2000 kW PV+BESS+Diesel Microgrid: Grid-Tied/Islanding Transfer & Black-Start Deep-Read
PV 800 kWp · BESS 600 kW/1355 kWh · Diesel 500 kW · 2×S13-2000/10 N+1 · on/off-grid + black start
1 · TL;DR Conclusion
Conclusion: this 2000 kW PV+diesel+BESS microgrid combines 800 kWp PV + 600 kW/1355 kWh BESS + 500 kW diesel + a 10 kV grid feed with grid-tied/islanding transfer and diesel black-start, on 2×S13-2000/10 transformers (N+1) — configurator total ≈ $803,022, EPC ≈ $770,000, 5-yr payback, 24.57% IRR, 487.3 t CO2/yr avoided (feasibility-level).
- •Four-source mix: 800 kWp PV (50% share) + 600 kW BESS (38%) + 500 kW diesel (13%), 3900 kW installed
- •Grid-tied/islanding transfer + black-start (500 kW diesel auto-start, blackStartCheck verified)
- •BESS 600 kW×4 h shaving saves ≈$113,880/yr (vs pure-diesel $245,280/yr)
- •Economics: $770,000 EPC, 5-yr payback, 24.57% IRR, 492% 25-yr ROI, LCOE $0.0983/kWh
- •N-1 redundancy passes: 2×2000 kVA at 84% loading after one unit trips; ≈487.3 t CO2/yr avoided
2 · Solution Overview
A PV+diesel+BESS microgrid integrates PV, storage, diesel generation and the grid into one self-healing microgrid that can transfer between grid-tied and islanded modes — built for mines, islands and remote base stations on weak or no grid. This 2000 kW design lets PV serve base load, BESS smooth fluctuation and shave peaks, and diesel provide black-start plus island backup, with renewable-first dispatch when grid-tied.
| Source | Role | Share kW | Share |
|---|---|---|---|
| Grid 10 kV | base | 0 kW | 0% |
| Solar PV 800 kWp | variable | 800 kW | 50% |
| BESS 600 kW / 1200 kWh | variable | 600 kW | 38% |
| Diesel 500 kW | base | 200 kW | 13% |
3 · Design Process & Rationale
1. Requirement identification
Mines/islands/base stations face weak or frequently-out grid supply, yet carry 800 kW of critical load that cannot drop. The design locks in islanding + black-start as hard requirements — which mandates diesel and BESS, not grid-tied PV alone.
2. Load grading & demand
2000 kW total → 1600 kW demand after demand factor; 800 kW critical, 1355 kW grade-2, 300 kW impact load (crusher/hoist) — the basis for sizing diesel and storage.
3. Source mix
800 kWp PV (daytime base) + 600 kW/1355 kWh BESS (2 h, fluctuation-smoothing + shaving) + 500 kW diesel (black-start + island backup) + 10 kV grid (main supply when tied), dispatched under one EMS.
4. Transformer sizing
1600 kW → ≈1684 kVA, so 2000 kVA tier with N+1 redundancy (redundancy=n1, 2 units) — a microgrid must survive one-unit trips and island heavy-load, so redundancy keeps critical load powered.
5. Transfer & black-start
gridMode=grid-tie-island + blackStart=yes: on grid loss the ATS transfers within 2 s, the diesel auto-starts for black-start (verified: 500 kW diesel can carry it). Anti-islanding prevents backfeed while islanded.
6. Distribution & protection
MV incomer → 2 transformers → MNS LV switchgear (with bus-tie) → feeders. LV fault 58.91 kA vs 80 kA breaking capacity; protection selectivity ratio 18.1×, grading satisfied.
7. Power quality & reactive
Impact load causes flicker and harmonics (THDi ≈20%); add SVG ±1 Mvar dynamic compensation + detuned reactors, and coordinate diesel with storage converters to avoid circulating current.
8. Economics check
BESS shaves 600 kW×4 h at a $0.13/kWh spread, saving ≈$113,880/yr; PV generates 812,160 kWh/yr. Overall 5-yr payback, 24.57% IRR, LCOE $0.0983/kWh.
Pain Points → Solution → Evidence
A grid outage halts production (800 kW critical load can't drop)
Grid-tied/islanding transfer + diesel black-start: ATS transfers in 2 s, diesel auto-starts for critical load
blackStartCheck verified (500 kW diesel) + N-1 pass (2×2000 kVA, 84% loading after a trip)
Diesel is expensive — $245k/yr fuel is unsustainable
PV+BESS shaving: 600 kW×4 h cuts diesel hours to a minimum
economic.shaving: ≈$113,880/yr saved; pure-diesel $245,280 vs hybrid $174,300/yr
Backfeed / PV disconnection risk when islanded
Anti-islanding protection (81U/81O) + EMS source coordination
microgrid drawing: PCC anti-islanding + transfer logic; compliance pass (no failures)
When does it pay back?
