The answer first: an offshore export transformer is sized by N-1 capacity and platform weight, not by farm nameplate
For a 500 MW offshore wind farm collecting at 66 kV and exporting at 220 kV, the standard answer is two 300 MVA, 66/220 kV, YNd11, ONAN/ONAF transformers with 14% impedance, each running at about 88% of rating at full farm output, so that one unit can still export roughly 285 MW after a single failure. Three constraints then override the electrical calculation: the transformer must fit a platform crane and deck load (about 260 t oil-filled for 300 MVA), it must survive C5-M salt fog with 31 mm/kV creepage and a 320–400 µm coating system, and beyond roughly 80–120 km of 220 kV export cable the charging current and reactive compensation become unmanageable — at which point the farm switches to HVDC and the export transformer is replaced by converter transformers.
Key takeaways
- Size on N-1, not on 2 × 50%. A 500 MW farm at 0.95 pf needs 526 MVA at the point of connection. Two 300 MVA units give 88% normal loading and 57% firm capacity after one outage — the curtailment most grid codes and offtake contracts accept.
- 66 kV array voltage is what makes 500 MW practical. Total array current falls from about 9.2 kA at 33 kV to 4.6 kA at 66 kV, halving the number of collector feeders and cable copper for the same loss budget.
- Weight is a hard limit, not a cost trade-off. A 300 MVA 220 kV unit is roughly 260 t with oil and 9.5 m long; the platform crane, deck strength and sea-fastening design are fixed before the transformer is ordered. Ask for the transport weight and centre of gravity in the enquiry, not after award.
- Salt fog changes the outside, not the core. C5-M paint, A4-70 stainless hardware, IP55 minimum (IP66 in exposed rooms), 31 mm/kV creepage, anti-condensation heaters and sealed conservator breathers are the specification items that decide whether the unit reaches 25 years.
- HVAC export dies somewhere between 80 and 120 km at 500 MW. A 220 kV cable draws about 7.5 A/km of charging current per phase; over 80 km that is roughly 600 A, or 230 MVAr, against a 1,381 A load current. HVDC becomes cheaper before the cable becomes electrically impossible.
Why is an offshore substation transformer not just an onshore unit on a platform?
Electrically it is a normal power transformer. Mechanically, thermally and logistically it is a different product. An onshore 300 MVA unit is designed around a concrete foundation, unlimited air, a road tanker for oil and a crew that can arrive in an hour. An offshore unit is designed around a steel deck with a known crane rating, a sealed room with ducted cooling, a jack-up vessel that visits twice a year, and an environment that deposits salt on every surface.
Those differences show up in five places. The tank and cooling equipment must be arranged for a narrow transport envelope and a single lift. The cooling system must reject heat through ducts or heat exchangers rather than open radiators. The insulation system must tolerate high humidity and salt contamination on bushings that are never washed. The monitoring must be remote, because nobody is on board. And the documentation must prove all of it to a classification society and an insurer before the platform leaves the yard.
The result is that an offshore-specified 300 MVA transformer typically costs 25–45% more than the same rating for an onshore substation, and weighs 5–10% more because of the tank stiffening, corrosion allowance and cooling redundancy. That premium is not margin for the manufacturer; it is paint, stainless steel, duplicate pumps, monitoring and third-party witness testing.
How do you size the export transformer for a 500 MW wind farm?
Start at the point of connection, not at the turbine terminals. The grid operator sets a power factor or reactive range at the onshore connection — commonly 0.95 leading to 0.95 lagging under ENTSO-E NC RfG — so the export transformer carries apparent power, not just active power. Then apply the redundancy rule from the offtake agreement or the transmission licence, and only then choose a standard rating.
Step 1 — convert MW at the connection point into MVA at the transformer
For 500 MW at 0.95 power factor, the apparent power is 500 / 0.95 = 526 MVA. Add the platform auxiliary load (typically 3–6 MW for cooling, HVAC, control, crane and accommodation) and the export transformer sees about 530 MVA at full output. Cable losses between the platform and shore are downstream of the transformer and are covered by the onshore reactive compensation, not by extra transformer rating.
