QDTB® Transformer

UPS Sizing & Battery Runtime Calculator

Size an uninterruptible power supply and its battery bank from the load, power factor and required autonomy — and see the actual runtime the installed battery delivers.

Start Calculating

Result

Enter your load → get a full design & BOM in seconds

Sample output
Recommended UPS rating
80 kVA
50 kW load · PF 0.8 · 30 min autonomy · VRLA lead-acid (12 V block)
UPS power
72 kW
Battery bank
32 blocks · 200 Ah
Actual runtime
39 min
Load margin
15%
Sizing calculation
StepValue
Load apparent powerS = P ÷ PF = 50 kW ÷ 0.8 = 62.5 kVA
Required UPS (loading factor)62.5 ÷ 0.8 = 78.1 kVA → standard 80 kVA
Battery energyE = P·t ÷ (ηinv·ηbat·DOD) = 50 kW × 0.50 h ÷ (0.94 × 0.9 × 0.5) = 59.10 kWh
Total battery capacity59.10 kWh ÷ 384 V = 154 Ah
Series blocks per string384 V ÷ 12 V = 32
Parallel strings154 Ah ÷ 200 Ah = 1
Battery configuration
String voltage32 × 12 V = 384 V
Installed capacity1 × 200 Ah = 200 Ah
Actual runtime(200 Ah × 384 V × 0.94 × 0.9 × 0.5) ÷ 50 kW = 39 min
Estimated recharge200 Ah ÷ 20 A (0.1C) × 1.1 ≈ 11.0 h
Bill of materials
EquipmentSpecQtySubtotal
Online double-conversion UPS80 kVA / 72 kW · 384 V DC bus1POA
VRLA lead-acid (12 V block) battery bank32S×1P (32 blocks, 200 Ah @ 384 V)1POA
Battery charger / rectifier20 A charging current1POA
Total equipment (UPS + charger)POA

For facility managers, data-center designers and electrical engineers sizing single- or three-phase UPS systems with VRLA or LiFePO₄ battery banks.

Use the calculator

Worked example

A pre-computed reference example (crawlable — no JavaScript required). Enter your own parameters above for a live result.

Example 1 — 50 kW data-center load, 30 minutes autonomy

Recommended UPS rating
80 kVA
50 kW load · PF 0.8 · 30 min autonomy · VRLA lead-acid (12 V block)
UPS power
72 kW
Battery bank
32 blocks · 200 Ah
Actual runtime
39 min
Load margin
15%
Sizing calculation
StepValue
Load apparent powerS = P ÷ PF = 50 kW ÷ 0.8 = 62.5 kVA
Required UPS (loading factor)62.5 ÷ 0.8 = 78.1 kVA → standard 80 kVA
Battery energyE = P·t ÷ (ηinv·ηbat·DOD) = 50 kW × 0.50 h ÷ (0.94 × 0.9 × 0.5) = 59.10 kWh
Total battery capacity59.10 kWh ÷ 384 V = 154 Ah
Series blocks per string384 V ÷ 12 V = 32
Parallel strings154 Ah ÷ 200 Ah = 1
Battery configuration
String voltage32 × 12 V = 384 V
Installed capacity1 × 200 Ah = 200 Ah
Actual runtime(200 Ah × 384 V × 0.94 × 0.9 × 0.5) ÷ 50 kW = 39 min
Estimated recharge200 Ah ÷ 20 A (0.1C) × 1.1 ≈ 11.0 h
Bill of materials
EquipmentSpecQtySubtotal
Online double-conversion UPS80 kVA / 72 kW · 384 V DC bus1POA
VRLA lead-acid (12 V block) battery bank32S×1P (32 blocks, 200 Ah @ 384 V)1POA
Battery charger / rectifier20 A charging current1POA
Total equipment (UPS + charger)POA

