QDTB®变压器官网

城市基础设施电力系统计算器

为城市基础设施设计配电系统——道路和隧道照明、桥梁/隧道、泵站和 EV- 充电负载,配套预装式箱式变电站、SF6 环网柜和低压配电。

开始计算 城市基础设施解决方案
智能化与监控
在 BOM 与架构图中加入保护、计量与 SCADA(监控与二次)层。

为什么使用此计算器

城市电网紧凑、低噪声且高度可靠。本计算器汇总市政负载,应用同时系数,并按 GB 50052、CJJ 45 和 GB 50054 选型集成 SF6 环网柜的预装式(箱式)变电站及环网。

Worked Examples

Example 1 — Urban Ring Network (Lighting + Pumping + EV Charging) · FOB $897,825
Urban infrastructure power system · 12kV/0.4kV · dispersed
1,250 kVA box substation
YB-S13-1250/12 · demand 1,085 kW · SF6 ring main
Connected load
1,550 kW
Demand (Kd 0.7)
1,085 kW
Box substations
2 node(s)
Ring main units
2 × SF6
Est. total (FOB)
POA
📦 Bill of Materials
EquipmentModelSpecQty
Main substationYB-S13-1250/121250 kVA · Box-Type · oil internal · S131
LV feeder panelGGD-2000distributes 10 circuits1
PFC capacitor bank200 kVARautomatic · GCK LV cabinet1
Series reactor (detuned)CKSG-12.0/0.412.0 kVAR · 6% · 0.4 kV1
Main feeder cable (TX→LV)YJV 0.6/1kV 300 mm² ×44× 300 mm² Cu · ΔU 5.86% @ 400 m ⚠ · $154.0/m4
Feeder cable — Zone feeder 1 (×10)YJV 300 mm²300 mm² Cu · 249 A · ΔU 3.2% ⚠ · $154.0/m10
Main busbar (Cu)Cu 100×10100×10 · 2000 A rating · ref $118/mincluded
Grounding electrodeΦ20mm × 2.5m rodR₁ 39.6 Ω → 13 rod(s) ≤ 4 Ω13
Ring main unit (SF6, 环网柜)XGN15-1212 kV · SF6 · 3-way · ring main connection2
Pole-mounted switchgear (柱上开关)ZW32-12 / FZW28-1212 kV · pole-mounted vacuum load-break switch · overhead MV sectioning1
EV charging stations (充电桩)500 kW totalAC/DC charging piles · dedicated feeders1
Lighting control cabinet (照明控制柜)street/tunnel lightingtime + photo-electric control · energy metering1
Tunnel ventilation fan feeder (隧道风机)150 kWtunnel/bridge ventilation fan supply1
📐 Single-line diagram
CTCT 70/5APTPT 12kV/100V50/5151NHV incomingKYN28A-12-630-25630 A / 25 kA - vacuumYB-S13-1250/121250 kVAkWhmeteringLV incomingGGD-20000.4 kV LV busbar100x10 Cu - 2000 ASPDPFC 200 kVAR+ detuned reactorLV feeder panel x1 - 10 circuitsZone feeder 1 - 249 AYJV 300 mm2Zone feeder 2 - 249 AYJV 300 mm2Zone feeder 3 - 249 AYJV 300 mm2Zone feeder 4 - 249 AYJV 300 mm2Zone feeder 5 - 249 AYJV 300 mm2Zone feeder 6 - 249 AYJV 300 mm2Zone feeder 7 - 249 AYJV 300 mm2Zone feeder 8 - 249 AYJV 300 mm2Zone feeder 9 - 249 AYJV 300 mm2Zone feeder 10 - 249 AYJV 300 mm2Grounding 13xdia20mmx2.5m rod
LEGENDBreaker (52)DisconnectorCTCT (current transformer)PTPT (voltage transformer)50/51Protection relay 50/51/51N/87kWhMeter (kWh)SPD (surge protection)Transformer
⚙️ Electrical schematic (protection & metering)
ELECTRICAL SCHEMATIC - PROTECTION & METERING12 kV / 0.4 kV - 1250 kVA - secondary circuits (schematic)INCOMING 12 kVCT70/5Aprotection CT5250/5151Novercurrent / earth-faultPT12kV/100Vbus PT (voltage)BOX SUB1250 kVAZ = 4%kWhrevenue meteringLV 520.4 kV LV BUSSPDPFC200 kvarCT.../5AZone feeder 1 - 249 A50/51CT.../5AZone feeder 2 - 249 A50/51CT.../5AZone feeder 3 - 249 A50/51CT.../5AZone feeder 4 - 249 A50/51CT.../5AZone feeder 5 - 249 A50/51CT.../5AZone feeder 6 - 249 A50/51CT.../5AZone feeder 7 - 249 A50/51CT.../5AZone feeder 8 - 249 A50/51CT.../5AZone feeder 9 - 249 A50/51CT.../5AZone feeder 10 - 249 A50/51
⛳ Grounding grid layout
