QDTB® Transformer
All figures are configurator-generated feasibility-level estimates; drawings are schematic deliverables pending refinement by a licensed design institute, not construction documents.
All Solutions

2000 kW Source-Grid-Load-Storage Microgrid: PV 1000 kWp + BESS 800 kW/1742 kWh + Auto-Transfer Deep-Read

PV 1000 kWp · BESS 800 kW/1742 kWh · Diesel 600 kW standby · 2×SCB13-2000/10 N+1 · on/off-grid

1 · TL;DR Conclusion

Conclusion: this 2000 kW source-grid-load-storage microgrid combines 1000 kWp PV + 800 kW/1742 kWh BESS + 600 kW diesel auto-transfer + a 10 kV grid feed with grid-tied/islanding, on 2×SCB13-2000/10 transformers (N+1) plus a grade-1 end-transfer switch (GATS) — configurator total ≈ $914,457, EPC ≈ $990,000, 4-yr payback, 24.80% IRR, 609.1 t CO2/yr avoided (feasibility-level).

  • •Multi-source mix: 1000 kWp PV (63% share) + 800 kW BESS (38%) + 600 kW diesel auto-transfer, 4400 kW installed
  • •Grid-tied/islanding + black-start (600 kW diesel auto-start, verified); 2 s auto-transfer
  • •Grade-1 800 kW end-transfer switch (GATS-630) + 300 kW EPS, 175% backup coverage
  • •PV self-use ≈$261,482/yr (incl. BESS shaving)
  • •Economics: $990,000 EPC, 4-yr payback, 24.80% IRR, LCOE $0.1011/kWh, 609.1 t CO2/yr avoided

2 · Solution Overview

A source-grid-load-storage microgrid unifies sources (PV/diesel/grid), the network, loads and storage under one EMS — the archetypal architecture for zero-carbon industrial parks and large campuses. This 2000 kW design has PV for base load, BESS for smoothing+shaving+demand, diesel for auto-transfer backup, the grid as the main tied supply, and a grade-1 end-transfer switch keeping critical production lines powered.

2×2000 kVA (SCB13-2000/10)
Transformer
1000 kWp
PV
800 kW / 1742 kWh
BESS
600 kW standby · auto-transfer
Diesel
10 kV
Grid
Grid-tie/island + black-start + auto-transfer
Mode
800 kW (end GATS transfer)
Grade-1 load
Pass (2×2000 kVA)
N-1
SourceRoleShare kWShare
Grid 10 kVbase0 kW0%
Solar PV 1000 kWpvariable1000 kW63%
BESS 800 kW / 1600 kWhvariable600 kW38%
Diesel 600 kWbackup0 kW0%

3 · Design Process & Rationale

1. Requirement identification

A zero-carbon industrial park wants both high renewable share and uninterrupted critical production (800 kW grade-1 load). Two hard requirements are locked first: source-grid-load-storage dispatch and reliable auto-transfer — mandating BESS, diesel and end ATS.

2. Load grading

2000 kW total → 1742 kW demand; 800 kW grade-1, 800 kW grade-2, 200 kW sensitive. Grade-1 needs an end transfer switch (GATS-630) + EPS; grade-2 is covered by grid+BESS.

3. Source mix

1000 kWp PV (63%) + 800 kW/1742 kWh BESS (38%, 2 h) + 600 kW diesel standby (auto-transfer) + 10 kV grid, dispatched by one EMS.

4. Transformer sizing

1742 kW → 1684 kVA → 2000 kVA tier + N+1 (2 dry-type units, indoor park). 84% loading after one trip (N-1 pass); grade-1 load transfers to the other source via end ATS.

5. Auto-transfer & switching

Grade-1 end GATS-630 auto-transfer: on grid loss it switches to diesel/BESS within 2 s; gridMode=grid-tie-island + blackStart=yes, 600 kW diesel black-starts, 175% backup coverage.

6. Distribution & protection

MV incomer → 2 dry-type transformers → MNS LV switchgear (with bus-tie) → feeders + grade-1 end ATS. LV fault 58.91 kA vs 80 kA breaking; selectivity 24.56×, grading satisfied.

7. Power quality

200 kW sensitive load + harmonics (THDi 20%) get reactive compensation + detuned reactors; storage/diesel converters coordinated to avoid circulating current.

8. Economics

BESS shaves 800 kW×4 h saving ≈$151,840/yr; PV generates 1,015,200 kWh/yr. Overall 4-yr payback, 24.80% IRR, LCOE $0.1011/kWh, 609.1 t CO2/yr avoided.

