QDTB®变压器官网

水泵站电力系统计算器

为供水或污水处理泵站进行配电选型 — 水泵负载、变压器与开关柜选择、软启动器或VFD选择,以及变速与定速能耗比较。

开始计算 水处理与泵送解决方案
智能化与监控
在 BOM 与架构图中加入保护、计量与 SCADA(监控与二次)层。

为什么使用此计算器

泵站是核心的水利基础设施负载。该计算器根据水泵功率、数量和同时系数为变压器选型,选择启动方式(软启动器或VFD)并进行电压跌落校验,同时利用相似定律估算VFD控制的年节能量。

Worked Examples

Example 1 — 6 × 160 kW Pump Station (Soft Starter, VFD Comparison) · FOB $217,600
Water pumping power system · 10kV/0.4kV · Soft starter
1,000 kVA transformer
SCB13-1000/10 · 6 pumps × 160 kW · Soft starter
Connected load
960 kW
Demand (Ks 0.7)
672 kW
Start dip
3.8%
VFD saving
60% energy
Est. total (FOB)
POA
📦 Bill of Materials
EquipmentModelSpecQty
HV incoming panelKYN28A-12-630-25630 A / 25 kA · vacuum1
Main transformerSCB13-1000/101000 kVA · Dry-Type · Copper · SCB131
LV incoming panelGGD-16001600 A busbar · In 1443 A1
LV feeder panelGGD-1600distributes 6 circuits1
PFC capacitor bank200 kVARautomatic · GCK LV cabinet1
Cable branch box (LV)DFW-0.41-in / 4-out · 0.4 kV · 630 A1
Series reactor (detuned)CKSG-12.0/0.412.0 kVAR · 6% · 0.4 kV1
Main feeder cable (TX→LV)YJV 0.6/1kV 240 mm² ×44× 240 mm² Cu · ΔU 1.17% @ 80 m · $123.0/m4
Feeder cable — Pump 1 (×6)YJV 150 mm²150 mm² Cu · 272 A · ΔU 1.4% · $86.0/m6
Branch trunk cable (LV → branch box 1)YJV 150 mm² ×22× 150 mm² Cu · 543 A · ΔU 1.4% · $86.0/m2
Main busbar (Cu)Cu 100×10100×10 · 2000 A rating · ref $118/mincluded
Grounding electrodeΦ20mm × 2.5m rodR₁ 39.6 Ω → 13 rod(s) ≤ 4 Ω13
Soft starter cabinet (×5)160 kWSoft starter (3.0× In)5
Pump units (motor + impeller)160 kWcentrifugal pump · duty/standby6
Control valves & actuatorsDN (per line)flow control / isolation valves + actuators3
📐 Single-line diagram
CTCT 60/5APTPT 10kV/100V50/5151NHV incomingKYN28A-12-630-25630 A / 25 kA - vacuumSCB13-1000/101000 kVAZ = 6%Dry-Type - Copper - SCB13kWhmeteringLV incomingGGD-16000.4 kV LV busbar100x10 Cu - 2000 ASPDPFC 200 kVAR+ detuned reactorLV feeder panel x1 - 6 circuitsPump 1 - 272 AYJV 150 mm2Pump 2 - 272 AYJV 150 mm2Pump 3 - 272 AYJV 150 mm2Pump 4 - 272 AYJV 150 mm2Pump 5 - 272 AYJV 150 mm2Pump 6 - 272 AYJV 150 mm2Grounding 13xdia20mmx2.5m rodCable branch box DFW-0.4 x1 (1-in / 4-out)
LEGENDBreaker (52)DisconnectorCTCT (current transformer)PTPT (voltage transformer)50/51Protection relay 50/51/51N/87kWhMeter (kWh)SPD (surge protection)Transformer
⚙️ Electrical schematic (protection & metering)
ELECTRICAL SCHEMATIC - PROTECTION & METERING10 kV / 0.4 kV - 1000 kVA - secondary circuits (schematic)INCOMING 10 kVCT60/5Aprotection CT5250/5151Novercurrent / earth-faultPT10kV/100Vbus PT (voltage)TRANSFORMER1000 kVAZ = 6%kWhrevenue meteringLV 520.4 kV LV BUSSPDPFC200 kvarCT.../5APump 1 - 272 A50/51CT.../5APump 2 - 272 A50/51CT.../5APump 3 - 272 A50/51CT.../5APump 4 - 272 A50/51CT.../5APump 5 - 272 A50/51CT.../5APump 6 - 272 A50/51
⛳ Grounding grid layout
SUBSTATION GROUNDING GRID LAYOUTsite 12 m x 8 m - ring earth electrode (schematic)TRANSFORMERR1R2R3R4R5R6R7R8R9R10R11R12R1312 mGround rods: 13 x dia 20 mm x 2.5 m copper-bonded steelRod spacing: 5 m (= 2 x rod length, ring electrode)Target resistance: <= 4 ohm (measure after installation)Standard: IEEE 80 / GB-T 50065 (earthing design) - indicative layout
