Size a 1,000 t/d cryogenic air separation unit from its compressor schedule: 23,050 kW connected, 21,646 kW demand, 21,678 kVA at 0.9985 PF with a 12,500 kW synchronous main air compressor at 0.98 leading, two 25 MVA 33/11 kV ONAN/ONAF units at 43.4% each (86.7% with one out), 18.3 kA at 11 kV with the tie closed, 2.6% TDD against a 5.0% IEEE 519 limit, and a 3.0% dip on LCI start.

By QDTB Engineering Team·Updated 2026-11-08
Air Separation Unit TransformerASU Power Supply Design33 kV ASU SubstationMain Air Compressor Motor StartingLCI VFD Harmonic FilterIEEE 519 TDD ComplianceOxygen Plant Transformer SizingN+1 Transformer RedundancyCryogenic Plant Electrical Load

The answer first: a 1,000 t/d oxygen plant is a 21.6 MW load, and two 25 MVA units carry it with full redundancy

A 1,000 t/d cryogenic air separation unit has 23,050 kW of connected load but a design demand of 21,646 kW, because the main air compressor runs flat out while the nitrogen and oxygen compressors trim with product demand. With the main air compressor's synchronous motor excited to 0.98 leading, the plant draws 21,678 kVA at 0.9985 power factor — 1,138 A at 11 kV, or 379 A at 33 kV. Two 25 MVA 33/11 kV ONAN/ONAF units carry that at 43.4% each, and 86.7% on one unit after the other is taken out, with no load shedding at all. Two 20 MVA units would save USD 120,000 and force 3.0 MW of product compressors off the bus exactly when oxygen supply matters most. The kVA is the easy part. What decides whether this plant stays on line is a 12,500 kW motor that must start without collapsing the 11 kV bus, a 24-pulse load-commutated inverter that injects 10.4% current distortion before filtering, and a cold box that takes 12–30 hours to return to purity after any supply interruption.

Key takeaways

  • 1,000 t/d O₂ (41.7 t/h) plus 1,100 t/d gaseous N₂ and 35 t/d Ar: 23,050 kW connected, 22,088 kW after demand factors, 21,646 kW after 0.98 diversity, 21,678 kVA at 0.9985 PF. The connected sum overstates the real demand by 6.5% — far less than in a warehouse, because an ASU runs at a fixed point 8,000 hours a year. The arithmetic is the same one used in the one-step sizing and budget formula.
  • Two 25 MVA 33/11 kV ONAN/ONAF units at 11% impedance: 43.4% loaded each, 86.7% with one out at 45 °C ambient (23.1 MVA ONAF rating). Two 20 MVA units sit at 54.2% each and reach 108.4% with one out, which is survivable only if the operator sheds the 3.0 MW nitrogen compressor within two minutes.
  • The 12,500 kW main air compressor is 58% of the demand and decides the specification: its synchronous motor supplies 2.5 Mvar leading, so the plant needs almost no capacitor bank, but its LCI start at 45% current still produces a 3.0% dip on a 197 MVA section.
  • Harmonic distortion: 2.6% TDD at the 11 kV bus after 24-pulse conversion, 5th and 7th detuned filters and active front ends, against an IEEE 519-2022 limit of 5.0% for Isc/IL = 16.1. The same load with plain six-pulse drives reaches 36.9% TDD and overheats the transformer long before any relay trips.
  • The electrical package — two 25 MVA transformers, 33 kV and 11 kV switchgear, filters, LV boards, cables and commissioning — costs USD 3.0–3.8 million, 7–9% of a USD 40–50 million ASU, and the transformers are 18–24 weeks away (industry experience, FOB China, 2025–2026).

What does a 1,000 t/d air separation unit actually draw?