Pain Points → Solution → Evidence

Pain

Critical production (800 kW grade-1) cannot drop for a second

Solution

End auto-transfer GATS-630 + 300 kW EPS: switch to diesel/BESS within 2 s

Evidence

N-1 pass (2×2000 kVA) + 175% backup coverage + GATS/EPS in BOM

Pain

High renewable share causes grid fluctuation and hard peak regulation

Solution

800 kW/1742 kWh BESS smoothing + shaving + demand, EMS source-grid-load-storage coordination

Evidence

economic.shaving: 800 kW×4 h, $151,840/yr saved

Pain

Pure-diesel backup costs $327k/yr — unsustainable

Solution

PV+BESS first, diesel only for auto-transfer emergencies

Evidence

Pure diesel $327,040 vs hybrid $232,400; ≈$151,840/yr saved

Pain

When does it pay back?

Solution

≈$990,000 EPC; PV+BESS save ≈$261,482/yr

Evidence

economic: 4-yr payback, 24.80% IRR, 497% 25-yr ROI

4 · Key Parameter Deep-Read

ParameterValueBasisImpact & Boundary
Transformer capacity2×2000 kVA (N+1 dry-type)1742 kW → 1684 kVA → 2000 kVA tier + one spare84% loading; stays 84% after a trip (N-1 pass)
Step to 2500 kVA for growth
PV capacity1000 kWp63% share; 1,015,200 kWh/yr generationServes base load by day, cutting diesel run and bills
Limited by site area and BESS absorption
BESS capacity800 kW / 1742 kWh (2 h)Smoothing + shaving + demand, 2 h durationShaves 800 kW×4 h, saving $151,840/yr
Long islanding needs ≥8 h plus a black-start check
Diesel capacity600 kW standby · auto-transferEmergency auto-transfer + black-start (600 kW verified)The only emergency source for grade-1 end transfer
standby = emergency-rated, cheaper than prime
Auto-transferGATS-630 end transfer, 2 s800 kW grade-1 load must be uninterruptedTransfers within 2 s; 175% backup coverage
Transfer time vs load criticality per IEC 60364
Grid modegrid-tie-island + black-startZero-carbon parks must island and black-startAnti-islanding prevents backfeed; 2 s ATS
Grid approval per local grid code (gridCodeNote)
EconomicsIRR 24.80% · 4 yr$990,000 EPC + $261,482/yr saving + 25-yr cashflowThe core investability metric
Tariff, irradiation and load factor are the key sensitivities

5 · Drawing Deep-Read

Dwg 3/31Single-line diagram — 10 kV grid + 1000 kWp PV + 800 kW/1742 kWh BESS + 600 kW diesel → 2×2000 kVA dry-type → LV bus + grade-1 end ATS
Why: The SLD shows the four elements plus end auto-transfer: four sources converge on the bus, grade-1 load connects dual supplies via GATS end transfer — the physical locus of source-grid-load-storage and auto-transfer design.
Dwg 20/31Grid-tied / islanding transfer — PCC · ATS 2 s · anti-islanding 81U/81O+32R · auto-transfer logic
Why: This is the soul of the scheme: grid loss → auto-transfer in 2 s → diesel black-start → grade-1 load stays up. The transfer chain (IEC 62898 / IEEE 1547) structurally dissolves the 'critical line can't drop a second' pain.
Dwg 4/31System topology — Source (grid/PV/diesel) · network · load · storage → transformer → load
Why: The topology lays out the energy hierarchy of the four elements: four sources → MV bus → 2 dry-type transformers → LV bus → load, making the EMS dispatch visible — PV-first when tied, diesel+BESS backup when islanded.
Dwg 14/31Protection configuration — 50/51 overcurrent + auto-transfer interlock · 24.56× selectivity
Why: This places settings for the grid incomer, transformers, feeders and the grade-1 end ATS; the auto-transfer interlock prevents accidental dual-source paralleling — the safety precondition for reliable transfer.
Dwg 28/31Peak-shaving operation profile — 24h profile · PV daytime / BESS peak-valley / diesel auto-transfer
Why: This turns source-grid-load-storage coordination into a 24h timeline: daytime PV serves base, peak-time BESS discharge shaves the peak, overnight valley charging — showing the shaved demand and saved bill ($151,840/yr).

The following drawings are shown for reference (full set in the configurator “View design document”):

Dwg 1 · Electrical design basisDwg 5 · Distribution systemDwg 8 · Short-circuit calculationDwg 15 · TCC coordination curveDwg 19 · Reactive & harmonic compensationDwg 16 · Grounding systemDwg 17 · Lightning & surge protectionDwg 24 · DC auxiliary powerDwg 25 · Fuel oil systemDwg 29 · BMS communicationDwg 30 · Fire & thermal zoningDwg 31 · EMS state machineDwg 13 · SCADA architectureDwg 9 · Applicable standards

6 · Operation Demo (Deep-Read)

Energy flow

Grid-tied: PV 1000 kW serves base first, surplus charges BESS; BESS discharges 800 kW at peak and charges at valley; grid fills the gap. On grid loss: auto-transfer switches to diesel/BESS in 2 s, grade-1 load stays up.

