, illustrative)
4. Storage: 20 MWh / 4 h = 5000 kW PCS · DoD 90% · RTE 90%
5. Complementarity: strong (balanced wind + solar)
6. Full-cost LCOE = (CAPEX × CRF + OPEX) ÷ energy = ($54,500,000 × 0.0858 + $1,000,000) ÷ 91,980 MWh = $61.7/MWh (illustrative)
Summary
Estimated total (FOB Qingdao, EXW) — priced equipment$14,577,056
📋 Design notes
Economics basis (illustrative): LCOE uses installed-cost basis: wind $1,150/kW, PV $850/kW, storage $300/kWh (NREL 2024 ATB / Lazard 2024 typical ranges). Excludes taxes, financing fees, degradation and curtailment. Actual project economics vary by site.
BOM vs economics reconciliation (P2-12): The BOM FOB total ($14,577,056) prices only the catalogue items (PV + storage); wind turbines and the step-up transformer are POA. The illustrative installed CAPEX ($54,500,000) adds wind at $1,150/kW and covers full turnkey installed cost — the two figures use different bases and are not directly comparable.
P50 / P90: P50 = expected annual generation; P90 = 0.85 × P50 (conservative one-year exceedance, illustrative resource variability). A bankable P90 uses site-measured interannual variability, not a fixed 0.85 factor.
Wind BOP: The wind farm balance-of-plant — collector cables, site access roads, crane pads, foundations and heavy-lift erection — is quoted per project and is included in the illustrative installed CAPEX (not the FOB BOM).
POA equipment: Wind turbine generators and the step-up power transformer (outside the distribution catalogue) are quoted per project (POA) — the BOM prices only the PV and storage from the catalogue.
Grid mode: Grid-connected: the hybrid plant sells energy and uses storage for shifting/firming.
Example 2 — 50 MW PV + 30 MWh Storage (Off-grid) · FOB $51,500,000
Wind + Solar + Storage hybrid · 35kV · off-grid
80,300 MWh/yr
P50 80,300 · P90 68,255 MWh/yr · LCOE $65.0/MWh
Wind
0 MW
Solar
50 MWp
Storage
30 MWh / 2 h
LCOE (P50)
$65.0/MWh
Est. BOM (FOB)
POA
📦 Bill of Materials
EquipmentModelSpecQty
PV modules90909 × 550 Wpmono PERC · 50 MWp DC1
String inverters50 MW ACthree-phase · grid-tied1
PV mounting structure50 MWpground-mount1
Battery energy storage (BESS)30 MWhLFP · 90% DoD · 90% RTE1
Power conversion system (PCS)15000 kW2 h duration · bidirectional1
Battery management system (BMS)clustercell monitoring & balancing1
Step-up power transformer52.6 MVAMV/35 kV grid connection · outside distribution catalogue1
📐 Single-line diagram
Wind farm0 MW - 23% CFPV plant50 MWp - 5.5 kWh/m2/dBattery (BESS)30 MWh / 2 hStep-up transformer52.6 MVA (POA)Load / microgridoff-grid
LEGENDBreaker (52)CTCT (current transformer)PTPT (voltage transformer)50/51Protection relay 50/51/51NkWhMeter (kWh)SPD (surge protection)
⚙️ Electrical schematic (protection & metering)
ELECTRICAL SCHEMATIC - PROTECTION & METERING35 kV / 35 kV - 52632 kVA - secondary circuits (schematic)INCOMING 35 kVCT.../5Aprotection CT5250/5151Novercurrent / earth-faultPT35kV/100Vbus PT (voltage)TRANSFORMER52632 kVAZ = 10%kWhrevenue meteringLV 5235 kV LV BUSSPDCT.../5APV plant - 825 A50/51CT.../5ABESS - 247 A50/51
⛳ Grounding grid layout
SUBSTATION GROUNDING GRID LAYOUTsite 40 m x 30 m - ring earth electrode (schematic)HYBRID PLANTR1R2R3R4R5R6R7R840 mGround rods: 8 x dia 16 mm x 2.5 m copper-bonded steelRod spacing: 5 m (= 2 x rod length, ring electrode)Target resistance: <= 4 ohm (measure after installation)Standard: IEEE 80 / GB-T 50065 (earthing design) - indicative layout