SUBSTATION GROUNDING GRID LAYOUTsite 12 m x 8 m - ring earth electrode (schematic)TRANSFORMERR1R2R3R4R5R6R7R8R9R10R11R12R1312 mGround rods: 13 x dia 20 mm x 2.5 m copper-bonded steelRod spacing: 5 m (= 2 x rod length, ring electrode)Target resistance: <= 4 ohm (measure after installation)Standard: IEEE 80 / GB-T 50065 (earthing design) - indicative layout
🔌 Cable schedule & routing
CABLE SCHEDULEIDFromToCable (model / spec)LengthC0TransformerLV panelYJV 0.6/1kV 300 mm2 (1804 A)400 mC1LV panelZone feeder 1YJV 300 mm2 (249 A)400 mC2LV panelZone feeder 2YJV 300 mm2 (249 A)400 mC3LV panelZone feeder 3YJV 300 mm2 (249 A)400 mC4LV panelZone feeder 4YJV 300 mm2 (249 A)400 mC5LV panelZone feeder 5YJV 300 mm2 (249 A)400 mC6LV panelZone feeder 6YJV 300 mm2 (249 A)400 mC7LV panelZone feeder 7YJV 300 mm2 (249 A)400 mC8LV panelZone feeder 8YJV 300 mm2 (249 A)400 mC9LV panelZone feeder 9YJV 300 mm2 (249 A)400 mC10LV panelZone feeder 10YJV 300 mm2 (249 A)400 mROUTING (schematic)LV PANELL1L2L3L4L5L6L7L8... +3 feedersCable lengths are indicative (run-length based); confirm on site before installation.
🗄 Switchgear arrangement
SWITCHGEAR ARRANGEMENTpanel lineup (front view, schematic)FEEDERGGD-2000PFC200 kvar2 panel(s) - each 320 mm (typical)Clearance / aisle per IEC 61936-1 - layout indicative
🛡 Protection configuration
PROTECTION CONFIGURATION12 kV / 0.4 kV - 1250 kVA - protection zones (schematic)INCOMING 12 kVCTCT 75/5A505151Novercurrent / earth-fault52TRANSFORMER1250 kVA - Z=4%49thermal overloadCTCT 2000/5A505151NLV incoming protection520.4 kV LV BUSCTCT 250/5A50/5151NZone feeder 1249 ACTCT 250/5A50/5151NZone feeder 2249 ACTCT 250/5A50/5151NZone feeder 3249 ACTCT 250/5A50/5151NZone feeder 4249 ACTCT 250/5A50/5151NZone feeder 5249 ACTCT 250/5A50/5151NZone feeder 6249 ACTCT 250/5A50/5151NZone feeder 7249 ACTCT 250/5A50/5151NZone feeder 8249 ACTCT 250/5A50/5151NZone feeder 9249 ACTCT 250/5A50/5151NZone feeder 10249 AProtection layout & CT ratios are schematic / illustrative final settings per IEC 60255 / IEEE 242.
📋 Protection settings
CircuitProtectionSettingTimeStandard
Transformer 1250 kVA49 thermal overload91% of ratedalarm/tripIEC 60076-7 / IEEE C57.91
LV incoming 0.4 kV50 instantaneous14434 AinstIEC 60947-2
LV incoming 0.4 kV51 overcurrent2165 A0.3 sIEC 60947-2 / IEC 60255
LV incoming 0.4 kV51N earth-fault361 A0.3 sIEC 60364-4-41
Zone feeder 150/51/51N (MCCB)Ir 273 A - Im 1989 A - Ig 50 A0.1 s (grading)IEC 60947-2 / IEC 60255
Zone feeder 250/51/51N (MCCB)Ir 273 A - Im 1989 A - Ig 50 A0.1 s (grading)IEC 60947-2 / IEC 60255
Zone feeder 350/51/51N (MCCB)Ir 273 A - Im 1989 A - Ig 50 A0.1 s (grading)IEC 60947-2 / IEC 60255
Zone feeder 450/51/51N (MCCB)Ir 273 A - Im 1989 A - Ig 50 A0.1 s (grading)IEC 60947-2 / IEC 60255
Zone feeder 550/51/51N (MCCB)Ir 273 A - Im 1989 A - Ig 50 A0.1 s (grading)IEC 60947-2 / IEC 60255
Zone feeder 650/51/51N (MCCB)Ir 273 A - Im 1989 A - Ig 50 A0.1 s (grading)IEC 60947-2 / IEC 60255
+4 more feeders50/51/51N (MCCB)per feeder load0.1 s (grading)IEC 60947-2
Settings are illustrative starting points — confirm with a protection coordination study per IEC 60255 / IEEE 242.
📚 Calculation book
CALCULATION BOOK
1250 kVA - 12kV/0.4kV - single - illustrative
1. Load calculation
Standard: IEC 60076 - IEC 60364-5-52
ParameterFormulaValue
Connected loadP = sum(kW)1,550 kW
Demand factorKd0.7