Step 2 — apply the N-1 rule and pick the unit rating
Two units are the norm for any farm above 200 MW, for three reasons: the largest single lift a platform crane can make, the desire to keep one unit exporting during maintenance, and the fault level at the 66 kV bus. A 500 MW farm with two 300 MVA units runs each at 88% at full output and retains 300 MVA — about 285 MW at 0.95 pf — after one unit trips. The farm controller then curtails to that figure until the unit is restored.
| Farm export capacity | Typical turbines | Array voltage | Export voltage | Export transformers | Normal loading at full output |
|---|---|---|---|---|---|
| 200 MW | 24 × 8.3 MW | 66 kV | 132 kV | 2 × 120 MVA | 88% |
| 500 MW | 60 × 8.3 MW | 66 kV | 220 kV | 2 × 300 MVA | 88% |
| 900 MW | 108 × 8.3 MW | 66 kV | 275 kV | 3 × 320 MVA | 94% |
| 1,200 MW (phased) | 2 × 72 × 8.3 MW | 66 kV | 275 kV or HVDC | 2 × 700 MVA or converter units | 86% |
| 1,400 MW (remote) | 168 × 8.3 MW | 66 kV | ±320 kV DC | Converter transformers, 12 single-phase units | n/a |
Step 3 — choose impedance to control the 66 kV fault level
Impedance is where electrical design meets switchgear cost. A 300 MVA transformer with 12% impedance delivers about 21.9 kA at the 66 kV terminals on its own; two in parallel give 43.8 kA, which forces 50 kA array switchgear and heavier busbars. At 14% the figures fall to 18.7 kA and 37.5 kA, allowing 40 kA switchgear. Most offshore platforms therefore specify 13–15% on the export units, accepting slightly worse voltage regulation in exchange for a cheaper and more compact 66 kV board. The calculation method is the same as for any transformer — see transformer short-circuit current calculation.
Voltage regulation is corrected by the on-load tap changer on the 220 kV side, normally ±8 × 1.25% (17 positions), with the AVR controlled from the onshore point of connection rather than the platform. If the farm is required to hold voltage at the POI across the full export range, the tap range and the reactive compensation must be designed together; a transformer alone cannot fix a cable that generates 230 MVAr.
66 kV or 33 kV array — which voltage should the platform collect at?
Both are used, but the economics have moved decisively to 66 kV above roughly 300 MW. Current is the reason. At 500 MW and 0.95 pf, the total array current is 4,601 A at 66 kV and 9,204 A at 33 kV. Halving the current quarters the resistive loss for the same conductor, or halves the copper for the same loss. It also halves the number of collector feeders: ten 50 MW feeders at 66 kV instead of sixteen to twenty at 33 kV, which matters because every feeder needs a switchgear bay on a platform where floor area is the most expensive square metre in the project.
| Parameter at 500 MW, 0.95 pf | 33 kV collection | 66 kV collection |
|---|---|---|
| Total array current | 9,204 A | 4,601 A |
| Typical feeder rating | 25–40 MW | 50–70 MW |
| Number of 66 kV switchgear bays (approx.) | 16–20 incomers + bus coupler | 10 incomers + bus coupler |
| Array cable conductor for 50 MW feeder | 3 × 630 mm² parallel runs | 1 × 630 mm² |
| Array cable loss at full output (approx.) | 2.5–3.5% | 1.2–1.8% |
| WTG transformer | 0.69/33 kV, 9 MVA | 0.69/66 kV, 9 MVA |
The 66 kV WTG transformer is the same physical size as its 33 kV equivalent in most designs, because the insulation increment at this level is small relative to the core and winding. That is why the switch to 66 kV happened quickly once 66 kV array cables and switchgear became commercially available: the turbine nacelle did not have to grow.
Turbine-side sizing and harmonic duty are covered separately in the wind farm step-up transformer guide; the platform transformer sees the sum of those converter harmonics but at a much lower current distortion, because the array cables and the multiple turbine converters dilute it.
HVAC or HVDC export: where is the crossover?