Start from the process, not from a kWh-per-tonne benchmark. A 1,000 t/d oxygen plant with 99.5% purity, 1,100 t/d of gaseous nitrogen at 10 bar and a 35 t/d argon column needs about 150,000 Nm³/h of feed air at 5.5–6.0 bar. The main air compressor moves that air; the booster air compressor lifts a side stream to the 40–60 bar needed by the liquid oxygen and nitrogen pumps; the product compressors push gas into the customer's pipeline. Each of those machines has its own motor, its own starting method and its own harmonic signature, and the transformer sees all of them at once.

The reference plant below is a grass-roots ASU serving a steel mill and a merchant gas pipeline in Southeast Asia: 1,000 t/d O₂ at 1.3 bar battery limit, 1,100 t/d N₂ compressed to 10 bar, 35 t/d Ar, 150,000 Nm³/h feed air, single cold box with a 12 m cold box and a 33 kV incoming supply from a 1,500 MVA utility source.

Load groupRating (kW)Voltage / startingDemand factorDemand (kW)
Main air compressor (MAC), synchronous12,50011 kV, LCI variable speed1.0012,500
Booster air compressor (BAC)2,80011 kV, VFD with active front end1.002,800
Nitrogen product compressor3,20011 kV, soft starter0.953,040
Oxygen product compressor1,80011 kV, VFD0.951,710
Argon compressor45011 kV, direct-on-line0.90405
Cooling water pumps (3 × 250 kW)7500.415 kV, 2 duty + 1 standby0.80600
Chilled water and evaporative cooling6200.415 kV, VFD0.75465
Regeneration and sump heaters3200.415 kV, on/off0.55176
Instrument air, analysers, lighting, LV4800.415 kV0.60288
Trace heating, valves, UPS1300.415 kV / DC0.80104
Total23,050——22,088 → 21,646

Two numbers in that table matter more than the rest. The first is the MAC at 12,500 kW: it is 58% of the demand, it is a synchronous machine, and it is the only load on the site that the electrical engineer can use as a reactive power source. The second is the ratio of demand to connected load, which is 0.94 before diversity and 0.94 after it. Compare that with a cold store or an assembly plant, where the same ratio is 0.70. An ASU is a base-load plant: the compressors are selected for a design point and then run there for 8,000 hours a year, so a nameplate-sum sizing error stays in the electricity bill rather than being absorbed by diversity.

Specific consumption lands at 519 kWh per tonne of oxygen, or 0.69 kWh per Nm³ of oxygen, for the whole plant including 1,100 t/d of nitrogen compression. The separation work alone is 0.55–0.60 kWh/Nm³; the difference is the product compressors, which is why an ASU that sells pipeline nitrogen carries a materially larger electrical package than one that vents it. At USD 0.07/kWh and 8,000 hours, the plant's annual electricity bill is about USD 12.1 million — and every kilowatt of transformer loss is charged at that rate, 8,000 hours a year, for 25 years.

Why does the main air compressor decide the transformer, not the connected load?

The MAC is a 12,500 kW, 11 kV synchronous motor driving an integrally geared centrifugal compressor through a load-commutated inverter (LCI). At 0.98 power factor the motor presents 12,755 kVA and 669 A to the 11 kV bus; the 12,500 kW is its electrical input rating, which is what the load schedule carries, and the shaft output is 12,060 kW at 96.5% efficiency. Three properties of that one machine shape the whole electrical design.

It starts at reduced current. An LCI ramps the motor from zero speed at 40–50% of rated current, so the starting kVA is about 5,950 kVA rather than the 76,500 kVA a direct-on-line start would demand. On a 197 MVA 11 kV section that is a 3.0% dip, and the compressor accelerates to rated speed in 90–140 seconds without the cold box seeing a pressure excursion. A DOL start of the same motor would draw 6× full-load current, produce a dip well above 30%, and trip every contactor on the section — which is why no ASU of this size uses one.

It is synchronous, so it can be excited to lead. At 0.98 leading the MAC absorbs 2,535 kvar from the bus; an induction motor of the same rating at 0.90 would consume 6,055 kvar, a swing of 8.6 Mvar on a 21.6 MW plant. That is the difference between a plant that needs 7 Mvar of correction and one that needs only the 6 Mvar of detuned filter banks required for harmonic absorption, where the filters serve double duty as the converter's reactive supply. Set excitation too high and the 11 kV bus voltage rises at light load; too low and the LCI's reactive demand is imported from the utility at a poor power factor. The excitation setpoint belongs in the commissioning procedure, not in the supplier's default.