🔌 Cable schedule & routing
CABLE SCHEDULE - HYBRID PLANTIDFromToCable (model / spec)LengthC1PV plant35 kV collector busYJV 26/35kV - 825 A13000 mC2BESS35 kV collector busYJV 26/35kV - 247 A13000 mPOI35 kV bus35 kV POI (step-up 52632 kVA)35 kV XLPE19500 mROUTING (schematic)LV PANELL1L2L3Cable lengths are indicative (run-length based); confirm on site before installation.
🗄 Switchgear arrangement
SWITCHGEAR ARRANGEMENT - HYBRID PLANTpanel lineup (front view, schematic)CB1PV plantCB2BESSTR52632 kVAPOI35 kV4 panel(s) - each 160 mm (typical)Clearance / aisle per IEC 61936-1 - layout indicative
🛡 Protection configuration
PROTECTION CONFIGURATION35 kV / 35 kV - 52632 kVA - protection zones (schematic)INCOMING 35 kVCTCT 900/5A505151Novercurrent / earth-fault52TRANSFORMER52632 kVA - Z=10%8749differential + thermalCTCT 900/5A505151NLV incoming protection5235 kV LV BUSCTCT .../5A50/5151NPV plant825 ACTCT .../5A50/5151NBESS247 AProtection layout & CT ratios are schematic / illustrative final settings per IEC 60255 / IEEE 242.
📋 Protection settings
CircuitProtectionSettingTimeStandard
PV plant collector50/51 overcurrent990 A0.1 sIEC 60255-151
BESS collector50/51 overcurrent297 A0.1 sIEC 60255-151
Step-up transformer 52632 kVA87 differential0.2 x CTinstIEEE C37.91 / GB/T 14285
Step-up transformer 52632 kVA50/51 overcurrent1042 A0.3 sIEC 60255-151
Step-up transformer 52632 kVA49 thermal100% ratedalarm 90%IEC 60076-7 / IEEE C57.91
Grid interconnection 35 kVanti-islanding / ROCOFper grid codeper grid codeIEEE 1547 / GB/T 19964-2024
Grid interconnection 35 kVAGC / AVC dispatch interfaceper grid codeper grid codeGB/T 19963 / IEEE 1547
Dispatch data networkIEC 60870-5-104 telecontrolRTU + comm linkper grid codeIEC 60870-5-104
Power forecastPV / wind power forecast interface15-min resolutionper grid codeGB/T 19964-2024
Settings are illustrative starting points — confirm with a protection coordination study per IEC 60255 / IEEE 242.
📚 Calculation book
CALCULATION BOOK
Wind-solar-storage hybrid - 35 kV - off-grid - illustrative
1. Wind resource
Standard: IEC 61400 (wind energy)
ParameterFormulaValue
CapacityPwind0 MW
Capacity factorcf @ 6 m/s23%
Annual energyE = P x cf x 87600 MWh/yr
2. PV resource
Standard: IEC 61724
ParameterFormulaValue
CapacityPpv50 MWp
Specific yieldGHI x 365 x PR1606 kWh/kWp/yr
Annual energyE = P x specific yield80,300 MWh/yr
3. Storage
Standard: IEC 62933 (EES)
ParameterFormulaValue
Energy capacityMWh30 MWh / 2 h
PowerP = MWh / h15.0 MW
Round-trip efficiencyrte90% - DoD 90%
4. Generation & complementarity
Standard: resource assessment (illustrative)
ParameterFormulaValue
Total energy (P50)E_wind + E_pv80,300 MWh/yr
P90P50 x 0.8568,255 MWh/yr
Complementaritywind sharesolar-dominant (add wind for nighttime/winter coverage)
5. Step-up & economics
Standard: IEC 60076 - NREL ATB
ParameterFormulaValue
Step-up transformerkVA52632 kVA (52.6 MVA)
Installed CAPEXwind + PV + storage$51,500,000
LCOE (P50)full-cost$65.0/MWh
This calculation book is illustrative resource factors and costs are typical assumptions. A licensed engineer must verify and seal final design documents.
🔧 Secondary schematic (control & signal)
SECONDARY CONTROL & SIGNAL CIRCUIT35 kV circuit breaker close/trip + indication + interlock (TYPICAL)+control supplyCS (close)interlock52Cclose coil-TC (trip)prot trip52Ttrip coilSIGNAL (indication)52a (closed)REDbreaker closed-TYPICAL CIRCUITStandard control/signal scheme for COLLECTOR FEEDER 1.Project detailing required (wiring, terminal assignment).