🔌 Cable schedule & routing
CABLE SCHEDULEIDFromToCable (model / spec)LengthC0TransformerLV panelYJV 0.6/1kV 240 mm2 (1443 A)80 mC1LV panelPump 1YJV 150 mm2 (272 A)80 mC2LV panelPump 2YJV 150 mm2 (272 A)80 mC3LV panelPump 3YJV 150 mm2 (272 A)80 mC4LV panelPump 4YJV 150 mm2 (272 A)80 mC5Branch boxPump 5YJV 150 mm280 mC6Branch boxPump 6YJV 150 mm280 mROUTING (schematic)LV PANELL1L2L3L4L5L6L7Cable lengths are indicative (run-length based); confirm on site before installation.
🗄 Switchgear arrangement
SWITCHGEAR ARRANGEMENTpanel lineup (front view, schematic)HV INCOMINGKYN28A-12-630-25LV INCOMINGGGD-1600FEEDERGGD-1600PFC200 kvarBRANCH BOXDFW-0.45 panel(s) - each 128 mm (typical)Clearance / aisle per IEC 61936-1 - layout indicative
🛡 Protection configuration
PROTECTION CONFIGURATION10 kV / 0.4 kV - 1000 kVA - protection zones (schematic)INCOMING 10 kVCTCT 75/5A505151Novercurrent / earth-fault52TRANSFORMER1000 kVA - Z=6%49thermal overloadCTCT 1500/5A505151NLV incoming protection520.4 kV LV BUSCTCT 300/5A50/5151NPump 1272 ACTCT 300/5A50/5151NPump 2272 ACTCT 300/5A50/5151NPump 3272 ACTCT 300/5A50/5151NPump 4272 ACTCT 300/5A50/5151NPump 5272 ACTCT 300/5A50/5151NPump 6272 AProtection layout & CT ratios are schematic / illustrative final settings per IEC 60255 / IEEE 242.
📋 Protection settings
CircuitProtectionSettingTimeStandard
HV incoming 10 kV50 instantaneous462 AinstIEC 60255-151 / IEEE 242
HV incoming 10 kV51 overcurrent69 A0.5 sIEC 60255-151 / IEEE 242
HV incoming 10 kV51N earth-fault12 A0.5 sIEC 60364-4-41
Transformer 1000 kVA49 thermal overload71% of ratedalarm 90%IEC 60076-7 / IEEE C57.91
LV incoming 0.4 kV50 instantaneous11547 AinstIEC 60947-2
LV incoming 0.4 kV51 overcurrent1732 A0.3 sIEC 60947-2 / IEC 60255
LV incoming 0.4 kV51N earth-fault289 A0.3 sIEC 60364-4-41
Pump 150/51/51N (MCCB)Ir 299 A - Im 2174 A - Ig 54 A0.1 s (grading)IEC 60947-2 / IEC 60255
Pump 250/51/51N (MCCB)Ir 299 A - Im 2174 A - Ig 54 A0.1 s (grading)IEC 60947-2 / IEC 60255
Pump 350/51/51N (MCCB)Ir 299 A - Im 2174 A - Ig 54 A0.1 s (grading)IEC 60947-2 / IEC 60255
Pump 450/51/51N (MCCB)Ir 299 A - Im 2174 A - Ig 54 A0.1 s (grading)IEC 60947-2 / IEC 60255
Pump 550/51/51N (MCCB)Ir 299 A - Im 2174 A - Ig 54 A0.1 s (grading)IEC 60947-2 / IEC 60255
Pump 650/51/51N (MCCB)Ir 299 A - Im 2174 A - Ig 54 A0.1 s (grading)IEC 60947-2 / IEC 60255
Settings are illustrative starting points — confirm with a protection coordination study per IEC 60255 / IEEE 242.
📚 Calculation book
CALCULATION BOOK
1000 kVA - 10kV/0.4kV - single - illustrative
1. Load calculation
Standard: IEC 60076 - IEC 60364-5-52
ParameterFormulaValue
Connected loadP = sum(kW)960 kW
Demand factorKd0.7
Demand powerPd = P x Kd672 kW
Power factorcos(phi) before -> after0.85 -> 0.95
Design apparent powerSd = Pd / cos(phi)707 kVA
Transformer loadingSd / Srated71%
2. Short-circuit calculation
Standard: IEC 60909
ParameterFormulaValue
System impedance (pu)Zs = S / Ssc0.33% (on 1000 kVA base)