It is a harmonic source. A 24-pulse LCI produces characteristic harmonics of order 23 and 25 and a current distortion of 6.8% at the converter terminals. That current flows through the 11 kV bus, the transformer windings and the utility meter, and it is the reason the transformer is specified with a harmonic loss allowance rather than a plain kVA rating. The harmonics guide covers the loss mechanism in detail; for an ASU the practical consequence is a 1.04–1.08 multiplier on eddy losses at 2.6% TDD, and a 1.5–1.6 multiplier if the drives are left six-pulse.

Multiplying that out gives the design demand: 21,646 kW and 21,678 kVA at a net 0.9985 power factor, 1,138 A at 11 kV and 379 A at 33 kV. Note what did not happen: no arbitrary 0.9 power factor was assumed, and no 20% design margin was added on top of a load schedule that already contains demand factors and diversity. A base-load plant with a fixed load list does not need a growth margin in the transformer; it needs the right number of units and the right impedance.

How many transformers does an air separation unit need?

Three arrangements are quoted for a plant of this size, and the choice is decided by what happens on the day one unit fails, not by the price of the transformers.

ArrangementNormal loadingLoading with one unit out11 kV fault level (tie closed)Switchgear class
2 × 20 MVA, uk 10%54.2% each108.4% — requires the 3.0 MW nitrogen compressor to be shed within 2 minutes20.9 kA25 kA
2 × 25 MVA, uk 11%43.4% each86.7% — no shedding, fans must be available18.3 kA25 kA
1 × 31.5 MVA, uk 12% + cold spare68.8%0% — 14–20 weeks to change out the failed unit12.1 kA25 kA

The 2 × 25 MVA arrangement wins on the only criterion that matters for an oxygen plant: it keeps 86.7% of production running with no operator action beyond confirming the bus tie is open. Two 20 MVA units save about USD 120,000 on transformers and lose it twice over — once in the automatic load-shedding scheme needed to drop the nitrogen compressor and one cooling water pump within two minutes, and again on the day the shedding fails because a PLC is in manual. The single 31.5 MVA unit with a cold spare is the cheapest capital option and the worst operational one: a spare that arrives in 14 weeks does not help a steel mill that needs 41.7 t/h of oxygen tonight.

The redundancy has two conditions that are usually left out of the quotation. The first is cooling: 25 MVA is the ONAF rating, 20 MVA is ONAN, and at a 45 °C site ambient the ONAF rating falls to about 23.1 MVA. That is still above the 21.7 MVA demand, but only while both fan groups are running, which means the fans need a UPS-backed control supply and a maintenance regime that does not leave one group isolated. The second is the bus tie: it is normally open, so each 11 kV section is fed by one transformer and sees 10.3 kA of fault current. Closing the tie for a transfer raises the fault level to 18.3 kA on both sections, which is why both switchgear line-ups are specified at 25 kA rather than the 16 kA that the normal configuration alone would justify.

Impedance deserves its own sentence because it is the parameter suppliers most often volunteer to reduce. At 11% on 25 MVA, each transformer contributes 0.44 per unit on a 100 MVA base; two in parallel plus the 1,500 MVA source give 18.3 kA at 11 kV and 26.2 kA at 33 kV. Drop the impedance to 9% to save copper and the 11 kV fault level rises to 21.9 kA — still inside the 25 kA class, but with 12% margin instead of 27%, and the 33 kV switchgear is now the constraint because the utility's 26.2 kA already exceeds a 25 kA rating. The short-circuit calculation method and the parallel operation conditions both apply here without modification; an ASU is unusual only in that it runs the calculation for a normally-open tie as well as a closed one.

