Metro Traction Rectifier Transformer: How to Size a 1,500 V DC Traction Substation — and Why the 150% Two-Hour Rating, Not the Nameplate, Carries the Peak

How to size a 1,500 V DC metro traction substation: a 6-car train drawing 2,880 kW of traction plus 180 kW of auxiliaries pulls 3,429 kW and 2,286 A at the DC bus, which is 3,627 kVA of transformer apparent power per train, so two trains accelerating in one section load 2 × 2,500 kVA to 145.1% and only the 150%/2 h duty class makes that legal. At uk 8% the prospective DC fault is 39 kA and fits 50 kA switchgear, uk 6% gives 52 kA and forces 63 kA boards, and because the unit lives at a 15.6% average load factor, 89% of its lifetime loss is no-load loss: 30 units burn 1,061 MWh a year, USD 84,800 at USD 0.08/kWh and USD 1.08 million in 25-year present value.

By QDTB Engineering Team·Updated 2026-11-22
Metro Traction TransformerRectifier Transformer Sizing1500 V DC Traction Substation12-Pulse Rectifier TransformerTraction Transformer Duty ClassDC Short Circuit CurrentCast Resin Transformer TunnelMetro Substation Specification

The answer first: a 1,500 V DC metro traction substation is built around two 2,500 kVA rectifier transformers — because the load it must carry is 145% of nameplate, not 100%

A 25 km metro line running 1,500 V DC traction needs a traction substation roughly every 1.6 km, and each of those substations is built on 2 × 2,500 kVA rectifier transformers — not because the trains consume 5,000 kVA on average, but because two trains accelerating in the same electrical section demand 7,254 kVA, or 145.1% of the installed nameplate, and only the 150% two-hour rating makes that legal. One 6-car train drawing 2,880 kW of traction plus 180 kW of auxiliaries pulls 3,429 kW from the DC bus, which at the 1,500 V nominal rail voltage is 2,286 A and 3,627 kVA of transformer apparent power once rectifier power factor and transformer efficiency are accounted for. Everything else in the specification follows from those two numbers: 8% impedance to hold the prospective DC fault at 39 kA instead of 52 kA, a 12-pulse rectifier to keep the 33 kV point of connection clean, cast-resin construction because there is no oil allowed in a tunnel, and a no-load-loss figure that carries 89% of the transformer's lifetime energy loss because the unit spends its life at a 15.6% average load.

Key takeaways

  • The nameplate is not the rating. A 2,500 kVA rectifier transformer in metro duty is specified at 100% continuous, 150% for 2 hours and 300% for 60 seconds; the 150% band is the one that runs the timetable, and it is reached every time two trains accelerate in the same section.
  • 2,286 A per train, 3,627 kVA per train. A 6-car train at 2,880 kW traction plus 180 kW auxiliary is not a 2,880 kVA load after rectifier power factor (0.955) and transformer efficiency (0.99) are applied.
  • Impedance is a fault-level decision, not a price decision. At 2 × 2,500 kVA, uk 8% gives 39 kA prospective DC fault, uk 6% gives 52 kA and forces 63 kA switchgear, uk 10% gives 31 kA and lets you buy 40 kA switchgear but costs 1.2% more rail voltage drop at peak.
  • Metro transformers are no-load-loss machines. At a 15.6% average load factor the 3.6 kW no-load loss is 89% of total loss; the 30 units on a 25 km line burn 1,061 MWh a year (USD 84,800 at USD 0.08/kWh, USD 1.08 million in 25-year present value) and almost all of it is core loss, not winding loss.
  • Buy the 150% duty test, not the kVA. A rectifier transformer that is only type-tested at rated current tells you nothing about the 145% condition it lives in; require the temperature-rise test at 1.5 × rated current and the short-time 3 × test in the works test schedule.

Why does a metro use a rectifier transformer instead of an ordinary distribution transformer?

A metro transmits at 33 kV (or 10 kV, depending on the city) along the tunnel and converts to 750 V or 1,500 V DC as close to the trains as it can, because DC cannot be transformed and the contact rail can only carry a few thousand amps a short distance. The conversion happens in a traction substation (TSS), and the transformer inside it is a different machine from the distribution transformer on a factory feeder in four ways that change the purchase specification.