AC export is limited by charging current, not by conductor thermal rating. A 220 kV XLPE cable has roughly 0.19 µF/km of capacitance, which at 50 Hz draws about 7.5 A/km per phase. Over 80 km that is 600 A of charging current against a 1,381 A load current — 43% of the cable capacity consumed before any power reaches shore. The reactive power is √3 × 220 kV × 600 A ≈ 229 MVAr, which must be compensated by shunt reactors on the platform, adding weight, space and another failure mode.
| Export at 500 MW | Load current | Charging current per km | Charging current at 80 km | Practical AC distance |
|---|---|---|---|---|
| 132 kV AC | 2,302 A | 6.0 A/km | 480 A (21%) | 40–60 km — cable rating binds first |
| 220 kV AC | 1,381 A | 7.5 A/km | 600 A (43%) | 80–120 km |
| 275 kV AC | 1,105 A | 9.4 A/km | 752 A (68%) | 100–140 km |
| ±320 kV DC | 900 A per pole | none (DC) | none | no practical distance limit |
Two consequences follow. First, a 500 MW farm at 80 km is still a comfortable HVAC project but needs two export cable circuits rated about 700 A each, plus 150–250 MVAr of shunt reactors, and the platform deck must carry them. Second, beyond roughly 120 km, or where the farm crosses a fjord or a marine protected area that forbids reactive compensation platforms, the project goes HVDC — and the equipment changes completely. The export transformer becomes a converter transformer bank: 12 single-phase units (or 6 three-phase) with valve-side windings designed for DC bias and high harmonic content, plus a converter hall that dwarfs the transformer room.
For a transformer supplier the practical message is that the HVAC/HVDC decision is taken at feasibility stage and must be fixed before the transformer enquiry. A converter transformer and an export transformer are not interchangeable, and a late change costs a year of design and a new platform layout.
Oil-immersed or dry-type on an offshore platform?
Oil-immersed wins above about 100 MVA, and the reason is not preference but physics. A 300 MVA dry-type unit at 220 kV would need air clearances and a cast-resin or vacuum-cast winding that no one builds economically at that rating; the unit would also be larger than the oil-filled equivalent and would lose the oil's role as a coolant and as an insulation medium. Dry-type is used offshore for auxiliary and platform service transformers, typically 1–20 MVA at 6.6/11/33 kV, where the absence of oil removes a fire load and a spill risk from an enclosed room.
| Factor | Oil-immersed export transformer | Dry-type (cast resin) |
|---|---|---|
| Economic rating range at 66–220 kV | 60–700 MVA | up to about 40 MVA at 66 kV |
| Weight for 300 MVA (approx.) | 260 t with oil | not built at this rating |
| Fire load | Oil volume 60–90 t; requires containment, deluge and drainage | Class F1 fire behaviour, no oil pool |
| Cooling | ONAN/ONAF radiators, or ODAF with sea-water or air heat exchangers | AN/AF with ducted room ventilation |
| Maintenance offshore | Oil sampling, DGA, breather, pumps, tap changer | Cleaning, partial discharge monitoring, no oil work |
| Corrosion exposure | Tank and radiators need C5-M system and stainless fittings | Resin surface inert, but fan and frame still corrode |
| Preferred use on platform | Export and array main transformers | Auxiliary, earthing, UPS, HVAC supply |
If the export unit is oil-immersed, the platform must provide a bunded room with a capacity for at least the full oil volume, an oil–water separator before any overboard drain, fire detection and a deluge or water-mist system, and ventilation that removes heat without admitting salt spray. These are platform costs, not transformer costs, but they are decided by the transformer choice — which is why the specification has to be agreed with the topside designer before the enquiry.
How does the marine environment change the specification?
Offshore atmosphere is classified C5-M under ISO 12944, the most severe category short of immersion. Every external steel surface, including the tank, radiators, cooler frames, cable boxes and conservator, needs a coating system of at least 320 µm total dry film thickness, typically an epoxy zinc-rich primer, an epoxy intermediate coat and a polyurethane topcoat. Many operators go further and invoke NORSOK M-501 for surface preparation and coating selection. Hot-dip galvanised parts are not a substitute; galvanising plus paint is.
Bushings deserve their own paragraph. A 245 kV bushing at 31 mm/kV needs about 7.6 m of creepage, and offshore units normally specify a composite (RIP or HTV silicone) bushing rather than porcelain, because a porcelain shed that cracks under thermal cycling admits moisture directly into the oil. Composite sheds are hydrophobic and resist salt build-up; they also survive the vibration of transport better. The specification should state the creepage per unit of highest system voltage, the shed profile, and the pollution severity class from IEC 60815, rather than just the rated voltage.
Other items that appear in every serious offshore specification:
- IP55 minimum, IP66 for exposed rooms. Enclosures must resist driven rain and salt spray, and every enclosure needs a drain and a breather that does not admit water.