Example 2 — 120 kW load, 60 minutes, lithium battery

Recommended UPS rating
200 kVA
120 kW load · PF 0.9 · 60 min autonomy · LiFePO₄ lithium (48 V module)
UPS power
180 kW
Battery bank
10 blocks · 350 Ah
Actual runtime
68 min
Load margin
35%
Sizing calculation
StepValue
Load apparent powerS = P ÷ PF = 120 kW ÷ 0.9 = 133.3 kVA
Required UPS (loading factor)133.3 ÷ 0.8 = 166.7 kVA → standard 200 kVA
Battery energyE = P·t ÷ (ηinv·ηbat·DOD) = 120 kW × 1.00 h ÷ (0.94 × 0.95 × 0.9) = 149.31 kWh
Total battery capacity149.31 kWh ÷ 480 V = 311 Ah
Series blocks per string480 V ÷ 48 V = 10
Parallel strings311 Ah ÷ 350 Ah = 1
Battery configuration
String voltage10 × 48 V = 480 V
Installed capacity1 × 350 Ah = 350 Ah
Actual runtime(350 Ah × 480 V × 0.94 × 0.95 × 0.9) ÷ 120 kW = 68 min
Estimated recharge350 Ah ÷ 35 A (0.1C) × 1.1 ≈ 11.0 h
Bill of materials
EquipmentSpecQtySubtotal
Online double-conversion UPS200 kVA / 180 kW · 480 V DC bus1POA
LiFePO₄ lithium (48 V module) battery bank10S×1P (10 blocks, 350 Ah @ 480 V)1POA
Battery charger / rectifier35 A charging current1POA
Total equipment (UPS + charger)POA

How it was calculated

  • · Load apparent power: S = P ÷ PF.
  • · Required UPS rating: S_UPS = S ÷ loading factor (typical 0.8), rounded up to a standard size.
  • · Battery energy: E = P · t ÷ (η_inv · η_bat · DOD).
  • · Battery capacity: Ah = E ÷ V_dc; series blocks = V_dc ÷ V_block; parallel strings = required Ah ÷ block Ah.
  • · Actual runtime: t = (installed Ah · V_dc · η_inv · η_bat · DOD) ÷ P.

Referenced standards

StandardScope
IEC 62040-3Uninterruptible power systems — method of specifying performance and test requirements
IEEE 1184Guide for batteries for uninterruptible power supply systems
IEEE 485Recommended practice for sizing lead-acid batteries for stationary applications

Frequently asked questions

How do I size a UPS for my load?

UPS kVA = load kW / Power Factor, plus 20-30% margin and future growth. A 40 kW IT load at 0.9 pf needs ~44 kVA, so select 60 kVA. Add margin for inrush and non-linear loads. The calculator sizes UPS kVA, battery Ah and runtime.

How is UPS battery runtime calculated?

Runtime depends on battery capacity (Ah), string voltage, load and efficiency. For a 40 kW load on a 240 V battery string, a 100 Ah bank gives roughly 20-30 minutes. The calculator computes actual runtime from battery blocks, DoD and load, and reports recharge time.

What is the difference between online and line-interactive UPS?

Online (double-conversion) UPS continuously rectifies and inverts, giving zero transfer time and full power conditioning — required for data centers. Line-interactive passes utility power and corrects only on events, cheaper but with a brief transfer. The calculator's sizing assumes online double-conversion for critical loads.

What battery type is used in UPS systems?

Valve-regulated lead-acid (VRLA) dominates UPS for low cost and maintenance-free operation, with a 3-5 year typical life. Lithium (LFP) is gaining share for longer life (10+ years), smaller footprint and higher cycle count, at 2-3x the upfront cost. The calculator sizes the battery bank for either chemistry.

How much runtime do I need before the generator starts?

Battery runtime must bridge to generator start, typically 5-15 minutes (generators reach full load in 30-60 s). Without a generator, size for 30-60 minutes for graceful shutdown. Longer runtime adds cost roughly linearly. The calculator lets you set runtime and sizes the battery accordingly.

Embed this calculator

Add this calculator to your own website for free. The iframe adapts to any width and runs entirely in your visitor's browser.

Related tools

Results are engineering estimates for preliminary design and reference only. Always verify with the applicable standards, the equipment nameplate and a licensed engineer before procurement or installation.

Send my complete design report

Get the full bill of materials, single-line diagram, calculation steps and FOB pricing as a PDF — free, no sign-up.

💬 Chat on WhatsApp

Your data stays private. No spam — only a reply to your enquiry.