First, the secondary is not a single 400 V winding: it is two windings, one star and one delta, each at 1,180 V line-to-line, so that two six-pulse bridges can be fed 30° apart and paralleled into a twelve-pulse output. Second, the load current is not sinusoidal; it is a rectangular, harmonically rich current with a displacement angle close to zero, which means the transformer must be designed for the harmonic loss spectrum rather than for a clean 50 Hz current. Third, the through-fault duty comes from the DC side and is set by the transformer's own impedance, so the impedance is a protection parameter before it is a voltage-regulation parameter. Fourth, and most often missed in tenders, the unit is specified by a duty class — continuous, two-hour overload, one-minute overload — because the load profile is a repeating rectangle, not a smooth industrial curve.

The DC voltage arithmetic that fixes the secondary voltage is simple and worth doing by hand. For a twelve-pulse rectifier the no-load direct voltage is Ud0 = 1.35 × U2, so a 1,180 V secondary produces 1,593 V DC, which is 6.2% above the 1,500 V nominal. That headroom is deliberate: it pays for contact-rail resistance, rectifier regulation and the difference between the nominal and the highest permanent voltage the rolling stock is allowed to see — EN 50163 sets the permanent band for a 1,500 V system at 1,000 V to 1,800 V, and a substation that started from a 1,500 V secondary would drop below the bottom of that band at the far end of its section under peak load.

If your line is 25 kV AC overhead rather than 750/1,500 V DC third rail, this is the wrong article: that machine is a single-phase traction transformer with V/v or Scott connections and a completely different specification, covered in the railway traction transformer guide.

How far apart should traction substations be — and why does 1.6 km win?

The spacing is set by voltage drop in the contact rail, not by transformer size. Take a 65 kg/m steel-aluminium composite third rail at 0.020 Ω/km with the return path through two running rails of 0.010 Ω/km each in parallel, giving 0.025 Ω/km of loop resistance. A train drawing 2,286 A at the midpoint of a section sees the drop in the table below, measured back to the nearest energised substation.

Distance from the feeding substationLoop resistanceVoltage drop at 2,286 ADrop as % of 1,500 VRail voltage the train sees
500 m0.0125 Ω28.6 V1.90%1,471 V
830 m (section midpoint at 1.67 km spacing)0.0208 Ω47.4 V3.16%1,453 V
1,000 m0.0250 Ω57.1 V3.81%1,443 V
1,670 m (a dead section, one substation only)0.0418 Ω95.4 V6.36%1,405 V

Two conclusions come out of that table. A 1.6–1.7 km spacing keeps the worst normal-case drop near 3%, which leaves room for the 5% you will lose in the rectifier, the 2% in the 33 kV cable and the 4–6% the train loses in its own filter and inverter before the motors see anything. And the last row is the reason spacing cannot simply be stretched to save capital: at 3 km the same calculation returns a 11.4% drop, the train derates its own traction to protect the DC link, and the timetable quietly slows down. In dense city centres with 1.5 km station spacing, TSS spacing of 1.5–2.5 km is normal; on lines with long gradients or 30 trains per hour per direction, it drops to 1.0–1.5 km, and the decision is made in the traction power simulation, not in the transformer datasheet.

The capital trade is real: a 33 kV traction substation with two rectifier units, DC switchgear, protection, auxiliaries and civil works is roughly USD 650,000–800,000 installed, so cutting one substation from a 25 km line saves about 3% of the traction power capex and costs 4–5% of line voltage. That is why operators add copper to the contact rail before they add substations, and why the contact-rail cross-section is specified together with the TSS spacing rather than separately.

What does one 6-car train actually demand at the DC bus?

Start from the motors, not from the train's advertised power. A typical 6-car metro unit has four motored cars with four 180 kW asynchronous machines each, and the auxiliaries — compressor, HVAC, lighting, control, battery charger — are a real load that never switches off.

StepValueBasis
Train mass, tare228 t (6 × 38 t)Steel-bodied metro cars, 4 motored + 2 trailer
Train mass, crush loaded315.6 t+1,460 passengers at 60 kg (6 passengers/m²)
Tractive effort at 1.0 m/s², level track320.1 kNInertia 315.6 kN + rolling resistance 2 kg/t
Speed where installed power limits acceleration32.4 km/h2,880 kW ÷ 320.1 kN
0–80 km/h acceleration time31.5 s over 456 mConstant force, then constant power
Kinetic energy at 80 km/h21.6 kWhRecoverable only if another train is braking nearby
Traction power at the motors2,880 kW16 × 180 kW
Auxiliaries180 kWHVAC, compressor, charger, control
At the DC bus3,429 kW÷ 0.92 motor and inverter efficiency, ÷ 0.97 DC line
DC current at 1,500 V2,286 A3,429 kW ÷ 1.5 kV
Transformer apparent power3,627 kVA÷ 0.955 rectifier power factor, ÷ 0.99 efficiency

