QDTB® Transformer
All figures are configurator-generated feasibility-level estimates; drawings are schematic deliverables pending refinement by a licensed design institute, not construction documents.
All Solutions

250 kW Office Building Power: 380 V LV Distribution + 80 kVA UPS + 80 kW Diesel Backup Deep-Read

380 V LV switchgear · 80 kVA online UPS (30 min) · 80 kW standby diesel · fire end-transfer ATS

1 · TL;DR Conclusion

Conclusion: this 250 kW office building uses 380 V LV distribution + an 80 kVA online UPS (30 min) for the 60 kW IT-room critical load + an 80 kW standby diesel for extended/fire backup — configurator total ≈ $102,229, 200 kW effective demand, selectivity pass, 25 kA breaking (3.1× margin), feasibility-level.

  • •380 V LV direct feed (no MV transformer): 250 kW installed → 200 kW demand (0.8 diversity), stdKva 211
  • •80 kVA (64 kW) online UPS, 30 min ≈ 39.8 kWh battery (384 VDC) — covers the 60 kW IT critical load at 107%
  • •80 kW standby diesel (1×500 kVA 20-ft container, 3-day fuel) — critical + fire loads, compliance C3 pass
  • •Fire load 30 kW on a dedicated circuit with end-transfer ATS (auto-added); selectivity 50/51 pass (Δt 0.5 s)
  • •Equipment total $102,229; LV fault 8 kA → 25 kA breaking (3.1× margin); 37 kW motor soft-start dip ≤10%

2 · Solution Overview

An office building is a grade-2 commercial load where the real risk is the tenant IT room: servers and network gear tolerate no outage. This scheme uses 380 V LV distribution (no MV transformer) plus two-layer backup — an online UPS for millisecond continuity and a standby diesel for extended outage — with the fire load on a dedicated end-transfer circuit.

None (380 V LV direct feed)
Transformer
380 V LV (0.38 kV)
Feed
200 kW (250 kW installed)
Demand
80 kVA (64 kW, 30 min)
UPS
80 kW standby (500 kVA unit)
Diesel
60 kW (IT room)
Critical load
30 kW (dedicated + ATS)
Fire load
160 kW (UPS + diesel)
Backup total
SourceRoleShare kWShare
Grid 0.38 kVbase200 kW100%
Diesel 80 kWbackup0 kW0%
UPS 80 kVAbackup0 kW0%

3 · Design Process & Rationale

1. Requirement identification

250 kW office building: tenant power 150 kW, lighting 60 kW, sensitive 60 kW (IT), fire 30 kW. Largest motor 37 kW (HVAC/lift), soft start.

2. Load & grading

Whole building grade-2 (loadGrade2=250); IT room 60 kW classified critical (no outage); fire 30 kW dedicated (fireDedicated=yes).

3. Source mix

380 V grid (base) + online UPS (critical IT) + standby diesel (extended + fire). LV direct feed, no MV transformer.

4. UPS sizing

60 kW critical → 80 kVA (64 kW) online double-conversion, 30 min battery (39.8 kWh, 384 VDC), 107% coverage.

5. Diesel sizing

80 kW standby duty; the configurator selects 1×500 kVA 20-ft container (standard min unit, ~20% load, 3-day fuel).

6. Protection

LV 25 kA breaking (8 kA fault, 3.1× margin); 50/51 selectivity Δt 0.5 s pass; fire end-transfer ATS auto-added.

7. Secondary & starting

Modbus + multifunction meters + local HMI; 37 kW motor soft-start keeps bus dip ≤10%.

Pain Points → Solution → Evidence

Pain

The tenant IT room can't tolerate a second of outage

Solution

Online UPS 80 kVA + static switch, diesel for extended outage

Evidence

UPS 30 min 39.8 kWh; diesel 3-day fuel; compliance C3 pass

Pain

Fire pumps and emergency lighting must run during a fire

Solution

Dedicated fire circuit + end-transfer ATS (auto-added)

Evidence

V11 pass; fire 30 kW dedicated

Pain

Multiple sources complicate switching

Solution

EMS + ATS/STS automatic transfer (hybrid CR-01)

Evidence

EMS $4,025 + STS $4,370 auto-added

Pain

Voltage drop and motor-start dips on LV

Solution

37 kW soft start + 185 mm² main cable

Evidence

V1 pass (≤5%); V5 dip ≤10%

4 · Key Parameter Deep-Read

ParameterValueBasisImpact & Boundary
UPS capacity80 kVA (64 kW)Covers 60 kW critical IT at 107%30 min ≈ 39.8 kWh (384 VDC)
Add a second unit for N+1 tolerance
Diesel genset500 kVA (80 kW standby)Standard 20-ft container min unit3-day fuel, ~20% load
500 kVA is oversized for 80 kW — verify a smaller unit
Demand200 kW (250 kW×0.8)Diversity factor kd=0.8stdKva 211
Higher kd → larger cable/gear
LV breaking25 kALV fault ikLv 8 kA3.1× margin
Confirm grid Ssc with the utility
UPS battery30 min / 39.8 kWhbackupTime=30384 VDC 8×48V blocks
Extend runtime → more Ah
Fire circuit30 kW dedicatedfireDedicated=yesEnd-transfer ATS auto-added
Confirm fire pump motor rating
Motor start37 kW soft startLargest motor 37 kWBus dip ≤10%
DOL would exceed the limit