Demand powerPd = P x Kd1,085 kW
Power factorcos(phi) before -> after0.90 -> 0.95
Design apparent powerSd = Pd / cos(phi)1,142 kVA
Transformer loadingSd / Srated91%
2. Short-circuit calculation
Standard: IEC 60909
ParameterFormulaValue
System impedance (pu)Zs = S / Ssc0.42% (on 1250 kVA base)
Transformer impedanceZt = Z%4%
Total impedanceZ = Zt + Zs4.42%
LV prospective IscIsc = In / Z40.9 kA
HV prospective IscIsc = Ssc / (sqrt(3) x V)14.4 kA
Breaking checkIcu >= IscLV 50 kA (1.2x margin) PASS
3. Voltage drop
Standard: IEC 60364-5-52 Annex G
ParameterFormulaValue
Main feederdU = sqrt(3) x I x L x R / V300 mm2 - dU 5.86% @ 400 m
Limitmax 3%EXCEEDS limit
Transformer volt. reg.dU ~ loading x Z% x sin(phi)1.1% at full load
4. Reactive power / harmonics
Standard: IEC 61921 (PFC) - IEEE 519 (harmonics)
ParameterFormulaValue
Required compensationQc = Pd x (tan1 - tan2)169 kvar
PFC bankstandard step200 kvar
Detuned reactorp = 6%12.0 kvar @ 6% (anti-resonance)
5. Grounding
Standard: IEC 60364-5-54 earthing arrangements and protective conductors LV earthing target 10 ohm (TN systems); 4 ohm used as a conservative design target - target 4 ohm
ParameterFormulaValue
Single rod resistanceR1 = rho/(2 x pi x L) x ln(4L/d)39.6 ohm
Rods requiredn = R1 / (target x 0.8)13 rod(s) <= 4 ohm
Rod specdia x length20 mm x 2.5 m
This calculation book is illustrative it consolidates the computed values with the referenced standards. A licensed engineer must verify and seal final design documents for construction.
🔧 Secondary schematic (control & signal)
SECONDARY CONTROL & SIGNAL CIRCUIT0.4 kV circuit breaker close/trip + indication + interlock (TYPICAL)+control supplyCS (close)interlock52Cclose coil-TC (trip)prot trip52Ttrip coilSIGNAL (indication)52a (closed)REDbreaker closed-TYPICAL CIRCUITStandard control/signal scheme for Zone feeder 1.Project detailing required (wiring, terminal assignment).
🔩 Terminal strip (typical)
TERMINAL STRIP (TYPICAL)X1 secondary wiring terminals (typical project detailing required)TerminalFunctionWireX1:1control supply L+1.5 mm2X1:2control supply L-1.5 mm2X1:3close command1.5 mm2X1:4trip command1.5 mm2X1:5breaker 52a status1.5 mm2X1:6breaker 52b status1.5 mm2X1:7trip circuit healthy1.5 mm2X1:8earth / shield2.5 mm2
🏙️ Load profile
ParameterValue
Road lighting300 kW
Tunnel lighting200 kW
Bridge/tunnel150 kW
Pumping stations400 kW
EV charging500 kW
🔁 Ring network
ParameterValue
Distributiondispersed (800 m radius)
Box substations2 node(s)
Ring main units2 × XGN15-12 SF6 (3-way)
📏 Standard basis (依据标准)
TopicStandard
Standard basisIEC · IEC 60364-5-52
Conductor ampacityIEC 60364-5-52 Table B.52.2–B.52.5 (copper, 3 loaded conductors, 30°C ambient, PVC) — typical/rounded values, conservative (±3%)
Voltage-drop limitIEC 60364-5-52 Annex G · max drop 3%
Winding temp riseIEC 60076-2 — winding temp rise 65 K (Class A insulation, ONAN)
kVA ratingsIEC 60076-1 R10 preferred numbers
Breaker framesIEC 60947-2 frame sizes (In)
Grounding targetIEC 60364-5-54 earthing arrangements and protective conductors — LV earthing target ≤ 10 Ω (TN systems); 4 Ω used as a conservative design target · target 4 Ω
Power supply designGB 50052 — code for design of electric power supply systems