The gap between 2,880 kW and 3,627 kVA is 26%, and it is the most common source of undersized metro substations. A 2,880 kW train looks comfortable on a 2 × 2,000 kVA substation until the efficiency chain and the rectifier power factor are applied: one train then loads the pair to 181% for the whole acceleration. Two trains in the same section are the design case, because with a 120 s headway each section contains two trains at some point in every cycle, and acceleration lasts 31.5 s of every 120 s — long enough that overlap is routine rather than exceptional.

How do you convert 2,286 A of DC into a transformer kVA?

Work from the rectifier's rated DC current, which is the transformer's kVA divided by the no-load DC voltage. With a 1,593 V Ud0, a 2,500 kVA unit delivers 1,569 A at its continuous rating, and a pair delivers 3,139 A — comfortably above the 2,286 A of one accelerating train, and below the 4,572 A of two trains, which is exactly the 145% condition the duty class exists for.

Unit ratingContinuous DC current per unitPair, continuous150% for 2 h (pair)300% for 60 s (pair)Prospective DC fault at uk 8%
2,000 kVA1,255 A2,511 A3,000 kVA6,000 kVA31.4 kA
2,500 kVA1,569 A3,139 A3,750 kVA7,500 kVA39.2 kA
3,150 kVA1,977 A3,955 A4,725 kVA9,450 kVA49.4 kA

Note what 3,150 kVA does to the switchgear: 49.4 kA prospective fault leaves nothing under a 50 kA/1 s rating, and most metro DC boards are specified at 50 kA. The 3,150 kVA substation is therefore only economical if the operator buys 63 kA switchgear, which typically costs 15–20% more than a 50 kA board — more than the transformer upsizing saves. This is the single most useful sanity check in a metro tender: the DC switchgear rating, not the transformer, decides whether the extra kVA is affordable.

Why is the 150% two-hour rating the number that carries the peak?

Because the instantaneous peak and the thermal duty are two different questions, and metro specifications answer them separately. The 145.1% condition lasts only as long as two trains accelerate together — typically 40–70 s — but the requirement is written as 150% for two hours because the designer cannot prove the overlap never lasts longer, and because the transformer's thermal time constant makes a short overload almost free while a sustained one is not.

Run the RMS over one 120 s peak-hour cycle with two trains, each drawing 3,627 kVA for 31.5 s and roughly 900 kVA (cruise plus auxiliaries) for the remaining 88.5 s. The equivalent thermally active load is 2,846 kVA on a 5,000 kVA installation — 56.9% of nameplate. That is the honest picture: the substation is loaded to 145% for seconds, to 57% on a thermal average, and to 15.6% over the year. The 150% rating is not an emergency provision; it is the normal shape of metro duty, which is why a rectifier transformer specified with a flat 100% rating and no duty class will pass the factory test and then fail its first summer.

Two mechanical details follow. The winding must be designed for the harmonic loss spectrum of a twelve-pulse rectifier, not for sinusoidal loss, because the 11th and 13th harmonic currents add eddy-current loss in the windings and structural heating that a 50 Hz loss test does not reveal; the K-factor logic in the K-factor selection guide is the industrial version of the same problem. And the temperature-rise test must be run at 1.5 × rated current, not at rated current, because that is the condition the specification actually claims.

What happens when one rectifier unit trips?

The line does not stop, but the substation's capability does. With one 2,500 kVA unit out, the surviving unit carries one train at 145.1% — inside the two-hour band — and two trains at 290.2%, which is inside the 300%/60 s band and nothing more. Three mechanisms keep the line running in that state, and a well-written specification names all three rather than pretending the redundancy is electrical.

First, the section is fed from both ends: the contact rail is continuous through the section, so a train between two substations draws from both, and the loss of one unit shifts load to the neighbour. Second, the DC bus tie between the two rectifier groups lets the surviving group feed both halves of the board, at the cost of losing the segregation that limits the fault level. Third, and most honestly, the timetable is the N-1 measure: extending the headway from 120 s to 150 s reduces the number of simultaneous accelerations, which is why metro control rooms have a degraded-mode timetable ready before the transformer is delivered. If the operator instead asks for full N-1 at 120 s headway, the answer is three units of 2,500 kVA or two of 3,150 kVA with 63 kA switchgear — and that decision should be taken with the traction simulation, not with a redundancy slogan. The load-sharing behaviour of paralleled units is covered in the parallel operation guide.