≈$770,000 EPC; PV+BESS save ≈$201,593/yr
economic: 5-yr payback, 24.57% IRR, 492% 25-yr ROI, NPV $1,213,967
4 · Key Parameter Deep-Read
| Parameter | Value | Basis | Impact & Boundary |
|---|---|---|---|
| Transformer capacity | 2×2000 kVA (N+1) | 1600 kW → 1684 kVA → 2000 kVA tier + one spare | 84% loading; stays 84% after one unit trips (N-1 pass) Step to 2500 kVA for growth or stricter redundancy |
| PV capacity | 800 kWp | 50% share; 812,160 kWh/yr generation | Serves base load in daytime, cutting diesel run-hours Limited by site area and BESS absorption; more PV needs more storage |
| BESS capacity | 600 kW / 1355 kWh (2 h) | Fluctuation-smoothing + shaving, 2 h duration | Shaves 600 kW×4 h, saving $113,880/yr Island backup needs ≥8 h plus a black-start source |
| Diesel capacity | 500 kW prime · black-start | Covers part of the 800 kW critical load + black-start (verified) | The only reliable source for island backup and black-start prime duty = continuous-rating, pricier than standby |
| Grid mode | grid-tie-island + black-start | Weak/no-grid sites must be able to island | 2 s ATS transfer; anti-islanding prevents backfeed Grid approval per local grid code (gridCodeNote) |
| Reactive compensation | SVG ±1 Mvar dynamic | 300 kW impact load causes flicker and reactive swings | Stabilizes bus voltage and suppresses flicker Add APF when THDi ~20% exceeds limits |
| Economics | IRR 24.57% · 5 yr | $770,000 EPC + $201,593/yr saving + 25-yr cashflow | The core investability metric Diesel price, irradiation and load factor are the key sensitivities |
5 · Drawing Deep-Read
The following drawings are shown for reference (full set in the configurator “View design document”):
6 · Operation Demo (Deep-Read)
Energy flow
Grid-tied: PV 800 kW serves base first, surplus charges BESS; BESS discharges 600 kW at peak and charges at valley; grid fills the gap. Islanded: diesel 500 kW black-starts, then BESS+PV+diesel jointly feed the 800 kW critical load.
Grid failure / black-start
Press 'Grid failure': ATS transfers within 2 s, diesel auto-starts for black-start, critical load stays up; in the N-1 case one transformer trips and the other continues at 84% loading.
Economics
812,160 kWh/yr generated, 0.8 self-use + surplus export; PV self-use ≈$201,593/yr (incl. BESS shaving); $770,000 invested, 5-yr payback, 24.57% IRR, LCOE $0.0983/kWh.
24h operation
A typical-day curve: daytime PV overlaps load, peak-time BESS discharge shaves the peak, overnight valley charging, diesel only during islanding/black-start — the four-source coordination in time order.
Other views (shown): Power quality & harmonics · Voltage profile · Scheme features · Environmental derating
7 · Economics & Payback
Equipment total ≈ $803,022, EPC ≈ $770,000 (incl. PV/BESS/diesel/distribution/installation). PV self-use saves ≈$201,593/yr (incl. BESS shaving); overall 5-yr payback, 24.57% IRR, 492% 25-yr ROI, LCOE $0.0983/kWh, NPV $1,213,967, 487.3 t CO2 avoided/yr.
8 · FAQ
How big a diesel in a PV+diesel+BESS microgrid?
How big a BESS, and how is duration computed?
How is black-start implemented?
How does grid-tied/islanding transfer work?
When does it pay back?
Pure diesel vs PV+diesel+BESS hybrid?
Will impact load collapse the bus?
Is N+1 transformer redundancy necessary?
How much PV should be installed?
What grid-connection paperwork is needed?
Special Considerations
- Grid-tied/islanding transfer needs grid approval plus anti-islanding/anti-backfeed (gridCodeNote TBC); assumed grid-tie-island here.
- Diesel duty=prime is continuous-rating (DG-1000kVA), pricier than standby; switch to standby to cut cost if only for emergencies.
- 2 h storage covers shaving/smoothing; long-duration islanding needs ≥8 h plus a black-start capacity check.
- 300 kW impact load causes flicker; SVG ±1 Mvar dynamic compensation is included; add APF if THDi ~20% exceeds limits.
- Feasibility-level estimate; drawings pending refinement by a licensed design institute.
Turn this into your project
Open this exact scenario pre-loaded in the Power System Configurator, then generate the full design document or the operation & techno-economic assessment.
Open in Power System Configurator →Related Scenarios
One-Stop Supply of Conventional & Solar Power Equipment
From power distribution system design to solar energy — transformers, switchgear, substations and solar equipment, sized and quoted in one place. Use our calculators to get a complete bill of materials and FOB price.