Calculateur d'interconnexion centrale photovoltaïque + réseau
Concevez l'interconnexion d'une centrale solaire à l'échelle d'un MW (niveau de tension, sous-station élévateur, compensation réactive, conformité au code réseau et économie du coût complet) dans un seul outil.
Concevez votre interconnexion PV
Un exemple de référence pré-calculé (explorable, aucun JavaScript requis). Entrez vos propres paramètres ci-dessus pour une conception en direct.
Comment cela a été calculé
· Voltage level (A): capacity → 10/35/110 kV POI by typical threshold (≤6 / 6–30 / >30 MW).
· Main transformer (C): MVA = P/0.95 × 1.1 → next standard; vector group YNd11, OLTC (IEC 60076).
· Reactive (D2): dynamic range ±(15–25)% of rating → SVG; shunt reactor absorbs cable/OHL charging (GB/T 29321-2026).
· PV short-circuit (D4): inverter current-source contribution ≈ 1.2 × rated (IEEE 1547 / IEC 60909).
· Generation (F): P50 = PAC × GHI × 365 × PR; P75/P90 = P50 × (1 − 0.674σ / 1.28σ), σ = 4%.
· LCOE (G): full-cost = (CAPEX + Σ(O&M + inverter replacement) discounted) ÷ Σ(generation discounted), WACC discounting, degradation included.
Normes référencées
| Standard | Scope |
|---|---|
| GB/T 19964 | 光伏发电站接入电力系统技术规定 — PV power-station grid interconnection technical requirements: voltage/frequency ride-through, active-power control, reactive-power capability and power-quality limits at the point of interconnection. |
| GB/T 29321-2026 | 光伏发电站无功补偿技术规范 — Reactive-power compensation for PV power stations — dynamic reactive range and compensation equipment (SVG, shunt reactor/capacitor). |
| GB/T 50065 | 交流电气装置的接地设计规范 — Earthing design for AC electrical installations, including substation grounding grids and step/touch voltage verification. |
| GB/T 14549 | 电能质量 公用电网谐波 — Harmonic current limits for equipment connected to the public supply network. |
| IEC 60076 | Power transformers — Power-transformer ratings, impedance, vector groups, tap-changers and cooling (basis for main-transformer selection). |
| IEC 62271 | High-voltage switchgear and controlgear — HV switchgear ratings — breaking current, busbar and GIS/AIS (basis for collector/substation switchgear). |
| IEC 60287 | Electric cables — calculation of the current rating — Cable ampacity calculation (basis for collector cable sizing). |
| IEC 60364 | Low-voltage electrical installations — LV installation and protection requirements. |
| IEC 60909 | Short-circuit currents in three-phase AC systems — Short-circuit current calculation (basis for POI fault level and protection grading). |
| IEC 61727 | Photovoltaic (PV) systems — characteristics of the utility interface — PV utility-interface characteristics, including power quality and protection requirements. |
| IEC 61000 | Electromagnetic compatibility (EMC) — EMC and power-quality (harmonics/flicker) limits. |
| IEEE 1547 | Standard for interconnection and interoperability of distributed energy resources — DER interconnection requirements: voltage/frequency ride-through, power control and anti-islanding. |
| EN 50549 | Requirements for generating plants connected in parallel with distribution networks — European grid-code requirements for generating plants at the distribution level. |
| VDE-AR-N 4105/4110/4120 | German technical connection rules (low / medium / high voltage) — German grid-connection codes for generators at LV/MV/HV. |
| SGCC 接入设计深度规定 | 国网《光伏发电站接入系统设计内容深度规定》 — State Grid Corporation of China regulation on the required depth/content of PV power-station interconnection-system design. |
Questions fréquemment posées
At what voltage should a PV plant connect to the grid?
Connection voltage follows plant size: under ~250 kW use 0.4 kV, 250 kW-6 MW use 10 kV, and above 6 MW use 35 kV or 110 kV. A 50 MW plant typically connects at 110 kV. The choice balances Transformer losses against interconnection cost; grid operators specify the exact point of connection. The calculator selects voltage and main-transformer rating automatically.
How much reactive compensation does a PV plant need?
Grid codes (GB/T 19964, IEEE 1547) require PV inverters to operate within a 0.95 leading to 0.95 lagging power-factor range and often to supply reactive support during faults. Large plants usually add a centralized SVG/SVC of 10-30% of plant capacity. A 50 MW plant commonly pairs a 10-15 Mvar dynamic compensator to meet grid-code voltage support.
What short-circuit contribution does a PV inverter add?
A grid-following PV inverter contributes roughly 1.0-1.2 times its rated current for a few cycles, far less than a synchronous generator (5-7 times rated). For a 50 MW plant the contribution is ~60-70 MVA. This matters when checking breaker and transformer fault ratings; the calculator folds PV short-circuit contribution into the interconnection study.
What is the typical collector system voltage in a PV plant?
Large PV plants gather strings through 800 V DC to central or string inverters, then step up through a 0.8 kV to 10 kV or 35 kV collector network. String inverters (up to 250 kW) feed a 10 kV collector; central inverters (500 kW-3 MW) feed 35 kV. Collector cable runs are typically 5-20 km, sized for under 2% voltage drop.
How is the main transformer sized for a PV plant?
The main transformer rating matches inverter AC capacity divided by Power Factor, with 5-10% margin and the next standard size (IEC 60076). A 50 MWac plant with 0.95 pf needs roughly 55 MVA, so select 63 MVA. Most PV main transformers are oil-immersed, ONAN, 35/110 kV, with a No-Load Loss limit set by GB/T 6451 efficiency grades.
What grid-code compliance checks does interconnection require?
Key checks per GB/T 19963/19964 and IEEE 1547 include: low/high-voltage ride-through, frequency ride-through (typically 47.5-51.5 Hz), power-factor capability, ramp-rate limits, and anti-islanding. The calculator verifies voltage-level fit, main-transformer sizing, reactive compensation and fault contribution, flagging parameters that fall outside the typical grid-code envelope.
Intégrer cette calculatrice
Ajoutez ce calculateur d'interconnexion photovoltaïque à votre site : le lien d'attribution permet de varier le texte d'ancrage.
Calculatrices associées
Conception de référence et estimations de prix (FOB Qingdao, EXW) pour la planification préliminaire uniquement — et non pour un devis final. Confirmez la conception avec un ingénieur local agréé par rapport au code réseau applicable.
Send my complete design report
Get the full bill of materials, single-line diagram, calculation steps and FOB pricing as a PDF — free, no sign-up.
Your data stays private. No spam — only a reply to your enquiry.