- Anti-condensation heaters rated for the standby condition, typically 2 × 3 kW at 220 V, interlocked so they run when the transformer is de-energised.
- Sealed conservator or bladder-type oil preservation to keep moist marine air out of the oil; silica gel breathers alone are not adequate for a unit that may sit de-energised for months.
- A4-70 stainless steel for all external fasteners, and duplex stainless for cable ladders and clamps in splash zones.
- Stainless or copper-nickel cooling circuits if sea-water heat exchangers are used, with double-wall tubes and leak detection so that a tube failure cannot contaminate the oil.
- Vibration and shock qualification for transport and for platform motion, with the sea-fastening design and accelerometer records included in the transport plan.
What weight and dimensions can an offshore platform actually carry?
This is the constraint that surprises onshore buyers. A 300 MVA, 220/66 kV oil-immersed transformer is about 9.5 m long, 4.2 m wide and 4.6 m high, and weighs 250–270 t with oil. Add transport skid, sea fastening and lifting gear and the hook load approaches 290 t. The platform crane is usually sized at 350–450 t to leave margin, and the deck must take that load through four or six jacking points into the topside structure.
Weight can be reduced in three ways, each with a cost. Shipping without oil removes 60–90 t and is standard practice: the unit travels nitrogen-filled at slight positive pressure, is inspected on arrival, and is filled and vacuum-treated on the platform using a temporary oil processing plant. Reducing the tank thickness is not an option — offshore tanks are stiffened for transport and for platform acceleration, and the corrosion allowance is set by the coating system's expected life. Selecting a higher-impedance, lower-loss design can shrink the core, but it also changes the fault level and the price.
Ask for four numbers in the enquiry, and make them contractual: transport weight, transport dimensions, centre of gravity, and lifting point loads. A manufacturer who cannot supply these at quotation stage is not experienced in offshore work, however good their onshore references are. The same discipline applies to the transport and installation plan described in transformer transportation and installation.
What changes for floating wind?
Floating platforms add motion. The transformer must tolerate static tilt of ±5° and dynamic roll and pitch of ±2–3° with accelerations at the deck of 0.2–0.5 g, depending on the platform concept and the sea state. That has three design consequences. The conservator must be baffled or replaced by a sealed tank with a gas cushion, because oil sloshing can expose the winding top and aerate the oil. The core and winding clamping must be designed for the additional dynamic load, and the tank must be analysed for fatigue rather than just static strength. And the on-load tap changer is often replaced by an off-circuit link, because a tap changer that must operate under motion and without maintenance access is a reliability liability.
Floating wind also pushes the export voltage decision earlier. A floating farm far from shore is usually HVDC or a high-voltage AC link with dynamic cables, and the transformer is either a converter transformer on the floater or a conventional unit on a fixed platform downstream. Either way, the motion specification has to be in the enquiry; a standard onshore unit with a note saying "marine coating" will not pass the classification review.
How should you evaluate losses and total cost?
Offshore losses cost more than onshore losses, because every kilowatt dissipated on the platform has to be removed by the cooling system and, in summer, by the HVAC plant. Most developers capitalise no-load loss at USD 5,000–8,000 per kW and load loss at USD 1,000–2,000 per kW, with the exact figures taken from their energy price and the farm's capacity factor. Those rates make loss evaluation a real design driver, not a formality.
Take a 300 MVA unit with 150 kW no-load loss and 1,050 kW load loss at rated output. At USD 6,000/kW and USD 1,500/kW, the capitalised loss value is USD 0.90M + USD 1.58M = USD 2.48M — comparable to 60–80% of the transformer price itself. A lower-loss design using a larger core and more copper might add USD 250,000 to the price and remove 40 kW of total loss, saving USD 300,000 in capitalised terms. That trade is worth doing, but only when the loss rates are stated in the specification; without them every bidder optimises for first cost.