🔩 Terminal strip (typical)
TERMINAL STRIP (TYPICAL)X1 secondary wiring terminals (typical project detailing required)TerminalFunctionWireX1:1control supply L+1.5 mm2X1:2control supply L-1.5 mm2X1:3close command1.5 mm2X1:4trip command1.5 mm2X1:5breaker 52a status1.5 mm2X1:6breaker 52b status1.5 mm2X1:7trip circuit healthy1.5 mm2X1:8earth / shield2.5 mm2
🌬️☀️ Resource & generation
ParameterValue
Wind capacity factor23% at 6 m/s (illustrative)
Wind energy0 MWh/yr
PV specific yield1,606 kWh/kWp/yr (5.5 kWh/m²/day, PR 0.8)
PV energy80,300 MWh/yr
Complementaritysolar-dominant (add wind for nighttime/winter coverage)
💰 Economics (full-cost, illustrative)
ParameterValue
Installed CAPEX$51,500,000 (wind $1,150/kW · PV $850/kW · storage $300/kWh)
Annual OPEX$800,000
P50 generation80,300 MWh/yr
P90 generation68,255 MWh/yr
LCOE (P50)$65.0/MWh
LCOE (P90)$76.5/MWh
📏 Standard basis (依据标准)
TopicStandard
Wind grid connectionGB/T 19963 — technical rule for connecting wind farm to power system
PV grid connectionGB/T 19964-2024 — technical rule for connecting photovoltaic power station to power system
Wind turbinesIEC 61400 — wind turbines (design requirements)
Battery storageGB/T 36547 — technical rule for electrochemical energy storage connecting to power grid
🧮 How it was calculated
1. Wind: 0 MW × CF 0.23 (at 6 m/s) × 8760 h = 0 MWh/yr
2. PV: 50 MWp × 5.5 kWh/m²/day × 365 × PR 0.8 = 80,300 MWh/yr
3. Combined P50 = 80,300 MWh/yr · P90 = 68,255 MWh/yr (0.85 × P50, illustrative)
4. Storage: 30 MWh / 2 h = 15000 kW PCS · DoD 90% · RTE 90%
5. Complementarity: solar-dominant (add wind for nighttime/winter coverage)
6. Full-cost LCOE = (CAPEX × CRF + OPEX) ÷ energy = ($51,500,000 × 0.0858 + $800,000) ÷ 80,300 MWh = $65.0/MWh (illustrative)
Summary
Estimated total (FOB Qingdao, EXW) — priced equipment$14,787,062
📋 Design notes
Economics basis (illustrative): LCOE uses installed-cost basis: wind $1,150/kW, PV $850/kW, storage $300/kWh (NREL 2024 ATB / Lazard 2024 typical ranges). Excludes taxes, financing fees, degradation and curtailment. Actual project economics vary by site.
BOM vs economics reconciliation (P2-12): The BOM FOB total ($14,787,062) prices only the catalogue items (PV + storage); wind turbines and the step-up transformer are POA. The illustrative installed CAPEX ($51,500,000) adds wind at $1,150/kW and covers full turnkey installed cost — the two figures use different bases and are not directly comparable.
P50 / P90: P50 = expected annual generation; P90 = 0.85 × P50 (conservative one-year exceedance, illustrative resource variability). A bankable P90 uses site-measured interannual variability, not a fixed 0.85 factor.
Wind BOP: The wind farm balance-of-plant — collector cables, site access roads, crane pads, foundations and heavy-lift erection — is quoted per project and is included in the illustrative installed CAPEX (not the FOB BOM).
POA equipment: Wind turbine generators and the step-up power transformer (outside the distribution catalogue) are quoted per project (POA) — the BOM prices only the PV and storage from the catalogue.
Grid mode: Off-grid mode: storage (and typically a diesel genset) must balance generation against load around the clock — contact us for a microgrid sizing.