Grid failure / auto-transfer

Press 'Grid failure': the grade-1 end GATS transfers to 600 kW diesel black-start + BESS within 2 s (175% backup coverage); in the N-1 case one transformer trips and the other continues at 84% loading.

Economics

1,015,200 kWh/yr generated, 0.8 self-use + surplus export; PV self-use ≈$261,482/yr (incl. BESS shaving); $990,000 invested, 4-yr payback, 24.80% IRR, LCOE $0.1011/kWh.

24h operation

A typical-day curve: daytime PV overlaps load, peak-time BESS discharge shaves the peak, overnight valley charging, diesel only during auto-transfer/black-start — source-grid-load-storage coordination in time order.

Other views (shown): Power quality & harmonics · Voltage profile · Scheme features · Environmental derating

7 · Economics & Payback

Equipment total ≈ $914,457, EPC ≈ $990,000 (incl. PV/BESS/diesel/auto-transfer/distribution/installation). PV self-use saves ≈$261,482/yr (incl. BESS shaving); overall 4-yr payback, 24.80% IRR, 497% 25-yr ROI, LCOE $0.1011/kWh, NPV $1,584,295, 609.1 t CO2 avoided/yr.

$990,000
EPC investment
4 yr
Payback
24.80%
IRR
497%
25-yr ROI
$0.1011/kWh
LCOE
609.1 t/yr
CO2 avoided
Key assumptions driving these numbers
$0.12/kWh
Electricity price
$0.06/kWh
Feed-in tariff
1015200 kWh
Annual generation (P50)
80%
Self-consumption
$0.13/kWh
Peak-valley spread

8 · FAQ

How do you understand source-grid-load-storage integration?
It unifies sources (PV/diesel/grid), the network, loads and storage under one EMS: PV serves base, BESS smooths+shaves, diesel handles auto-transfer, grid is the main tied supply.
What is auto-transfer and how fast?
A grade-1 end GATS-630 transfers within 2 s of grid loss to diesel/BESS, keeping critical production powered, with 175% backup coverage.
How big a BESS?
800 kW / 1742 kWh = 2 h, for smoothing, shaving and demand management; 800 kW×4 h shaving saves ≈$151,840/yr.
How is black-start implemented?
Grid loss → auto-transfer in 2 s → 600 kW diesel auto-starts for black-start (verified) → grade-1 load stays up.
When does it pay back?
≈$990,000 EPC; PV self-use + BESS shaving save ≈$261,482/yr; ~4-yr payback, 24.80% IRR.
Pure diesel vs source-grid-load-storage hybrid?
Pure diesel ≈$327,040/yr vs hybrid ≈$232,400/yr — about $151,840/yr saved (800 kW×4 h shaving basis).
How is the 800 kW grade-1 load kept uninterrupted?
End GATS-630 auto-transfer + 300 kW EPS + 2×2000 kVA N+1 transformers, 84% loading after a trip (N-1 pass).
How much PV should be installed?
This scheme uses 1000 kWp (63% share) for 1,015,200 kWh/yr. More PV needs more storage to absorb, else curtailment or backfeed.
Could auto-transfer accidentally parallel two sources?
No — the auto-transfer interlock prevents accidental paralleling; selectivity 24.56× with grading satisfied, and a full transfer test is required before commissioning.
What grid-connection paperwork is needed?
Grid approval + anti-islanding/anti-backfeed/PF (gridCodeNote); the on/off-grid and auto-transfer schemes must be approved per the local grid code.

Special Considerations

  • Grade-1 800 kW end auto-transfer (GATS-630) + 300 kW EPS are included; transfer time vs load criticality must be confirmed per IEC 60364 by the design institute.
  • The auto-transfer interlock prevents accidental dual-source paralleling; selectivity 24.56×, grading satisfied; a full transfer test is required before commissioning.
  • 2 h storage covers shaving/demand; long islanding needs ≥8 h plus a black-start capacity check.
  • 200 kW sensitive load + THDi 20% have reactive compensation + detuned reactors; add APF if limits are exceeded.
  • Feasibility-level estimate; drawings pending refinement by a licensed design institute.

Turn this into your project

Open this exact scenario pre-loaded in the Power System Configurator, then generate the full design document or the operation & techno-economic assessment.

Open in Power System Configurator →

One-Stop Supply of Conventional & Solar Power Equipment

From power distribution system design to solar energy — transformers, switchgear, substations and solar equipment, sized and quoted in one place. Use our calculators to get a complete bill of materials and FOB price.