QDTB® Transformer

Load & Demand Calculation Calculator

Build a load schedule from connected loads and demand factors, then derive the calculated demand (kW/kVA), demand current and a recommended transformer rating.

Start Calculating

Result

Enter your load → get a full design & BOM in seconds

Sample output
Calculated demand load
83.2 kW
97.9 kVA at PF 0.85 · connected 145.0 kW · Ks 0.8
Overall demand factor
72%
Demand current
141 A
Transformer
160 kVA
Load factor
61%
Load schedule
Load groupConnected kWDemand factorDemand kW
Lighting20.090%18.0
HVAC / air conditioning40.080%32.0
Motors & pumps60.070%42.0
Sockets / general purpose15.040%6.0
Other / special loads10.060%6.0
Subtotal (diversified)145.0104.0
Demand load (× Ks 0.8)83.2 kW
Result
Demand kVA83.2 kW ÷ 0.85 = 97.9 kVA
Demand current97.9 kVA ÷ (√3 × 0.4 kV) = 141 A
Recommended transformer97.9 kVA ÷ 0.8 = 122 kVA → 160 kVA (load factor 61%)
Bill of materials
EquipmentSpecQtySubtotal
Distribution transformer (S13 oil-immersed)160 kVA · 10/0.4 kV · Dyn111POA
Low-voltage switchgear (GCK/GCS)98 kVA demand · 141 A1POA
Total equipment (transformer)POA

For electrical designers and consultants doing the first step of any distribution design — feeder, switchgear and transformer sizing from a load schedule.

Use the calculator

Worked example

A pre-computed reference example (crawlable — no JavaScript required). Enter your own parameters above for a live result.

Example 1 — office & light-industrial load schedule

Calculated demand load
83.2 kW
97.9 kVA at PF 0.85 · connected 145.0 kW · Ks 0.8
Overall demand factor
72%
Demand current
141 A
Transformer
160 kVA
Load factor
61%
Load schedule
Load groupConnected kWDemand factorDemand kW
Lighting20.090%18.0
HVAC / air conditioning40.080%32.0
Motors & pumps60.070%42.0
Sockets / general purpose15.040%6.0
Other / special loads10.060%6.0
Subtotal (diversified)145.0104.0
Demand load (× Ks 0.8)83.2 kW
Result
Demand kVA83.2 kW ÷ 0.85 = 97.9 kVA
Demand current97.9 kVA ÷ (√3 × 0.4 kV) = 141 A
Recommended transformer97.9 kVA ÷ 0.8 = 122 kVA → 160 kVA (load factor 61%)
Bill of materials
EquipmentSpecQtySubtotal
Distribution transformer (S13 oil-immersed)160 kVA · 10/0.4 kV · Dyn111POA
Low-voltage switchgear (GCK/GCS)98 kVA demand · 141 A1POA
Total equipment (transformer)POA

Example 2 — commercial building with high HVAC share

Calculated demand load
134.6 kW
149.6 kVA at PF 0.9 · connected 235.0 kW · Ks 0.75
Overall demand factor
76%
Demand current
216 A
Transformer
200 kVA
Load factor
75%
Load schedule
Load groupConnected kWDemand factorDemand kW
Lighting30.090%27.0
HVAC / air conditioning120.085%102.0
Motors & pumps40.060%24.0
Sockets / general purpose25.050%12.5
Other / special loads20.070%14.0
Subtotal (diversified)235.0179.5
Demand load (× Ks 0.75)134.6 kW
Result
Demand kVA134.6 kW ÷ 0.9 = 149.6 kVA
Demand current149.6 kVA ÷ (√3 × 0.4 kV) = 216 A
Recommended transformer149.6 kVA ÷ 0.8 = 187 kVA → 200 kVA (load factor 75%)
Bill of materials
EquipmentSpecQtySubtotal
Distribution transformer (S13 oil-immersed)200 kVA · 10/0.4 kV · Dyn111POA
Low-voltage switchgear (GCK/GCS)150 kVA demand · 216 A1POA
Total equipment (transformer)POA

How it was calculated

  • · Connected load: P_conn = Σ P_i.
  • · Diversified demand: P_d = Σ (P_i × Kd_i).
  • · Calculated demand: P = P_d × Ks (simultaneity factor).
  • · Demand apparent power: S = P ÷ PF; demand current: I = P ÷ (√3 · U).
  • · Recommended transformer: S_tr = S ÷ target load factor (0.8), rounded up to a standard size.

Referenced standards

StandardScope
IEC 60364Low-voltage electrical installations
IEEE 241Recommended practice for electric power systems in commercial buildings (Gray Book)
GB 50054Code for design of low-voltage electrical installations

Frequently asked questions

What is the difference between connected load and demand load?

Connected load is the sum of all equipment nameplate ratings; demand load is the maximum power actually drawn simultaneously, equal to connected load x demand factor. A 500 kW connected load at 0.7 demand factor has a 350 kW demand. Transformers are sized to demand, not connected load. The calculator computes demand from connected load.

What demand factor should I use for different building types?

Typical demand factors: residential 0.3-0.5, commercial/office 0.4-0.6, industrial 0.6-0.8, continuous process 0.8-0.9. A hospital runs 0.7-0.8. Using the right factor prevents a 30-50% Transformer oversize. The calculator provides guidance and computes the recommended kVA.

How do I convert demand kW to transformer kVA?

kVA = demand kW / Power Factor. A 350 kW demand at 0.9 pf needs 389 kVA, so select 400 kVA. If power factor is uncorrected at 0.75, the same load needs 467 kVA — power factor correction shrinks the transformer. The calculator applies pf and selects the standard rating.

What is the NEC vs IEC demand factor difference?

NEC Article 220 gives table-based demand factors per appliance/load type; IEC/GB practice uses engineering judgment and experience factors per building type. Both aim to avoid oversizing. The calculator uses engineering demand factors aligned with GB 50052 and IEC practice.

How do I account for future growth in load demand?

Add 15-25% to the present demand for growth, then select the next standard transformer rating. If present demand is 350 kVA, plan for ~440 kVA and select 500 kVA (or 2x250 kVA). The calculator's margin guidance keeps the transformer loadable at 70-80% after growth.

Embed this calculator

Add this calculator to your own website for free. The iframe adapts to any width and runs entirely in your visitor's browser.

Related tools

Results are engineering estimates for preliminary design and reference only. Always verify with the applicable standards, the equipment nameplate and a licensed engineer before procurement or installation.

Send my complete design report

Get the full bill of materials, single-line diagram, calculation steps and FOB pricing as a PDF — free, no sign-up.

💬 Chat on WhatsApp

Your data stays private. No spam — only a reply to your enquiry.