Urban road lightingCJJ 45 — standard for lighting design of urban road
Low-voltage distributionGB 50054 — code for design of low-voltage electric installations
Prefabricated substationGB/T 17467 · IEC 62271 — high-voltage/low-voltage prefabricated substations
🧮 How it was calculated
1. Road lighting: 300 kW
2. Tunnel lighting: 200 kW
3. Bridge/tunnel: 150 kW
4. Pumping stations: 400 kW
5. EV charging: 500 kW
6. Connected load = 1,550 kW → demand = 1,550 × 0.7 = 1,085 kW
7. Dispersed load (800 m radius) → 2 box substation node(s) recommended
8. Ring main units: 2 × XGN15-12 SF6 (ring main connection)
9. Loads: P=1,550 kW, PF 0.90, 10 circuits
10. Demand: 1,550 × 0.7 = 1,085 kW
11. PFC: Qc = 1,085 × (0.484 − 0.329) = 169 kVAR → 200 kVAR bank
12. Transformer: S = 1,085 ÷ 0.95 = 1142.1 kVA → 1,250 kVA standard
13. Loading: 1,142 ÷ 1,250 = 91% (high — consider next size)
14. Voltage regulation: 91% × 4% × sinφ ≈ 1.1% at full load
15. HV unit integrated in substation (In 60.1 A)
16. LV: In 1804 A, Isc 40.9 kA (Xfmr Z 4% + system 0.4%) → GGD-2000 (integrated), 1 feeder panel(s)
17. Grounding: R₁ 39.6 Ω → 13 rod(s)
18. Main feeder: 4× 300 mm² · ΔU 5.86% — FAIL (exceeds 3% limit)
Summary
Estimated total (FOB Qingdao, EXW) — priced equipment$897,825
📋 Design notes
Pricing basis: FOB Qingdao (EXW) equipment price. Freight, duty and installation are not included — add for landed economics.
Transformer loading: 91% at design demand — high, consider the next size up.
Short-circuit check: HV 14.4 kA vs 25 kA (1.7× margin) · LV 40.9 kA vs 50 kA (1.2× margin).
Voltage regulation: ≈ 1.1% at full load (typical limit 5%).
Power factor correction: 200 kVAR automatic bank corrects PF to 0.95.
Voltage-drop check — FAIL: ΔU exceeds the 3% limit on: main feeder 5.9%, Zone feeder 1 3.2%, Zone feeder 2 3.2%, Zone feeder 3 3.2%, Zone feeder 4 3.2% … +6 more — increase cross-section or add a parallel run.
Parallel conductors: Single-cable ampacity exceeded — parallel conductors specified: main feeder 4× 300 mm² (per IEC 60364-5-52 / GB 50054).
Cable & grounding pricing: Cable conductors and grounding are priced from the confirmed cables-trays-grounding price reference (per-metre copper YJV; aluminium remains POA). The main copper busbar is POA — its length is project-specific.
Busway (high-current feeders): For LV feeders above ~2500 A, a busway (母线槽) trunking system is recommended instead of parallel cables.
Prefabricated (box) substation: A factory-assembled box substation integrates the SF6 ring main unit, transformer and LV panel — compact, low-noise and quick to energize for urban sites (GB/T 17467).
Ring main network: The MV ring main unit (XGN15-12) keeps supply continuous: a fault on one feeder can be isolated while the ring feeds from the other side.
Load distribution: Dispersed load over a 800 m radius — 2 box substation node(s) keep LV feeders short and reduce cable loss.
EV charging: EV charging is a growing, highly intermittent urban load; size for simultaneous charging diversity and consider dedicated feeders.
Pole-mounted switchgear: For overhead MV sections, a pole-mounted vacuum load-break switch (ZW32/FZW28-12) provides line sectioning and fault isolation — priced at $1,183/unit (FOB reference).