How much DC short-circuit current does a rectifier transformer produce?

For a rectifier, the prospective DC fault current is close to the unit's rated DC current divided by its per-unit impedance — a rule of thumb that follows from the commutating reactance doing the current limiting. At 2,500 kVA and 1,569 A rated, uk 8% gives 19.6 kA per unit and 39.2 kA for the pair, which is why metro DC boards are specified at 50 kA/1 s with margin.

ConfigurationProspective DC faultSwitchgear that fitsConsequence
2 × 2,500 kVA, uk 6%52.3 kA63 kA/1 sBest voltage regulation, most expensive board
2 × 2,500 kVA, uk 8%39.2 kA50 kA/1 sStandard metro solution
2 × 2,500 kVA, uk 10%31.4 kA40 kA/1 sCheaper board, 1.2% more DC drop at peak
2 × 3,150 kVA, uk 8%49.4 kA50 kA/1 s (no margin)More capacity, no fault headroom

Higher impedance is not free either: every point of uk adds to the commutating reactance and therefore to the DC voltage drop under load, which the DC-side calculation above does not include. Going from 8% to 10% costs about 18 V at 2,286 A, or 1.2% of nominal, and that lands directly on the contact-rail voltage budget you spent the spacing calculation on. On the 33 kV side the numbers are much less dramatic — 43.7 A per 2,500 kVA unit, and 8.7 kA of prospective fault from a 500 MVA source — but the AC protection still has to discriminate between a rectifier fault and a downstream DC fault, and the transformer's impedance is the parameter that makes that possible. The calculation method is the same one used for any through-fault study, set out in the short-circuit current guide.

12-pulse or 24-pulse: which pulse number does a metro actually need?

Twelve pulses is the default for a 1,500 V metro, and the decision to go to twenty-four is almost never about the 33 kV voltage distortion — on a stiff 500 MVA source, 9% current THDi on a 5 MVA load produces about 0.1% voltage THD, far inside the 5% that IEEE 519 allows at a point of common coupling below 69 kV. The reasons that actually drive the choice are the DC ripple frequency, the track-circuit and telecom interference study, and utility practice on dedicated feeders.

ConfigurationCharacteristic harmonicsCurrent THDi at transformer primaryRipple frequency at 50 HzHardwareCost premium
6-pulse (one bridge)5th, 7th, 11th, 13th25–30%300 HzOne secondary windingBaseline
12-pulse (Y + Δ secondaries)11th, 13th, 23rd, 25th8–10%600 HzTwo windings, one transformer+8% on the transformer
24-pulse (two units, 15° shifted)23rd, 25th4–5%1,200 HzTwo transformers with phase-shifted secondaries+15–18%

The 300 Hz and 600 Hz components are the ones that couple into audio-frequency track circuits and into tunnel telecoms, and that study — not the harmonic limit at the point of common coupling — is where a 24-pulse requirement usually originates. If your line is being specified for the first time, the defensible position is 12-pulse per unit, with the transformer's secondaries ordered so that a future 15° phase shift between two units is possible; that keeps the 24-pulse option open without paying for it in every substation. The general harmonic mechanisms and mitigation options are in the transformer harmonics guide.

How hot is a tunnel traction substation, and what does that cost in kVA?

Tunnel plant rooms run hotter than designers expect. Piston effect from train movement pushes 35–40 °C air through the tunnel in summer, and a louvred equipment room with the rectifier losses inside sits 5–10 K above tunnel air unless it is mechanically ventilated. A cast-resin transformer's AN rating is quoted at 40 °C ambient, and the standard derating is 1% of nameplate per kelvin above 40 °C — the same rule that governs outdoor units, described with worked examples in the temperature derating guide.