What harmonic distortion does an ASU create, and what does IEEE 519 actually allow?

An air separation unit is one of the harmonic-rich industrial loads: three variable-speed compressors, a 24-pulse LCI, soft starters and a large population of small drives on the cooling water system. The question is not whether distortion exists but whether it stays inside the limit at the point of common coupling, and where that point is.

At the 11 kV bus the fundamental current is 1,138 A and the fault level is 18.3 kA, so Isc/IL = 16.1. IEEE 519-2022 Table 1 puts that in the lowest band, where the total demand distortion limit is 5.0% for a system between 1 kV and 69 kV. At the 33 kV metering point the fault level is 26.2 kA and the fundamental current only 379 A, so Isc/IL = 69 — a band where the same table allows 12.0% TDD. The 11 kV bus is therefore the binding constraint by a factor of more than two, and the filter design is done there, even though the utility meters at 33 kV. Getting that backwards is a common and expensive mistake: a filter designed to the 33 kV limit will be half the size it needs to be.

Drive configurationHarmonic current at 11 kVTDDAgainst the 5.0% limit
All compressors six-pulse, no filters420 A36.9%7.4× the limit — transformer derating to 0.82 required
12-pulse LCI on MAC, six-pulse VFDs elsewhere118 A10.4%2.1× the limit — eddy losses up 1.55×
24-pulse LCI, AFE on BAC and O₂ compressor, no filters58 A5.1%At the limit with no margin for a fifth drive
24-pulse LCI + 5th/7th detuned filters + AFE drives30 A2.6%52% of the limit — the specified design

Two details decide whether the design number survives commissioning. The first is filter tuning: a 5th-harmonic filter is detuned to 4.7% (tuned at 189 Hz on a 50 Hz system) so that it does not resonate with the 4.5–5.2% impedance tolerance of the transformer plus source combination, and so that it tolerates the 1–2% frequency drift on a weak grid. A filter tuned exactly to 250 Hz will draw more current than it filters once the transformer's actual impedance differs from the nameplate value. The second is the transformer's own harmonic capability: state the spectrum in the datasheet, not just the TDD, because the loss increase appears in the windings as eddy current where no thermometer reaches. At 2.6% TDD the multiplier is about 1.04, which is inside normal design tolerance; at 10.4% it is 1.55, and a transformer rated 25 MVA without that allowance is really a 21 MVA transformer running at 100% of its thermal capability.

There is also a low-frequency effect that pure harmonic analysis misses. The LCI draws a reactive current that varies with speed, so the 11 kV bus voltage moves by 1–2% during a ramp; the MAC's excitation responds, the filters' output changes with V², and the plant's power factor wanders between 0.97 and 1.00 leading. A static compensator is not needed for a plant this size, but the excitation controller and the filter controller must talk to each other, or they will fight. The voltage regulation guide explains the same mechanism from the transformer side.

How do you start a 12.5 MW motor without collapsing the 11 kV bus?

Motor starting is where ASU projects are lost, because the electrical study is usually done after the compressor package is bought, and the compressor supplier's default starting method is whatever was cheapest in the quotation.

MachineRatingStarting methodStarting currentDip on the 11 kV section
Main air compressor, synchronous12,500 kWLCI at 45% current, 90–140 s ramp301 A3.0%
Nitrogen compressor, induction3,200 kWDirect-on-line, 5.8× FLC1,114 A10.8% — not acceptable
Nitrogen compressor, induction3,200 kWSoft starter at 2.2× FLC423 A4.1%
Oxygen compressor, induction1,800 kWVFD, current-limited to 110%104 A at 11 kV equivalent1.0%
Cooling water pump (largest)250 kWStar-delta on 0.415 kV2.6× FLC0.3% at 11 kV

The MAC's 3.0% is the number that the utility will ask for, and it is comfortable against the 5% that most European and Southeast Asian networks allow at the point of common coupling. The nitrogen compressor is the problem: at 3,200 kW it is too large for a direct-on-line start on an 11 kV section with 197 MVA of fault level, and a 10.8% dip will drop the MAC's LCI control, trip the oxygen compressor's VFD on undervoltage, and take the cold box down. A soft starter at 2.2× full-load current brings it to 4.1%, which is inside the limit but leaves nothing for the simultaneous start of a cooling water pump.

