QDTB® Transformer
All figures are configurator-generated feasibility-level estimates; drawings are schematic deliverables pending refinement by a licensed design institute, not construction documents.
All Solutions

500 kW Truck Battery-Swap Station: 8×120 kW DC Chargers + 250 kW/1161 kWh Peak-Shaving BESS

8× DC120 kW · SCB13-400/10 · 250 kW/1161 kWh BESS · 400 A APF + SVG

1 · TL;DR Conclusion

Conclusion: an 8-bay truck battery-swap station (8×120 kW DC chargers, 960 kW installed) runs on one SCB13-400/10 transformer + a 250 kW/1161 kWh peak-shaving BESS + a 400 A APF — $264,418 equipment total. The BESS shaves 250 kW×4 h (≈ $47,450/yr at $0.13/kWh spread) so the 960 kW fleet stays within a 500 kW connection.

  • •8× 120 kW DC fast-charge bays (960 kW installed) — demand-limited to 500 kW (350 kW at Kd 0.7) via charger power-sharing + BESS.
  • •250 kW / 1161 kWh BESS peak-shaves 250 kW×4 h; ≈ $47,450/yr arbitrage at $0.13/kWh spread (feasibility-level).
  • •400 A APF (APF-403A) + ±1 Mvar SVG handle THDi ≈ 80% from the DC rectifier chargers.
  • •SCB13-400/10 single transformer at 92% loading — economical but thin headroom (watch the 5–7% cascade voltage-drop warn).
  • •BESS EPC ≈ $212,500 vs ≈ $47,450/yr shaving → ≈ 4.5 yr simple payback (demand-charge avoidance adds more).

2 · Solution Overview

A truck battery-swap station is the classic 'high-power DC fast-charging + peak-shaving BESS' case: 8 swap bays each with a 120 kW DC charger (960 kW installed), yet only a 500 kW grid connection — via charger power-sharing + a 250 kW/1161 kWh BESS that shaves the peak under the demand limit. The DC rectifier stack injects THDi ≈ 80%, requiring a 400 A APF + SVG.

500 kW / 350 kW
Grid connection / demand
8× 120 kW DC
Charger fleet (960 kW installed)
250 kW / 1161 kWh
Peak-shaving BESS (4 h)
SCB13-400/10
Transformer (single)
APF 400 A + SVG ±1 Mvar
Harmonic + reactive mitigation
$264,418
Equipment total (feasibility-level)
SourceRoleShare kWShare
Grid 10 kVbase100 kW29%
BESS 250 kW / 1000 kWhvariable250 kW71%

3 · Design Process & Rationale

① Size the charger fleet, not just the load

8×120 kW = 960 kW installed, but swap duty cycles are staggered → Kd 0.7 → 350 kW demand → 500 kW grid contract.

② Peak-shaving BESS instead of a bigger connection

250 kW/1161 kWh (4 h) BESS shaves the peak 250 kW×4 h, holding grid at 500 kW and cutting demand charges — no need for a 960 kW MV dedicated feeder.

③ Nonlinear load → harmonic mitigation

DC fast chargers are 6-pulse/Vienna rectifier loads; 400 kW nonlinear (80%) → THDi up to 80% → 400 A APF (APF-403A) + ±1 Mvar SVG.

④ Impact load from swap inrush

150 kW impact (battery-swap step load) — LV feeders sized for inrush; chargers soft-start / staggered switching.

⑤ Transformer sizing

350 kW demand / 0.92 PF ≈ 380 kVA → SCB13-400/10 (single) at 92% loading — economical but thin headroom.

⑥ MV/LV distribution + protection

KYN28A-12 MV + MNS LV switchgear, 8 charger feeders (YJV 25 mm²), 50/51 coordination, 14.15 kA LV short-circuit → 25 kA breaking.

⑦ EMS + BMS orchestration

EMS-1161 coordinates charger power-sharing + BESS charge/discharge against a real-time demand cap; SCADA + BMS communication.

Pain Points → Solution → Evidence

Pain

8 chargers at once (960 kW) would trip a 500 kW connection

Solution

charger power-sharing + 250 kW BESS peak-shaving caps grid draw at 500 kW

Evidence

capacitySummary renewablePct 71%, supplyMix storage shareKw 250 of 350 kW demand

Pain

DC rectifiers inject THDi ≈ 80%, overheating cables and transformers

Solution

400 A APF + ±1 Mvar SVG hold PCC THD under 5%

Evidence

BOM APF-403A ($14,605) + SVC/SVG ±1 Mvar ($32,200)

Pain

The 350 kW peak inflates the demand-charge bill

Solution

BESS shaves 250 kW×4 h → ≈ $47,450/yr at $0.13/kWh spread

Evidence

economic.shaving annualSaving 47450, invest 212500

4 · Key Parameter Deep-Read

ParameterValueBasisImpact & Boundary
totalKw500 kWgrid connection / contracted demandsets transformer + BESS sizing
installed fleet 960 kW > 500 kW — diversity + BESS bridge the gap
loadNonlinear400 kW (80%)DC fast chargers are rectifier loadsAPF + SVG required
THDi up to 80% uncompensated
loadImpact150 kWbattery-swap step loadfeeder + transformer inrush margin
high impact → soft-start / staggered swap
kd (demand factor)0.7staggered swap duty cycles350 kW demand from 500 kW connected
higher simultaneity → larger transformer
storageUsepeak-shaving + demandshave peak & cut demand charge250 kW/1161 kWh BESS (4 h)
4 h storage duration matches the peak window
avgPf0.92DC chargers with PFC front-end350/0.92 = 380 kVA → 400 kVA transformer
lower PF → larger transformer + PFC