5 · Drawing Deep-Read

Dwg 3/25Single-line diagram — 380 V grid → LV incoming/feeder panels → IT (80 kVA UPS) · fire (end ATS) · diesel
Why: The SLD shows the two-layer backup skeleton: grid base, UPS for millisecond IT takeover, diesel end-transfer for fire — the structural source of 'no second of outage'.
Dwg 4/25System topology — Grid · UPS · diesel → 380 V bus → power/lighting/IT/fire
Why: The topology visualizes the three-source hierarchy — grid (base), UPS (critical IT), diesel (fire + extended) — with EMS/ATS transfer, the energy-management landing point for reliable office power.
Dwg 13/25Protection configuration — 50/51 overcurrent + Δt 0.5 s selectivity + fire end-transfer
Why: Protection is the second line of defense against site-wide trips: multi-stage overcurrent grading + end-transfer means a downstream fault trips only its feeder and fire circuits can transfer to diesel.
Dwg 14/25TCC protection coordination curve — Incoming → feeder Δt 0.5 s, current ratio 10.02×, selectivity pass
Why: The TCC verifies selectivity: a downstream fault trips only its feeder (0.1 s) while the upstream holds (0.6 s); the 10× current ratio keeps the grading valid.
Dwg 23/25DC auxiliary power — DC auxiliary power · protection still trips on AC loss
Why: DC auxiliary power is the last-mile reliability guarantee: on AC loss the DC panel still powers relays and trip coils, so fault clearing never depends on AC.

The following drawings are shown for reference (full set in the configurator “View design document”):

Dwg 18 · Reactive & harmonic compensationDwg 11 · Power quality assessmentDwg 7 · Short-circuit calculationDwg 15 · Grounding systemDwg 16 · Lightning & surge protectionDwg 17 · Equipment layout planDwg 20 · Secondary control & signalDwg 9 · Main equipment technical data

6 · Operation Demo (Deep-Read)

Reliability & backup

Shows grid loss → UPS millisecond takeover of IT → diesel start for fire/extended load; UPS 30 min covers critical IT, diesel 3-day fuel as backstop.

Fault & protection

A downstream fault trips only its feeder (Δt 0.5 s selectivity); fire circuits end-transfer to diesel — no site-wide blackout.

Energy flow

Grid 200 kW feeds power/lighting, UPS online double-conversion carries critical IT, diesel 80 kW standby — three-source status at a glance.

Economics

Equipment total $102,229 (LV panels + 80 kVA UPS + 500 kVA diesel + cables + secondary); no renewables so no payback/IRR — the value is reliability.

Other views (shown): LCC (life-cycle cost) · Voltage profile · Power quality · Scheme features

7 · Economics & Payback

Equipment total ≈ $102,229 (380 V LV switchgear + 80 kVA UPS + 500 kVA diesel container + cables + secondary, feasibility-level). With no renewable generation there is no payback/IRR — the value is reliability: the UPS carries the 60 kW IT load for 30 min and the diesel extends it to 3 days while backing the fire pumps. Adding rooftop PV would unlock a 6–12 yr payback path.

$102,229
Equipment total
30 min
UPS backup
3 days
Diesel autonomy
160 kW
Backup total
60 kW
Critical IT

8 · FAQ

What transformer size for a 250 kW office building?
None — this is a 380 V LV direct feed. 250 kW installed → 200 kW demand (0.8 diversity), stdKva 211, served directly from LV switchgear without an MV transformer.
How big a UPS for the IT room?
80 kVA (64 kW) online double-conversion, 30 min ≈ 39.8 kWh at 384 VDC, covering the 60 kW IT critical load at 107%.
Do I need a diesel genset?
Yes for critical/fire backup — the configurator flags C3 (critical load without emergency source) and adds an 80 kW standby diesel (1×500 kVA 20-ft container, 3-day fuel).
How is the fire load handled?
30 kW on a dedicated circuit with an end-transfer ATS (auto-added when fireDedicated=yes), so fire pumps transfer to diesel on mains loss.
What's the short-circuit / breaking capacity?
LV fault 8 kA → 25 kA breaking gear (3.1× margin); selectivity 50/51 Δt 0.5 s passes.
What's the total cost?
≈$102,229 equipment (LV switchgear + UPS + diesel + cables + secondary), feasibility-level, excl. industry-specific POA items.
Voltage drop and motor starting?
Cumulative drop ≤5% (pass); the 37 kW largest motor uses soft start to keep the dip ≤10%.
Why no payback/IRR here?
There's no PV/storage, so the configurator reports no renewable economics — the value is reliability; add rooftop PV to unlock energy-savings payback.
380 V vs 10 kV feed — which is right?
380 V suits a ≤250 kW building near an existing LV network; larger or remote sites should step to a 10 kV feed + on-site transformer.

Special Considerations

  • No MV transformer (380 V LV direct feed) — losses / transformer TCO are N/A; the 0.38 kV connection assumes an existing upstream 10/0.4 kV transformer.
  • The diesel is 1×500 kVA (standard 20-ft container) for only 80 kW standby duty (~20% load) — verify a smaller genset with the supplier or accept the standard unit.
  • UPS 80 kVA (64 kW) covers the 60 kW IT critical load at 107%; add a second unit for N+1 single-failure tolerance.
  • Fire load 30 kW on a dedicated circuit + end-transfer ATS (auto-added) — confirm the fire pump motor rating and soft-start.
  • Feasibility-level estimate; drawings are schematic, pending a licensed design institute.

Turn this into your project

Open this exact scenario pre-loaded in the Power System Configurator, then generate the full design document or the operation & techno-economic assessment.

Open in Power System Configurator →

One-Stop Supply of Conventional & Solar Power Equipment

From power distribution system design to solar energy — transformers, switchgear, substations and solar equipment, sized and quoted in one place. Use our calculators to get a complete bill of materials and FOB price.