Room air temperatureAN derating factorEffective rating of 2 × 2,500 kVATwo-train demand of 7,254 kVA is
40 °C (design basis)1.005,000 kVA145.1% — inside the 150% band
45 °C0.954,750 kVA152.7% — outside the 150% band
50 °C0.904,500 kVA161.2% — outside the 150% band

Five kelvin of unmanaged room temperature is enough to move a compliant design into non-compliance, which is why the ventilation of a tunnel TSS belongs in the transformer specification and not in the civil package. Forced-air cooling (AF) recovers 25–30% of the rating at the cost of fans, controls and — in a tunnel — filters that clog with brake and wheel dust within weeks. On a line with 30 trains per hour, specify AN/AF with the AF stage as a summer peaking facility and put the filter differential-pressure alarm on the SCADA, or accept 3,150 kVA units and buy the 63 kA board. The cooling-class logic is the same as for any other unit, set out in the cooling methods and temperature rise guide.

Why do 89% of a metro transformer's losses happen at no load?

Because the transformer is sized for a peak that occurs for a few percent of the time and then lives at a fraction of its rating. A 25 km line with 14 trains per hour per direction over 20 hours, 20 kWh per train-km and 5.11 million train-km a year consumes about 102 GWh of traction energy — and spread over 30 transformer units that is a 15.6% average load factor per unit.

Operating pointLoad factorLoss per unit (3.6 kW NL + 18 kW LL)Line total, 30 unitsHours per year
Annual average15.6%4.04 kW121 kW8,760
Off-peak service30%5.22 kW157 kW~5,000
Peak service, RMS56.9%9.43 kW283 kW~2,500
Two trains accelerating145%41.4 kW1,243 kW<400

At the annual average, no-load loss is 89% of the total. The 30 units therefore burn about 1,061 MWh a year, or USD 84,800 at USD 0.08/kWh — USD 1.08 million in 25-year present value at 6%. That number is five times the annual energy bill an industrial plant of the same installed kVA would show, because the industrial plant would run at 60% load where load loss dominates. The inversion matters for procurement: in metro duty you are buying core loss, and the load-loss figure on the datasheet is almost decorative.

The economics still have to be run honestly. Take a low-loss variant with 40% lower no-load loss (3.6 kW down to 2.16 kW) and 10% lower load loss, at a 15% capital premium on 30 units — USD 427,500 on a USD 2.85 million transformer package. The saving is 44.5 kW, worth USD 31,200 a year, or USD 399,000 in 25-year present value at 6%. The premium does not pay back at USD 0.08/kWh; the break-even tariff is USD 0.086/kWh. At a USD 0.10–0.12/kWh tariff, or with a premium negotiated down to 10%, the same variant clears comfortably. This is the calculation to put in front of the operator's energy manager, and it is the same total-cost logic used in the TCO guide.

Cast resin or oil-immersed for a metro traction substation?

Inside a tunnel or an underground station box, the answer is cast resin almost without exception — not because it is more efficient, but because it removes the oil and therefore the fire load, the bund, the oil-containment civil works and the deluge question from a space that has no room for any of them. Trackside and elevated substations are a different commercial case.

CriterionCast-resin dry-typeOil-immersed
Fire loadNone; self-extinguishing Class F insulation1,000–1,500 L of mineral oil per 2,500 kVA
Tunnel and station boxStandard choiceGenerally excluded by the fire strategy (NFPA 130 for stations and tunnels)
Weight, 2,500 kVA~7.5 t~9.5 t including oil
FootprintLarger, needs 800–1,000 mm clearancesCompact, but needs bunding and blast containment
Overload capabilityGood short-time, short thermal time constantBetter sustained overload, longer time constant
Humidity and pollutionRequires clean, dry room air; IP 31–IP 41 enclosureTolerant
Price, 33/1.18 kV, 2,500 kVA, FOB ChinaUSD 85,000–110,000USD 62,000–78,000
MaintenanceDust removal, partial-discharge monitoringOil tests, DGA, tap-changer servicing

The price gap of 25–35% is real and it is why trackside substations on elevated viaducts are often oil-immersed inside a kiosk, while tunnel and station-box substations are cast resin. The comparison principles are the same as for any industrial plant and are set out in the oil-immersed versus dry-type guide; for metro the fire strategy decides first and the price decides second. If you do buy dry-type, specify the insulation class and the permissible temperature rise together, because the 10 K rule that halves insulation life applies to cast resin exactly as it does to paper — the insulation class guide has the arithmetic.

What does stray current have to do with the transformer specification?

The transformer does not carry traction current to earth, but the way its secondary is earthed decides how much current escapes. A 1,500 V metro returns current through the running rails, and 1–2% of the traction current leaks into the ground through rail-to-earth resistance, drainage bonds and structures — 23–46 A per substation at 2,286 A of traction current, which is enough to corrode a buried pipe or a tunnel lining reinforcement over a decade.