Transformer impedanceZt = Z%6%
Total impedanceZ = Zt + Zs6.33%
LV prospective IscIsc = In / Z22.8 kA
HV prospective IscIsc = Ssc / (sqrt(3) x V)17.3 kA
Breaking checkIcu >= IscLV 25 kA (1.1x margin) PASS
3. Voltage drop
Standard: IEC 60364-5-52 Annex G
ParameterFormulaValue
Main feederdU = sqrt(3) x I x L x R / V240 mm2 - dU 1.17% @ 80 m
Limitmax 3%within limit
Transformer volt. reg.dU ~ loading x Z% x sin(phi)1.3% at full load
4. Reactive power / harmonics
Standard: IEC 61921 (PFC) - IEEE 519 (harmonics)
ParameterFormulaValue
Required compensationQc = Pd x (tan1 - tan2)196 kvar
PFC bankstandard step200 kvar
Detuned reactorp = 6%12.0 kvar @ 6% (anti-resonance)
5. Grounding
Standard: IEC 60364-5-54 earthing arrangements and protective conductors LV earthing target 10 ohm (TN systems); 4 ohm used as a conservative design target - target 4 ohm
ParameterFormulaValue
Single rod resistanceR1 = rho/(2 x pi x L) x ln(4L/d)39.6 ohm
Rods requiredn = R1 / (target x 0.8)13 rod(s) <= 4 ohm
Rod specdia x length20 mm x 2.5 m
This calculation book is illustrative it consolidates the computed values with the referenced standards. A licensed engineer must verify and seal final design documents for construction.
🔧 Secondary schematic (control & signal)
SECONDARY CONTROL & SIGNAL CIRCUIT0.4 kV circuit breaker close/trip + indication + interlock (TYPICAL)+control supplyCS (close)interlock52Cclose coil-TC (trip)prot trip52Ttrip coilSIGNAL (indication)52a (closed)REDbreaker closed-TYPICAL CIRCUITStandard control/signal scheme for Pump 1.Project detailing required (wiring, terminal assignment).
🔩 Terminal strip (typical)
TERMINAL STRIP (TYPICAL)X1 secondary wiring terminals (typical project detailing required)TerminalFunctionWireX1:1control supply L+1.5 mm2X1:2control supply L-1.5 mm2X1:3close command1.5 mm2X1:4trip command1.5 mm2X1:5breaker 52a status1.5 mm2X1:6breaker 52b status1.5 mm2X1:7trip circuit healthy1.5 mm2X1:8earth / shield2.5 mm2
⚙️ Soft-start / VFD selection
ParameterValue
Pump160 kW · started Soft starter (3.0× In)
Start voltage dip3.8% vs limit 15% — OK ✓
Starters / VFD panels5 × Soft starter (160 kW each)
💰 Fixed-speed vs VFD energy (per year)
ParameterValue
Fixed-speed (throttle)2,176,000 kWh/yr · $217,600
VFD (affinity law, 70% flow)878,080 kWh/yr · $87,808
Annual saving1,297,920 kWh/yr (60%) · ≈ $129,792/yr
📏 Standard basis (依据标准)
TopicStandard
Standard basisIEC · IEC 60364-5-52
Conductor ampacityIEC 60364-5-52 Table B.52.2–B.52.5 (copper, 3 loaded conductors, 30°C ambient, PVC) — typical/rounded values, conservative (±3%)
Voltage-drop limitIEC 60364-5-52 Annex G · max drop 3%
Winding temp riseIEC 60076-11 — dry-type Class F 100 K rise
kVA ratingsIEC 60076-1 R10 preferred numbers
Breaker framesIEC 60947-2 frame sizes (In)
Grounding targetIEC 60364-5-54 earthing arrangements and protective conductors — LV earthing target ≤ 10 Ω (TN systems); 4 Ω used as a conservative design target · target 4 Ω
Pumping station designGB 50265 — design code for pumping stations
