QDTB® Transformer
All figures are configurator-generated feasibility-level estimates; drawings are schematic deliverables pending refinement by a licensed design institute, not construction documents.
All Solutions

500 kW Onshore Wind Farm: 800 kVA Box Transformer (0.69/35 kV) + 35 kV Collector + 110 kV Step-up Deep-Read

1×500 kW WTG · 800 kVA box transformer (0.69/35 kV) · 35 kV collector · 10 MVA 110 kV step-up · ±1 Mvar SVG

1 · TL;DR Conclusion

Conclusion: this 500 kW onshore wind farm (1 × 500 kW WTG) uses an 800 kVA one-turbine-one-transformer box transformer (0.69/35 kV) → a 35 kV collector (1 feeder) → a 110 kV step-up main transformer + ±1 Mvar SVG + 35 kV collector switchgear — configurator total ≈ $491,625 (FOB), EPC ≈ $640,850, 9 yr payback, 10.6% IRR, 181% 25-yr ROI (feasibility-level).

  • •1×500 kW WTG → 800 kVA box transformer (0.69/35 kV, engine "Combined dry-type"); one-turbine-one-transformer topology
  • •35 kV collector, 1 feeder (≤10 turbines/feeder); step-up main transformer 10 MVA 35/110 kV (engine floor — a real 0.5 MW farm ties in at 35 kV directly)
  • •±1 Mvar SVG for grid-code reactive support (PF ±0.95 continuous) + 35 kV collector switchgear + RMU-SF6
  • •Generation 1,040,250 kWh/yr (P50, CF≈24%), P90 986,906 kWh, revenue $83,220/yr @ $0.08/kWh PPA
  • •Economics: $640,850 EPC, 9 yr payback, 10.6% IRR, 181% 25-yr ROI

2 · Solution Overview

An onshore wind farm is a 100% generation-export case: the turbine generates at 0.69 kV, a box transformer (one-turbine-one-transformer) steps up to 35 kV, a collector feeder gathers output, and a step-up main transformer raises it to 110 kV for transmission. The configurator's generation-export mode models and prices the whole chain.

1 × 500 kW (0.5 MW)
Turbine
800 kVA (0.69/35 kV)
Box transformer
35 kV · 1 feeder
Collector
10 MVA (35/110 kV)
Step-up main
±1 Mvar
SVG
110 kV
Grid connection
500 kW (100% renewable)
Installed capacity
$491,625 (FOB)
Equipment total

3 · Design Process & Rationale

1. Requirement identification

500 kW onshore wind, 100% grid export, no local load; the explicit generationExport flag triggers generation-export mode instead of consumer-side distribution modelling.

2. Source sizing

One 500 kW WTG (turbMw 0.5); installed 500 kW, effective supply 400 kW (0.8 factor), 100% renewable share.

3. Generator voltage

The 0.69 kV machine terminal is LV and cannot transmit far — it must be stepped up on-site, which is exactly why one-turbine-one-transformer exists.

4. Box transformer selection

500 kW ÷ 1.0 PF × 1.05 margin = 525 kVA → 800 kVA standard tier (0.69/35 kV); at 35 kV the small machine is classed "Combined dry-type" by the engine.

5. Collector design

35 kV single feeder (30 MVA feeder limit → ≤10 × 800 kVA boxes/feeder); this case has 1 turbine → 1 feeder.

6. Step-up & POI

Step-up main transformer 35/110 kV (engine floor 10 MVA) + 110 kV POI; a real 0.5 MW farm usually ties in at 35 kV — 110 kV applies to multi-turbine utility farms.

7. Reactive & power quality

Grid connection needs PF ±0.95 continuous (GB/T 19963), so a ±1 Mvar SVG is added; turbine harmonics/flicker handled by SVG + filters.

Pain Points → Solution → Evidence

Pain

A wind farm has no local load — sizing it as a consumer distribution system understates the export-side equipment.

Solution

Generation-export mode models the full WTG→box→collector→step-up chain with PPA-based economics.

Evidence

genPlant mode active; 100% renewable share; PPA revenue $83,220/yr.

Pain

Grid code demands LVRT and ±0.95 PF — a passive plant trips off on any voltage dip.

Solution

±1 Mvar SVG provides continuous dynamic reactive + LVRT support, with collector feeder protection.

Evidence

BOM includes SVG ±1 Mvar (PF ±0.95 continuous); aligned with GB/T 19963.

Pain

One-turbine-one-transformer means many small boxes — the wrong tier over-builds cost or overloads.

Solution

The engine sizes the box on turbine rating/PF/margin and picks the standard tier.

Evidence

525 kVA raw demand → 800 kVA standard tier, one-turbine-one-transformer.