The clean answer is to specify the nitrogen compressor with a VFD as well, or to interlock starting so that no two motors above 1 MW start within 10 minutes of each other. The interlock costs nothing and is routinely omitted: the plant's start-up sequence is written by the process engineer, who is thinking about cold box pressure, not about the 11 kV bus. Write the starting sequence into the electrical specification and make it part of the commissioning tests, together with an actual dip measurement on the first start of each machine.

Two secondary effects are worth checking in the same study. The first is transformer inrush when a 25 MVA unit is energised while the other carries the plant: a 25 MVA transformer draws 8–10× rated current for 0.1 s, and with the tie closed that inrush flows through the healthy unit's impedance as well. The inrush current guide covers the mitigation; for an ASU the practical answer is to energise the spare transformer with the tie open and check the 11 kV voltage dip, or to use a controlled switching relay. The second is re-acceleration: after a 200 ms voltage dip caused by an upstream fault, the MAC's LCI rides through and re-accelerates, but the nitrogen compressor's soft starter may drop out, and the resulting 3 MW step is what actually trips the plant. Specify ride-through, not just starting.

What does the 33 kV connection look like, and why does an ASU need an on-load tap changer?

The supply is a single 33 kV point from the utility, split into two incomers with a mechanically interlocked changeover, metering on the utility side of the interlock, and the plant's protection on the transformer side. In most of Southeast Asia and the Gulf the utility will quote a fault level between 1,000 and 1,500 MVA at 33 kV; 1,500 MVA is 26.2 kA, which is above the 25 kA switchgear class, so the incomers are specified at 31.5 kA/1 s and 31.5 kA/3 s making current. That single number — 26.2 kA — moves the 33 kV switchgear up one class and adds 15–20% to its price; ask the utility for the written fault level before the switchgear is ordered, not after.

The tap changer is the part that separates an ASU transformer from a distribution transformer. Utility voltage at 33 kV is permitted to vary by ±6% under IEC 60038, and in practice moves 3–4% between light and heavy load on a weak feeder. An ASU does not absorb that quietly: the MAC's power varies with the compressor's inlet pressure and with ambient temperature, and a 3% drop in supply voltage raises the current for the same absorbed power, which raises the I²R loss and heats the motor. The plant therefore needs an on-load tap changer with ±8 × 1.25% (17 positions), operating on the HV winding, with the control set to hold the 11 kV bus at 1.00–1.02 per unit rather than at a fixed tap position. An off-circuit tap changer with five positions will be at the wrong tap for half the year, and the difference in a 25 MVA unit is about USD 45,000 — small against 25 years of running the plant at the wrong voltage. The OLTC selection guide has the maintenance implications, which for an ASU are modest because tap changes are infrequent once the control is tuned.

ParameterSpecified valueReason
Rating20 MVA ONAN / 25 MVA ONAF, 45 °C ambient43.4% normal, 86.7% with one unit out; 23.1 MVA ONAF at 45 °C still covers 21.7 MVA
Voltage ratio33 ±8 × 1.25% / 11.5 kV, Dyn11OLTC for ±6% utility variation; 11.5 kV no-load gives 11.0 kV at full load with 11% impedance
Impedance11% at 25 MVA, on the OLTC mid position18.3 kA at 11 kV with the tie closed; keeps 25 kA switchgear with margin
LossesNo-load 16.5 kW, load 118 kW at 75 °C referenceGrade 2 equivalent; 8,000 h/yr operation makes no-load loss the dominant cost
CoolingONAN/ONAF, two fan groups, 1.0 kW each, IP55 motorsRedundancy depends on fans; group failure must alarm, not trip
Harmonic duty2.6% TDD stated, eddy loss allowance 1.05×, K-factor 4The spectrum, not just the TDD, sizes the winding transposition and tank shielding
Protection87T, 64 REF, 50/51, 51N, 51G, Buchholz, PRD, OTI/WTI, magnetic oil gaugeArc-flash limitation and incipient fault detection; see the protection devices guide
MonitoringDGA sampling valve, top-oil and winding temperature to SCADA, IEC 61850Non-negotiable for a unit that cannot be spared; the DGA baseline is taken at commissioning
Enclosure and sitingOutdoor, IP23, cable box bottom entry, fire wall to the cold boxOil-filled units kept out of the oxygen vent plume and the LOX storage separation zone