EN 50122-2 governs the provisions against stray currents, and the design consequence for the transformer is concrete: the rectifier's DC negative is left unearthed in normal operation, the earthing of the transformer's secondary and of the DC switchgear frame is separated from the running-rail return, and the AC and DC earthing systems are tied only at the points the stray-current study permits. On the transformer itself, an electrostatic shield between the HV and LV windings is worth specifying: it keeps the 300 and 600 Hz rectifier ripple out of the 33 kV network, which protects the utility's own protection and metering. The general earthing principles are in the grounding system design guide, though for a traction system the stray-current study, not the LV earthing table, is the governing document.

What belongs in a metro rectifier transformer specification?

The specification below is the short list that separates a unit that survives 30 years of metro duty from one that survives the factory test. It is written for a 1,500 V DC, 33 kV line with 2 × 2,500 kVA substations and should be re-run for 750 V light rail, where the unit is 1,250–2,000 kVA and the DC current is twice as high for the same power.

  1. Rating and duty class: 2,500 kVA, 100% continuous, 150% for 2 h, 300% for 60 s, with the load profile and the daily cycle attached as an annex.
  2. Voltages: 33 kV ±2 × 2.5% on-load or off-circuit tapping, two secondaries at 1,180 V (one star, one delta), Ud0 = 1,593 V.
  3. Vector group: Dyn11d0 or Dd0y11, with the 30° shift between secondaries stated on the nameplate — not left to the rectifier supplier to discover.
  4. Impedance: 8% ±7.5% tolerance at rated current, with the guaranteed value stated because it sets both the 39 kA DC fault and the DC voltage drop.
  5. Harmonic design: winding and core designed for the 11th and 13th harmonic spectrum of a twelve-pulse rectifier; harmonic loss factor stated in the loss calculation.
  6. Insulation: Class F insulation, 100 K average winding rise for AN, partial discharge ≤ 10 pC at 1.5 Um, impulse level per the 33 kV system BIL (typically 170 kV).
  7. Cooling: AN/AN or AN/AF with the AF stage rated for the site ambient; filters with differential-pressure alarm if AF is used in a tunnel.
  8. Temperature rise test: witness at 1.5 × rated current for the duty class, not at rated current only — this is the test that proves the 150% claim.
  9. Short-circuit: through-fault withstand per IEC 60076-5 for the duty class, including the 300% one-minute condition.
  10. Enclosure: IP 31 minimum, IP 41 for dusty tunnel environments, with the enclosure rated for the same duty as the transformer and not as an afterthought.
  11. Materials: low-smoke zero-halogen where the operator applies EN 45545-2 hazard level 3 to fixed equipment; otherwise state the fire performance of the cast resin system explicitly.
  12. Earthing: electrostatic shield between HV and LV, separate earthing terminals for core, frame and tank, and a documented interface to the stray-current protection.
  13. Sound: guaranteed sound power level at 1.5 × rated current, and the test method, because tunnel plant rooms have hard surfaces and no absorptive treatment.
  14. Tests: routine tests, type tests including the temperature-rise and short-circuit duty, and a pre-shipment inspection witnessed by the operator and the traction system integrator — the checklist in the pre-shipment inspection guide covers the witness points.
  15. Documentation: loss calculation at 25%, 50%, 100% and 150% load, harmonic loss factor, and the DC-side data the rectifier supplier needs to confirm the fault level.

Commissioning is the other half of the same argument. A rectifier transformer arrives with two secondaries whose phase relationship is the whole basis of the twelve-pulse design, so the turns-ratio and vector-group checks at site are not a formality: a reversed secondary connection produces a six-pulse system with a circulating current in the DC bus that will destroy a rectifier within hours. The pre-energisation sequence for that is in the commissioning tests checklist, and a first-energisation procedure written for a distribution transformer should not be copied onto a traction substation without adding the DC-side checks.

Which mistakes break a metro transformer tender?

Six failures that repeat across metro projects in the Gulf, Southeast Asia, India and Latin America, and the specification line that prevents each one.