Rotating machinesIEC 60034 — rotating electrical machines
Adjustable-speed drivesIEC 61800 — VFD & pump system energy efficiency
Power supply designGB 50052 — code for design of electric power supply systems
🧮 How it was calculated
1. Pumps: 6 × 160 kW = 960 kW connected
2. Demand P = 960 × 0.7 = 672 kW
3. Start method Soft starter: start kVA = 627 kVA → dip 3.8% (limit 15%)
4. Fixed-speed energy = 4 × 160 × 0.85 × 4000 h = 2,176,000 kWh/yr
5. VFD energy (affinity law) = 4 × 160 × 0.7³ × 4000 h = 878,080 kWh/yr
6. Saving = 1,297,920 kWh/yr (60% ≈ $129,792/yr @ 0.1 $/kWh)
7. Loads: P=960 kW, PF 0.85, 6 circuits
8. Demand: 960 × 0.7 = 672 kW
9. PFC: Qc = 672 × (0.620 − 0.329) = 196 kVAR → 200 kVAR bank
10. Transformer: S = 672 ÷ 0.95 = 707.4 kVA → 1,000 kVA standard
11. Loading: 707 ÷ 1,000 = 71% (good range)
12. Voltage regulation: 71% × 6% × sinφ ≈ 1.3% at full load
13. HV: In 57.7 A, Isc 17.3 kA → KYN28A-12-630-25
14. LV: In 1443 A, Isc 22.8 kA (Xfmr Z 6% + system 0.3%) → GGD-1600, 1 feeder panel(s)
15. Cable branch boxes: 1 × DFW-0.4 (1-in/4-out) for feeder grouping
16. Grounding: R₁ 39.6 Ω → 13 rod(s)
17. Main feeder: 4× 240 mm² · ΔU 1.17% — OK
Summary
Estimated total (FOB Qingdao, EXW) — priced equipment$144,195
📋 Design notes
Pricing basis: FOB Qingdao (EXW) equipment price. Freight, duty and installation are not included — add for landed economics.
Transformer loading: 71% at design demand — good range.
Short-circuit check: HV 17.3 kA vs 25 kA (1.4× margin) · LV 22.8 kA vs 25 kA (1.1× margin).
Voltage regulation: ≈ 1.3% at full load (typical limit 5%).
Power factor correction: 200 kVAR automatic bank corrects PF to 0.95.
Copper price linkage: Copper-wound transformer price tracks LME copper (current $14,115/t · 2026-09-14 · LME Copper (Sina hf_CAD)).
Parallel conductors: Single-cable ampacity exceeded — parallel conductors specified: main feeder 4× 240 mm², branch trunk 1 2× 150 mm² (per IEC 60364-5-52 / GB 50054).
Cable & grounding pricing: Cable conductors and grounding are priced from the confirmed cables-trays-grounding price reference (per-metre copper YJV; aluminium remains POA). The main copper busbar is POA — its length is project-specific.
Busway (high-current feeders): For LV feeders above ~2500 A, a busway (母线槽) trunking system is recommended instead of parallel cables.
Starting: Each 160 kW pump started Soft starter draws a 3.8% bus dip (within 15% limit).
VFD savings: At 70% average flow, VFD control saves ≈ 60% energy vs fixed-speed throttling (1,297,920 kWh/yr). Actual savings depend on the pump duty profile.
Static head correction: The affinity-law saving (P∝n³) assumes negligible static head. Where the pump lifts against a static head (elevation/tank pressure), the achievable saving is lower — the calculated figure is the ideal upper bound.
Pumps & valves: Pump units and control valves are quoted per project (POA) — this calculator sizes the electrical side (transformer, switchgear, starters/VFD).
Simultaneity: Not all pumps run together — demand factor 0.7 avoids oversizing the transformer.