Siting is an engineering decision, not a layout detail. A cryogenic ASU vents oxygen-rich gas during defrost and at the cold box relief valves, and liquid oxygen storage sits within the plot. An oil-filled transformer in an oxygen-enriched atmosphere is a fire hazard that no protection relay can address, so the units go outside the vent plume and behind a fire wall, with the separation distances taken from NFPA 55 and the site's HAZOP rather than from the general arrangement drawing. Where the plot is tight, the alternative is a dry-type transformer inside the building — at 25 MVA that is a cast-resin unit of a size and price that usually sends the designer back to the outdoor layout. The oil versus dry-type comparison sets out where the crossover falls.

What does the electrical package cost, and what is the lead time?

The figures below are 2025–2026 FOB China ranges for a project of this size, useful for the shape of the budget rather than the last digit.

ItemScopeCost (USD)
Two 25 MVA 33/11 kV Dyn11 transformersONAN/ONAF, 11% uk, OLTC ±8 × 1.25%, Grade 2 losses, IP23, monitoring760,000–920,000
33 kV switchgearTwo incomers with interlock, two transformer bays, metering, 31.5 kA260,000–340,000
11 kV switchgear12 panels, 25 kA, vacuum CBs, relays, arc-flash rated340,000–440,000
Harmonic filters2 × 3,000 kvar detuned 5th/7th, 11 kV, controllers380,000–470,000
LV boards, MCCs, cables, earthing, trays3,200 A main boards, compressor MCCs, 33 kV and 11 kV XLPE, earth mat950,000–1,250,000
Protection, SCADA, commissioning, sparesRelay settings, injection testing, dip tests, DGA baseline, spares280,000–360,000
Total—2.97–3.78 million

Add the compressor packages' own electrical content — VFDs, LCI, motor control, harmonic filters inside the packages — and the complete electrical scope lands at USD 5.5–6.5 million, or 12–15% of the ASU's installed cost. Lead times decide the construction sequence: 25 MVA transformers are 18–24 weeks, 33 kV switchgear 20–26 weeks, harmonic filters 16–20 weeks, 11 kV switchgear 16–20 weeks. A transformer ordered after the cold box foundations are poured will arrive after the compressor packages are ready to run, which is how a 26-month ASU becomes a 30-month one.

Loss economics matter more here than in almost any other application, because the plant runs 8,000 hours a year at 43% loading. At the actual loading each transformer loses 16.5 kW at no load and 22.2 kW at load, 38.7 kW together; two units are 77.4 kW, which is 619 MWh a year and USD 43,300 at USD 0.07/kWh — 0.36% of the plant's 173 GWh consumption. The capitalised value of that loss is what sets the acceptable price premium: at USD 0.07/kWh, 8,000 hours and 6% over 20 years, a kilowatt of no-load loss is worth about USD 6,400 and a kilowatt of load loss about USD 1,200 at this loading. A Grade 1 unit that saves 4 kW of no-load loss over a Grade 2 unit is therefore worth USD 25,000 more, and a supplier asking USD 60,000 more for it is selling efficiency the plant cannot recover. The total cost of ownership method and the efficiency standards comparison give the same answer by different routes; the loss grade comparison explains why amorphous cores do not appear above 5 MVA.

How do you size an ASU supply in six steps?

The method scales from 200 t/d to 2,500 t/d; only the numbers change.