  • Buying kVA without the efficiency chain. A 2,880 kW train becomes 3,627 kVA at the transformer. Tendering 2 × 2,000 kVA because "one train is only 2.9 MW" leaves the second train at 181% of a pair — outside the duty class before the line opens.
  • No duty class on the datasheet. A 100% continuous rating with no 150%/2 h and 300%/60 s figures cannot be assessed, and the cheapest bid will always omit it. Require the three numbers as a table and make them a technical compliance item.
  • Impedance chosen by the transformer supplier. uk 6% looks like better voltage regulation until the 52 kA DC fault forces 63 kA switchgear across every substation on the line. Fix uk in the specification and let the supplier price it.
  • Room temperature left to the civil package. Five kelvin above 40 °C moves two 2,500 kVA units from 145.1% to 152.7% at the design peak. Write the design room temperature into the transformer specification and make the ventilation a matching interface.
  • Optimising load loss instead of no-load loss. At a 15.6% average load factor, 89% of the loss bill is core loss. Tenders are usually written around load loss because that is what industrial buyers compare — for metro it is the wrong half of the loss pair.
  • Copying a distribution-transformer FAT and commissioning plan. Without a temperature-rise test at 1.5 × rated current and a secondary phase-relationship check at site, the two tests that matter most for a twelve-pulse system are simply absent.

How do you check the numbers before you issue the enquiry?

Run the chain in the order this article uses it: train traction power, auxiliaries, DC bus power, DC current, apparent power, then kVA. If your line is 750 V light rail rather than 1,500 V metro, the same chain applies but the DC current doubles for the same power, the substation is 1,250–2,000 kVA at 0.5–1 km spacing, and the contact-rail drop becomes the dominant constraint. If it is a 25 kV AC line, none of this applies and the AC traction article is the right starting point.

The two checks that catch most errors are cheap. Divide your transformer kVA by 1,593 V and compare the result with 1.5 × the train's DC current: it should be comfortably above one train and slightly below two. Then divide your pair's kVA by uk and confirm the number lands under your DC switchgear rating with margin. For the sizing arithmetic itself, the power system calculators cover the kVA, fault-level and loss steps, and the sizing and budget formula puts a price band beside them. For readers coming from the industrial side of the same problem, the rectifier duties of an aluminium smelter rectiformer and a chlor-alkali plant are worth comparing with metro duty: same conversion principle, very different load shape.

Sources / 资料来源

Source: IEC 60076-1 — Power transformers, Part 1: General.
Source: IEC 60076-2 — Power transformers, Part 2: Temperature rise for liquid-immersed transformers.
Source: IEC 60076-5 — Power transformers, Part 5: Ability to withstand short circuit.
Source: IEC 60076-11 — Power transformers, Part 11: Dry-type transformers.
Source: IEC 60146-1-1 — Semiconductor converters, Part 1-1: General requirements and line commutated converters.
Source: EN 50329 — Railway applications, fixed installations, traction transformers.
Source: EN 50163 — Railway applications, supply voltages of traction systems.
Source: EN 50122-1 — Railway applications, protective provisions relating to electrical safety and earthing.
Source: EN 50122-2 — Railway applications, provisions against the effects of stray currents caused by DC traction supply systems.
Source: EN 45545-2 — Railway applications, fire protection on railway vehicles, requirements for fire behaviour of materials and components.
Source: NFPA 130 — Standard for fixed guideway transit and passenger rail systems.
Source: IEEE 1653 series — DC traction power systems.
Source: IEEE 519-2022 — Harmonic control in electrical power systems.
Source: IEC 62236-2 — Railway applications, electromagnetic compatibility, emission of the whole railway system to the outside world.
Source: Industry experience — 6-car metro train traction and auxiliary power, 16 × 180 kW, 228 t tare, 31.5 s to 80 km/h, 2018–2026.
Source: Industry experience — contact-rail loop resistance of 0.020–0.025 Ω/km for 65 kg/m composite third rail with twin running-rail return, 2018–2026.
Source: Industry experience — 12-pulse current THDi of 8–10% and 6-pulse of 25–30% at the transformer primary, 2018–2026.
Source: Industry experience — 1% nameplate derating per kelvin above 40 °C ambient for AN dry-type units, and 5–10 K room rise in louvred tunnel plant rooms, 2018–2026.
Source: Industry experience — 2026 FOB China price bands for 33/1.18 kV cast-resin rectifier transformers of USD 85,000–110,000 per 2,500 kVA, and installed 33 kV traction substation cost of USD 650,000–800,000, 2025–2026.
Source: QDTB Engineering Team — 33 kV, 1,500 V DC and 750 V DC traction substation designs for metro and light rail projects in the Gulf, Southeast Asia and Latin America, 2021–2026.