计算过程说明

选型计算原理

接入负载 = 道路照明 + 隧道照明 + 桥梁/隧道 + 泵站 + EV 充电。需用负载 = 接入负载 × 同时系数(典型值 0.7)。在给定供电半径内分散的负载由多个箱式变电站节点供电,每个节点集成 SF6 环网柜、变压器和 LV 配电屏(GB/T 17467)。

适用标准

选型参考 GB 50052(供配电设计)、CJJ 45(城市道路照明设计)、GB 50054(低压配电设计)、GB/T 17467 和 IEC 62271(预装式变电站)。

常见问题

什么是预装式箱式变电站?何时使用?

箱式变电站把变压器、高低压开关柜集成在一个全天候外壳内,遵循 GB/T 17467 与 IEC 62271-202。城市基础设施(道路照明、隧道、泵站、充电)用它在土建变电站过贵或过大的场合。容量典型 100-1600 kVA、12/0.4 kV。

道路和隧道照明如何配电?

道路照明用 TT 或 TN-S 系统,由专用变压器或照明箱变供电,馈线可长达 1 km,压降按 CJJ 45 限 5%。隧道照明属安全负荷,需双电源或应急电源。计算器对分散负荷与馈线半径建模以选箱变。

什么是 SF6 环网柜?城市里为什么用它?

SF6 环网柜是采用 SF6 气体绝缘灭弧的紧凑密封型 12-24 kV 开关柜,维护量小、可装在小柜间内。城市在 10-12 kV 环网中用它给箱变供电,在密集区提供 N-1 供电。计算器包含城市馈线的环网柜选型。

EV 充电站给城市基础设施带来什么负荷特性?

EV 充电是陡峭且集中的负荷:一台 120 kW 直流快充可拉 120 kVA,10 桩站点峰值近 500-1200 kVA。充电时间高度相关、同时系数低,变压器选型须计入同时性。IEC 61851 与 GB/T 51313 规范安装;计算器把充电负荷纳入城市负荷组合。

城市 12 kV 配电用什么电缆?

城市 12 kV 网络用 XLPE 交联聚乙烯电缆(国内 YJV/YJV22,IEC 60502),截面 120-400 mm²,直埋或穿管。XLPE 取代油纸绝缘电缆,允许 90 ℃ 运行、维护更低。计算器选馈线电缆并校核载流量与压降。

城市隧道需要什么应急电源?

隧道属安全关键设施:照明、通风和消防需双电源,并加柴发或 EPS 供疏散(GB 50052 一级重要负荷)。应急照明须在 0.5-15 s 内恢复(GB 51309)。计算器对应急等级建模并为城市负荷配置备用回路。

嵌入此计算器

复制下方 iframe 代码,即可将此计算器嵌入任何网站。嵌入页面为 noindex,适配任意宽度。

相关计算器

结果为工程估算,仅供参考。最终设计须由当地持证工程师根据现场条件和适用规范确认。价格为青岛交货价 FOB(EXW),不含运费、关税及安装费。

发送我的完整设计报告

免费获取完整设备清单(BOM)、单线图、计算步骤与 FOB 报价的 PDF 报告,无需注册。

💬 WhatsApp 咨询

您的信息仅用于回复询盘,不用于任何其他用途。