计算过程说明

选型计算方式

需用功率 P = 水泵台数 × kW × 同时系数。启动方式决定启动电流倍数kst及由此产生的母线电压跌落。对于VFD运行,轴功率遵循相似定律 P ∝(转速)³,因此在降低的平均流量下运行可节省节流能耗的约(1 − 流量³)。

适用标准

选型参考GB 50265(泵站设计)、IEC 60034(旋转电机)、IEC 61800和GB/T 25409(可调速驱动)以及GB 50052(供电设计)。

常见问题

泵站用软启动器还是变频器更好?

软启动器适合仅启动恶劣的恒流量泵,成本比变频器低 40-60% 且损耗更低。当流量变化大(平均流量低于额定的约 80%)时变频器划算,因为泵功率遵循相似三次方定律——降速 20% 可省近 50% 电能。计算器对比两者并估算变频回本周期。

变频器在泵上能省多少电?

泵功率随转速三次方变化(相似定律)。80% 转速约耗满速功率的 51%,70% 转速为 34%。一台 160 kW 泵年运行 4000 小时、平均流量 0.7 时,变频可比节流省 40-50% 电能。计算器会量化你的工况点下的节电量和费用。

多泵泵站需要多大变压器?

把各泵额定功率相加,乘以同时系数(多泵 0.6-0.8)和功率因数(0.85-0.9),再取邻近标准 kVA。6 台 160 kW 泵、同时系数 0.7、功率因数 0.88 约需 760 kVA,取 800 kVA。还需考虑最大泵启动;计算器把变压器与开关柜一并选型。

泵电机馈线电缆选型遵循哪些规则?

泵馈线电缆按载流量(IEC 60364-5-52)和电压降选型,并要耐受电机启动电流。160 kW、0.4 kV 电机满载约 290 A、直接启动约 5 倍;电缆须能短时承受启动电流并保持稳态压降 5% 以内。计算器推荐截面积并校核启动压降。

如何对比定速与变速泵的能耗?

定速泵满速运行并通过节流调流量(浪费扬程),变速泵则让转速匹配需求。70% 流量工况下变速可省约 34% 电能。计算器输入年运行小时、平均流量与电价,分别计算两种方式的能耗费用和变频投资的简单回本周期。

泵电机需要哪些保护?

泵电机需要过载(热)、短路、缺相和接地保护,潜水泵还需干转保护。保护器件遵循 IEC 60947 与 GB/T 14048,启动器集成接触器 + 热继电器。计算器 BOM 按泵功率配带集成保护的软启动器或变频器。

嵌入此计算器

复制下方 iframe 代码,即可将此计算器嵌入任何网站。嵌入页面为 noindex,适配任意宽度。

相关计算器

结果为工程估算,仅供参考。最终设计须由当地持证工程师根据现场条件和适用规范确认。价格为 FOB 青岛(EXW),不含运费、关税及安装费。

Design the complete system

Move to the full Power System Configurator — 4 layers, 13 drawings, protection schedule, BOM and price.

Open Power System Configurator →

发送我的完整设计报告

免费获取完整设备清单(BOM)、单线图、计算步骤与 FOB 报价的 PDF 报告,无需注册。

💬 WhatsApp 咨询

您的信息仅用于回复询盘,不用于任何其他用途。