5 · Drawing Deep-Read

Dwg 3/29Single-line diagram — 10 kV grid → SCB13-400/10 → 8 charger feeders + BESS branch
Why: Shows the electrical connection of all 8 charger bays + BESS + SVG — the core drawing of the scheme.
Dwg 26/29Peak-shaving operation profile — 24 h peak flattened by 250 kW×4 h BESS
Why: Quantifies the shaving economics: 250 kW×4 h daily at $0.13/kWh spread = $130/day — the basis for the BESS payback.
Dwg 12/29Power quality assessment — THDi ≈ 80% → APF to < 5%
Why: The DC rectifier harmonics are the station's biggest risk; the before/after APF+SVG comparison shows why filtering is non-optional.
Dwg 29/29EMS control state machine — Power-sharing + BESS charge/discharge scheduling logic
Why: How charger power-sharing + BESS scheduling enforce the demand cap in real time — the software core of '960 kW on a 500 kW connection'.

The following drawings are shown for reference (full set in the configurator “View design document”):

Dwg 1 · Electrical design basisDwg 4 · System topology diagramDwg 8 · Short-circuit calculationDwg 14 · Protection configurationDwg 15 · TCC protection coordination curveDwg 25 · Peak-shaving single-lineDwg 27 · BMS communication architectureDwg 28 · Fire suppression & thermal zoning

6 · Operation Demo (Deep-Read)

Load flow / voltage

Drag the load slider at 350 kW demand to see I²R losses and the cascade voltage drop (5–7% warn); doubling load roughly quadruples losses — why headroom matters.

Power quality

THDi 80% uncompensated → APF to < 5%; SVG compensates the charger reactive power dynamically.

Peak-shaving economics

250 kW×4 h shave at $0.13/kWh spread = $130/day ≈ $47,450/yr → ≈ 4.5 yr simple payback vs $212,500 BESS EPC.

Other views (shown): Load flow · Voltage · Losses · Peak-shaving economics · Power quality

7 · Economics & Payback

Equipment total $264,418 (feasibility-level). The economics live in the BESS: 250 kW/1161 kWh shaves 250 kW×4 h at $0.13/kWh spread ≈ $47,450/yr, against ≈ $212,500 BESS EPC → ≈ 4.5 yr simple payback (plus demand-charge savings where applicable). Honest caveat: at a flat tariff with no demand charge, pure energy arbitrage may not pay back — the BESS's real value is demand-cap avoidance + letting the 960 kW fleet run on a 500 kW connection, plus backup.

$264,418
Equipment total
$212,500
BESS EPC (250 kW/1161 kWh)
≈ $47,450/yr
Peak-shaving arbitrage (250 kW×4 h)
≈ 4.5 yr
BESS simple payback
Key assumptions driving these numbers
$0.12/kWh
Electricity price
$0.06/kWh
Feed-in tariff
80%
Self-consumption
$0.13/kWh
Peak-valley spread

8 · FAQ

8×120 kW = 960 kW, why only a 500 kW connection?
Swap duty cycles are staggered (Kd 0.7) → 350 kW demand; plus 250 kW BESS shaving + charger power-sharing, the grid peak stays under 500 kW — no HV dedicated feeder needed.
What BESS size for peak-shaving?
250 kW / 1161 kWh (4 h). The shave window 250 kW×4 h = 1161 kWh matches the station's peak period; too little capacity triggers the 'storage duration < required' warning.
Do DC fast chargers need harmonic filtering?
Yes. The DC rectifier stack reaches THDi ≈ 80%, which overheats cables and transformers. A 400 A APF (APF-403A, $14,605) + ±1 Mvar SVG hold PCC THD under 5%.
Is 400 kVA enough for 500 kW?
Yes. Demand 350 kW / 0.92 PF ≈ 380 kVA → SCB13-400/10 (92% loading). Watch the 5–7% cascade voltage drop — enlarge cable at the farthest bays.
How much does the BESS save, and when does it pay back?
250 kW×4 h at $0.13/kWh spread ≈ $47,450/yr; BESS EPC ≈ $212,500 → ≈ 4.5 yr simple payback, faster where demand charges apply.
Why is there a voltage-drop warning?
Concentrated chargers + long feeders + high current → 5–7% cascade drop. Enlarge the feeder, raise PF, or increase transformer capacity.
How is the swap inrush handled?
150 kW impact load (swap step) is included; LV feeders are sized for inrush and chargers soft-start / stagger switching to avoid stacked inrush.
Single or N+1 transformer?
A swap station is commercial/transport, not grade-1 load — a single SCB13-400/10 suffices; upgrade to N+1 only for 24/7 non-stop operation.
What does the whole scheme cost?
About $264,418 equipment (feasibility-level): SCB13-400/10, BESS-1161kWh, PCS-250kW, APF, SVG, KYN28A-12/MNS and secondary monitoring — 27 items.

Special Considerations

  • Cascade voltage drop 5–7% (warn) — enlarge the feeder cable or raise PF for the farthest charger bays.
  • THDi up to 80% on DC charger feeders — the 400 A APF + SVG are mandatory, not optional.
  • Ssc (500 MVA) and grid-code for BESS interconnection are assumed — confirm with the utility.
  • All figures are feasibility-level estimates; drawings are schematic, pending design-institute refinement.

Turn this into your project

Open this exact scenario pre-loaded in the Power System Configurator, then generate the full design document or the operation & techno-economic assessment.

Open in Power System Configurator →

One-Stop Supply of Conventional & Solar Power Equipment

From power distribution system design to solar energy — transformers, switchgear, substations and solar equipment, sized and quoted in one place. Use our calculators to get a complete bill of materials and FOB price.