计算过程说明

选型计算原理

风电发电量 = 容量 × 容量系数 × 8760 h(容量系数由风速得出)。PV 发电量 = 容量 × GHI × 365 × 性能比 (0.80)。储能功率 = 电量 ÷ 时长。P50 为预期年发电量;P90 为保守值 0.85 × P50。LCOE = (CAPEX × CRF + OPEX) ÷ 年发电量,基于安装成本计算。

适用标准

选型参考 GB/T 19963(风电场并网)、GB/T 19964-2024(PV 电站并网)、IEC 61400(风力发电机组)和 GB/T 36547(电池储能并网)。

常见问题

如何设计风光储一体化电站容量?

按负荷或外送曲线配光伏与风电,再加储能平抑出力。计算器默认 20 MW 风电 + 30 MW 光伏 + 20 MWh/4 h 储能。容量按逐时资源与负荷匹配,储能填补波动发电与需求的缺口。配置器输出容量、电量与 LCOE。

风电和光伏的互补性是什么?

风电常在夜间和冬季大发,光伏在白天和夏季大发,二者结合可平滑总出力、减少平抑所需的储能。良好的风光互补能把容量因子比单一电源提高 10-20%。配置器分析组合后的 P50/P90 电量曲线。

风光互补电站的典型容量因子是多少?

单独光伏容量因子 15-20%,陆上风电 25-35%,匹配良好的风光互补可达 25-40%。容量因子越高越平滑,LCOE 和电网价值越好。配置器根据风速与辐照输入计算组合容量因子。

储能如何平抑风光互补电站出力?

储能在高发、低价时段充电,在风光不足时放电,把波动出力转成更稳定、可调度的曲线。4 小时电池可覆盖多数日内缺口,计算器默认 20 MWh/4 h。这可提高高峰电价窗口的可交付电量占比。

风光储互补电站适用哪些电网导则?

风机遵循 IEC 61400 与 GB/T 19960,光伏遵循 GB/T 19964,储能遵循 GB/T 36547 与 IEC 62933,互补电站并网遵循 GB/T 19963。配置器引用这些标准并按其电压/频率穿越要求设计。

风光储互补电站能达到多少 LCOE?

资源好的地区大型互补电站 LCOE 达 0.03-0.06 美元/kWh,储能按配比加 0.01-0.03 美元/kWh。默认 20 MW 风电 + 30 MW 光伏 + 20 MWh 典型约 0.04-0.05 美元/kWh。配置器用 WACC、运维和衰减计算全成本 LCOE。

嵌入此计算器

复制下方 iframe 代码,即可将此计算器嵌入任何网站。嵌入页面为 noindex,适配任意宽度。

相关计算器

结果为工程估算,仅供参考。最终设计须由当地持证工程师根据现场条件和适用规范确认。价格为青岛交货价 FOB(EXW),不含运费、关税及安装费。

发送我的完整设计报告

免费获取完整设备清单(BOM)、单线图、计算步骤与 FOB 报价的 PDF 报告,无需注册。

💬 WhatsApp 咨询

您的信息仅用于回复询盘,不用于任何其他用途。