  • Step 1 — take the compressor schedule, not the plant's kW-per-tonne figure. MAC, BAC, nitrogen and oxygen compressors, argon, pumps, chillers, heaters, LV. Each with its rated kW, efficiency, power factor and starting method. A benchmark figure cannot tell you whether the MAC is synchronous or induction, and that single fact moves the plant's power factor by 3 points.
  • Step 2 — apply demand factors and diversity, then stop. 23,050 kW connected becomes 22,088 kW after demand factors and 21,646 kW after 0.98 diversity. Do not add a 20% future margin to a plant that will run at its design point from day one; buy the redundancy in transformer count instead.
  • Step 3 — resolve reactive power with the motor excitation included. Add kvar arithmetically including the synchronous machine's leading contribution, then take the vector sum. Dividing 21,646 kW by an assumed 0.9 gives 24,051 kVA and a transformer one size too large.
  • Step 4 — choose count and impedance together, then check the fault level twice. Normal loading, one-unit-out loading, fault level with the tie open and with the tie closed. If closing the tie for a transfer needs a switchgear class the project cannot afford, change the impedance, not the switchgear.
  • Step 5 — run the harmonic, motor-starting and harmonic-loss studies. TDD at the 11 kV bus, not at the 33 kV meter; dip for the largest motor at the worst moment; eddy-loss multiplier for the transformer. These three studies decide more of the specification than the kVA does.
  • Step 6 — issue the load schedule and the starting sequence as controlled documents. The compressor starting interlocks, the excitation setpoint, the load-shedding table and the tap changer control are part of the transformer order. If they are not in the datasheet package, the plant is specified for a mode of operation nobody will use.

Steps 3 to 5, with the fault level and harmonic arithmetic built in, are what the power system calculators automate: enter the load list and the voltage, and the kVA, fault level and loss figures follow.

What are the seven specification mistakes that cost the most?

These recur in ASU enquiries from Southeast Asia, the Gulf and Europe, and each has a price attached to it.

  • Sizing from the connected load with a 20% margin. 23,050 kW plus 20% is 27,660 kW, which buys a 31.5 MVA transformer, buries the real loading figure and hides the fact that the plant is running at 69% instead of 87% with one unit out.
  • Two 20 MVA units instead of two 25 MVA units. USD 120,000 saved, then 3.0 MW of automatic load shedding added, then the shed fails on the day it is needed and the cold box trips.
  • Six-pulse drives on the compressors. 36.9% TDD, a transformer that must be derated to 0.82, and a filter that costs more than the active front ends would have cost inside the drives.
  • A direct-on-line start on the 3,200 kW nitrogen compressor. A 10.8% dip, a MAC LCI that trips on undervoltage, and a fault report that blames the transformer.
  • No harmonic loss allowance in the datasheet. The transformer passes its factory temperature-rise test on a sinusoidal supply and runs 8–12 K hotter on site, which halves insulation life without tripping anything.
  • An off-circuit tap changer. Five positions set at dispatch and never moved, against a utility voltage that moves 4% between seasons, on a plant whose compressor power depends on terminal voltage.
  • No DGA baseline at commissioning. Without a first sample every later result is uninterpretable, and the incipient fault that a month-14 sample would have caught is found at month 30 in the DGA test when the oil is already gassing.

What changes at 2,000 t/d, or when the utility asks for a 132 kV connection?

Doubling the oxygen output roughly doubles the electrical load, but the transformer voltage class does not scale linearly with it. A 2,000 t/d ASU with gaseous nitrogen and argon has about 44,600 kW of connected load and 41,900 kW of demand — 41.9 MVA at 0.9985 power factor, which is 733 A at 33 kV and 2,200 A at 11 kV.