| Cost element for a 300 MVA offshore export transformer | Typical value | Notes |
|---|---|---|
| Transformer price, FOB China | USD 3.0–4.2 million | Offshore specification, C5-M, monitoring, redundancy |
| Capitalised no-load loss (150 kW at USD 6,000/kW) | USD 0.90 million | Runs 8,760 h/year |
| Capitalised load loss (1,050 kW at USD 1,500/kW) | USD 1.58 million | Depends on capacity factor and loss rate |
| Transport, sea fastening and installation | USD 0.4–0.9 million | Jack-up vessel day rates dominate |
| Platform civil, bunding, fire protection | USD 0.5–1.2 million | Driven by oil volume and room size |
| Offshore commissioning and oil processing | USD 0.2–0.4 million | Includes vacuum plant and specialist crew |
Values are industry experience ranges for 2026 and vary with copper price, platform concept and vessel market. They are given so that a buyer can see the shape of the cost stack, not as a quotation. The loss-grade logic for distribution units is explained in S11 vs S13 vs S20 loss grades; the principle is identical at transmission ratings, only the capitalisation rates change.
Which protection and monitoring systems are mandatory?
An offshore transformer is unmanned, so protection must be complete and monitoring must be able to predict a failure weeks in advance. The electrical protection package is conventional: overall differential (87T), restricted earth fault (64REF), overcurrent and earth fault backup, Buchholz or sudden-pressure relay, pressure relief device, oil and winding temperature trips, and tap changer monitoring. What differs is the specification of the sensors and their communication.
- Online DGA — at minimum hydrogen, carbon monoxide, ethylene and acetylene, with trends transmitted to the control centre. A single gas reading is useless; the rate of change is the diagnostic.
- Fibre-optic winding temperature — direct hot-spot measurement rather than a calculated thermal image, because the loading guide calculation assumes cooling conditions that may not hold in a ducted room.
- Bushing monitoring — leakage current and capacitance for each 220 kV bushing, or at least a portable tap for later measurement.
- Moisture in oil — relative saturation and temperature, so that a drying cycle can be planned before the paper absorbs water.
- Cooling plant status — pump running, fan running, flow and differential pressure, with automatic start of the standby pump and an alarm on any loss of redundancy.
- OLTC monitoring — motor current, tap position, number of operations and filter pressure, if an on-load tap changer is fitted.
All of this has to be wired to a substation control system that survives the loss of the platform's auxiliary supply. Specify the protocol (IEC 61850 is now standard), the redundant power supply, and the local historian that keeps 30 days of data so that a transient is not lost while the link to shore is down.
What does FAT, sea fastening and commissioning involve?
Factory acceptance testing follows IEC 60076-1: ratio and polarity, winding resistance, impedance and load loss, no-load loss and current, applied voltage and induced voltage dielectric tests, and a full impulse test on the line terminal. Offshore projects normally add a temperature-rise type test if the design is new, a noise measurement to IEC 60076-10, and a third-party witness from the classification society or the owner's engineer. The witness should see the loss measurement itself, not a certificate — loss figures are the easiest item to dispute later.
Sea fastening is a design package, not a shipping note. It includes the skid, the welded or bolted restraints, the shock-absorbing pads, the accelerometer log, and a calculation showing that the arrangement survives the design storm and the vessel motions. The transformer should travel with impact recorders and a nitrogen pressure gauge that can be read without opening the tank. On arrival, the pressure and dew point are recorded before any valve is touched; a unit that arrived at zero pressure has to be dried before oil filling.
Commissioning on the platform repeats a subset of the FAT and adds the system tests: oil filling under vacuum to a defined vacuum and holding time, standing time before energisation, SFRA and DGA baselines, protection relay secondary injection, interlock and trip tests with the platform control system, and a first-energisation sequence with the export cable and the onshore grid connected. The pre-shipment and pre-energisation checklists in transformer pre-shipment inspection and transformer commissioning tests apply, with the marine items added.