At that size the 11 kV distribution becomes the constraint before the transformer does: 2,200 A of 11 kV busbar is 3,200 A switchgear with a 40 kA fault level once two 31.5 MVA transformers are in parallel, and the cable terminations alone become a layout problem. Most projects above about 35 MVA therefore move to a 132/11 kV or 220/11 kV connection with a single 50–63 MVA GSU-style unit plus a spare, or keep 33 kV with three 25 MVA units and a sectionalised 11 kV bus. The decision is made by the utility's fault level and by the price of 132 kV GIS, not by the transformer price.

What does not change is the arithmetic that matters. The main air compressor is still more than half the load and still the machine that decides starting and reactive power. The 11 kV bus is still the binding harmonic constraint, because the ratio of fault level to load current falls as the plant grows, which tightens Isc/IL and drops the plant into a lower TDD band. And the cost of a trip is still measured in cold box recovery hours, not in transformer money. Design the first phase with a spare 33 kV bay, a duct bank sized for the second feeder and 30% free space in the switch room; that costs about 5% of the phase-one electrical budget and is the only part of the design that is genuinely hard to change later.

One further note for projects that combine an ASU with on-site generation: if the plant has a captive gas turbine or a solar-plus-BESS supply, the ASU's LCI becomes a load that the source must ride through, and the transformer's impedance now sits between two converters. The BESS step-up guide and the solar PV step-up guide cover the source side; the ASU side is unchanged, but the harmonic study must include the source's impedance at the same time as the plant's, or the resonant frequency will be calculated for a network that does not exist.

Sources / 资料来源

Source: IEC 60076-1:2011 — Power transformers, General.
Source: IEC 60076-2:2011 — Temperature rise for liquid-immersed transformers.
Source: IEC 60076-3:2013 — Insulation levels, dielectric tests and external clearances in air.
Source: IEC 60076-5:2006 — Ability to withstand short circuit.
Source: IEC 60076-7:2018 — Loading guide for oil-immersed power transformers, emergency loading tables.
Source: IEC 60076-11:2018 — Dry-type transformers.
Source: IEC 60038:2009 — Standard voltages, ±6% tolerance at 33 kV.
Source: IEC 60909-0:2016 — Short-circuit currents in three-phase AC systems, calculation of currents.
Source: IEC 60034-12 — Starting performance of single-speed three-phase cage induction motors.
Source: IEEE 519-2022 — Recommended practice and requirements for harmonic control in electric power systems, Table 1 total demand distortion limits.
Source: IEEE C57.12.00-2021 and C57.12.90-2021 — General requirements and test code for liquid-immersed transformers.
Source: GB 20052-2020 — Minimum allowable values of energy efficiency and energy efficiency grades for three-phase distribution transformers.
Source: GB/T 6451 — Technical parameters and requirements for oil-immersed power transformers.
Source: NFPA 55 — Compressed gases and cryogenic fluids code, separation distances for oxygen storage and venting.
Source: EN ISO 21014 — Cryogenic vessels, cryogenic insulation performance.
Source: Industry experience — specific power consumption of 0.55–0.62 kWh per Nm³ of oxygen for large cryogenic ASUs without product compression, and 0.65–0.75 kWh/Nm³ with gaseous nitrogen and oxygen compression, 2019–2026.
Source: Industry experience — LCI starting current of 40–50% of rated, ramp times of 90–140 s for 10–15 MW main air compressors, 2019–2026.
Source: Industry experience — 24-pulse LCI current distortion of 6–8% at the converter terminals and six-pulse VFD distortion of 30–40%, 2019–2026.
Source: Industry experience — 33 kV utility fault levels of 1,000–1,500 MVA and permitted starting voltage dips of 3–5% at the point of common coupling, 2019–2026.
Source: Industry experience — transformer, switchgear, filter and installation price ranges and 16–26 week lead times for 20–25 MVA, 33/11 kV units, FOB China, 2025–2026.
Source: Industry experience — industrial electricity tariffs of USD 0.07/kWh used in the loss and operating cost calculations.
Source: QDTB Engineering Team — load schedules, harmonic studies and 33/11 kV transformer specifications for air separation and industrial gas plants in Southeast Asia, the Middle East and Europe, 2021–2026.