Offshore wind transformer specification checklist
| Item | Typical offshore requirement | Why it matters |
|---|---|---|
| Rating and voltage | 300 MVA, 66/220 kV, YNd11, 50 Hz | Matches farm capacity and export voltage |
| Impedance | 13–15% on rating | Limits 66 kV fault level to 40 kA switchgear |
| Cooling | ONAN/ONAF, 65%/100%, N+1 pumps and fans | Full output with one cooler circuit out |
| Temperature rise | 60 K top oil / 78 K hot spot at 45°C ambient | Marine ambient and ducted room |
| Tap changer | OLTC ±8 × 1.25% on HV, or off-circuit links for floating | Voltage control at POI |
| Corrosion protection | ISO 12944 C5-M, 320–400 µm, NORSOK M-501 option | 25-year external life |
| Bushings | Composite, 31 mm/kV creepage, IEC 60137 | Salt pollution and vibration |
| Enclosure | IP55 minimum, IP66 exposed, anti-condensation heaters | Driven rain and condensation |
| Oil preservation | Sealed conservator or bladder, no open breather | Moisture ingress during standby |
| Monitoring | Online DGA, fibre-optic temperature, bushing and moisture monitoring, IEC 61850 | Unmanned operation |
| Transport | Oil-less nitrogen fill, impact recorders, sea-fastening calculation | Deck load and vessel motion |
| Testing | IEC 60076-1 routine + impulse + temperature rise, third-party witness | Insurer and classification acceptance |
Frequently asked questions about offshore wind substation transformers
How large is an offshore wind export transformer?
Most units fall between 120 MVA and 400 MVA, at export voltages of 132, 220 or 275 kV. A 300 MVA, 220/66 kV unit is about 9.5 m long, 4.2 m wide and 4.6 m high, and weighs 250–270 t with oil. Above about 400 MVA the transport weight and the platform crane become the limiting factors, which is why very large farms use three units or switch to HVDC converter banks.
Why not use one transformer instead of two?
Because a single unit makes the farm dependent on one asset and one lift. Two units allow maintenance without a full outage, keep each unit in the efficient 70–90% loading band, and let the platform crane and deck be designed around a smaller load. The cost penalty is modest — two 300 MVA units cost perhaps 15–25% more than one 600 MVA unit — and it buys N-1 capability that most offtake contracts require.
Can a dry-type transformer be used for the export?
Not economically above about 40 MVA at 66 kV, and not at 220 kV. Dry-type units are used for platform auxiliary supplies, where the absence of oil removes a fire load from an enclosed space. For the export unit, oil-immersed is the only practical choice at 100 MVA and above, with the oil containment and fire protection designed into the platform.
How long does an offshore transformer take to manufacture and deliver?
Allow 12–18 months from award for a 300 MVA offshore-specified unit, including design review, third-party witness testing and transport. The offshore specification adds 6–10 weeks over an equivalent onshore unit because of the coating system, the monitoring package and the documentation. Platform installation windows are fixed by vessel availability, so the transformer is usually ordered before the topside fabrication contract is placed.
When does a project switch from HVAC to HVDC?
Roughly when the export distance exceeds 80–120 km at 500 MW, or earlier if the cable route requires heavy reactive compensation, or if the farm is larger than about 1 GW at a long distance. The decision is driven by charging current and cable losses, not by transformer cost. Once HVDC is chosen, the export transformer becomes a converter transformer and the platform layout changes completely.
What is the most common specification mistake?
Treating the transformer as an onshore unit with a marine paint specification. The failures that follow are predictable: a tank that does not fit the transport envelope, a cooling system that cannot reject heat in a sealed room, bushings that flash over in salt fog after two years, and a monitoring package that cannot be integrated with the platform control system. The fix is to write the platform constraints — weight, dimensions, ambient, cooling medium, communication protocol — into the enquiry, and to require the manufacturer to confirm each one in the bid.
Sources / 资料来源
- Source: IEC 60076-1 — Power transformers: General
- Source: IEC 60076-2 — Temperature rise for liquid-immersed transformers
- Source: IEC 60076-3 — Insulation levels, dielectric tests and external clearances
- Source: IEC 60076-5 — Ability to withstand short circuit
- Source: IEC 60076-7 — Loading guide for oil-immersed power transformers
- Source: IEC 60076-10 — Determination of sound levels
- Source: IEC 60076-11 — Dry-type transformers
- Source: IEC 60137 — Insulated bushings for alternating voltages above 1,000 V
- Source: IEC 60815 — Selection and dimensioning of high-voltage insulators for polluted conditions
- Source: IEC 60071 — Insulation co-ordination
- Source: ISO 12944 — Corrosion protection of steel structures by protective paint systems
- Source: NORSOK M-501 — Surface preparation and protective coating
- Source: DNV-ST-0145 — Offshore substations
- Source: ENTSO-E Regulation (EU) 2016/631 — Network code on requirements for grid connection of generators
- Source: QDTB export quotation ranges, Q4 2026, FOB Qingdao, and industry experience values for offshore loss capitalisation and installation cost