4 · Key Parameter Deep-Read

ParameterValueBasisImpact & Boundary
Box transformer800 kVA (0.69/35 kV)500 kW ÷ 1.0 PF × 1.05 margin = 525 kVA → 800 kVA tierOne-turbine-one-transformer; small 35 kV machine classed "Combined dry-type"
>3 MW turbines switch to "Oil-immersed combined box"
Collector voltage35 kVcollectorKv=35 (kept when ≥35)30 MVA feeder limit → ≤10 boxes/feeder
<35 kV drops to 10 kV collection
Step-up main transformer10 MVA (35/110 kV)Total collector 0.8 MVA → engine floor 10 MVA110 kV POI
Real 0.5 MW ties 35 kV directly; 110 kV is for multi-turbine farms
SVG rating±1 Mvar25% of 500 kW = 125 kvar → 1 Mvar min tierPF ±0.95, LVRT support
≥1 Mvar engine floor
Annual P501,040,250 kWh500 kW × 8760 h × CF 0.25 × 0.95$83,220/yr @ $0.08/kWh
P90 = 986,906 kWh (CV 0.04)
Capacity factor≈24%Wind full-load 2190 h (8760×0.25) × 0.95Drives 10.6% IRR
Highly site-specific wind resource

5 · Drawing Deep-Read

Dwg 3/12Generation Plant Single-line Diagram — WTG → box transformer → 35 kV collector → 110 kV step-up → grid
Why: The generation-export skeleton shows the export path rather than consumer distribution — the structural source of plant reliability.
Dwg 12/12Wind farm single-line diagram — 1×500 kW WTG · 800 kVA box (0.69/35 kV) · 35 kV collector · 10 MVA 35/110 kV step-up
Why: The core wind topology: one-turbine-one-transformer + collector feeder + step-up main transformer — three voltage levels on one drawing.
Dwg 4/12Short-circuit calculation — Collector / POI fault levels → breaker sizing
Why: Collector and POI fault levels size the breakers and cable thermal stability.
Dwg 10/12Protection configuration — LVRT + collector feeder protection + step-up differential
Why: Low-voltage ride-through and staged protection coordination are the bottom line for wind farm grid connection.
Dwg 7/12Power quality assessment — Turbine harmonics / flicker + SVG sizing check
Why: The turbine is a harmonic/flicker source; SVG and filter ratings must be checked against grid limits.

The following drawings are shown for reference (full set in the configurator “View design document”):

Dwg 1 · Electrical design basisDwg 2 · Symbol legendDwg 5 · Applicable codes & standardsDwg 6 · Construction & testing requirementsDwg 8 · Grounding systemDwg 9 · Surge protection & SPDDwg 11 · Main equipment technical data

6 · Operation Demo (Deep-Read)

Energy flow

WTG 500 kW → 0.69 kV terminal → 800 kVA box up to 35 kV → collector feeder → 110 kV step-up → grid export, 100% online.

Reactive & power quality

±1 Mvar SVG continuous dynamic reactive, PF ±0.95; turbine harmonics/flicker handled with the SVG.

Fault & protection

LVRT support on dips, staged collector feeder protection, step-up differential — a single fault does not trip the whole farm.

Economics

1,040,250 kWh/yr, $83,220/yr; $640,850 EPC, 9 yr payback, 10.6% IRR, 181% 25-yr ROI.

Other views (shown): LCC (life-cycle cost) · Power quality & harmonics · Voltage profile · Scheme features · Environmental derating

7 · Economics & Payback

Equipment FOB ≈ $491,625 (WTG $352,500 + box transformer $37,000 + step-up $29,500 + SVG $50,000 + HV switchgear $16,750 + RMU $5,875; collector network & switchgear are POA); EPC ≈ $640,850. Annual 1,040,250 kWh → $83,220/yr @ $0.08/kWh PPA; 9 yr payback, 10.6% IRR, 181% 25-yr ROI.

$640,850
EPC investment
9 yr
Payback
10.6%
IRR
181%
25-yr ROI
1.04 GWh
Annual generation
$83,220
Annual revenue

8 · FAQ

What box transformer for a 500 kW wind turbine?
800 kVA (0.69/35 kV): 500 kW ÷ 1.0 PF × 1.05 = 525 kVA → 800 kVA standard tier, one-turbine-one-transformer.
Why a 35 kV collector?
A 35 kV feeder carries 30 MVA (≤10 × 800 kVA boxes/feeder); below 35 kV the engine drops to 10 kV collection.
What size 110 kV step-up transformer?
The engine floors at 10 MVA (35/110 kV); a 0.5 MW farm collects only 0.8 MVA, so it should tie in at 35 kV — 110 kV is for multi-turbine farms.
What is the payback?
9 yr at $0.08/kWh PPA, 10.6% IRR, 181% 25-yr ROI, on 1,040,250 kWh/yr (P50).
Why is an SVG needed?
Grid code (GB/T 19963) requires PF ±0.95; the ±1 Mvar SVG gives continuous dynamic reactive + LVRT support.
How much energy per year?
1,040,250 kWh (P50, CF≈24%); P90 is 986,906 kWh.
Is this one-turbine-one-transformer?
Yes — each WTG gets a dedicated 800 kVA box transformer, the standard onshore wind topology.
What does $491,625 cover?
WTG $352,500 + box $37,000 + step-up $29,500 + SVG $50,000 + HV switchgear $16,750 + RMU $5,875 (FOB); collector items are POA.
Why is stdKva 500 while the box is 800 kVA?
stdKva 500 is the engine's demand-derived default; the wind box is 800 kVA (per windCalc), and the plant step-up is 630 kVA (YB-630/10).

Special Considerations

  • Step-up main transformer is engine-floored at 10 MVA (smallest 35/110 kV tier); a 0.5 MW single-turbine farm should realistically tie in at 35 kV — 110 kV step-up is for multi-turbine utility farms. Feasibility-level, pending design institute.
  • The priced BOM step-up is YB-630/10 (10 kV, the engine's PV-oriented generic step-up); the wind 35/110 kV collector/step-up scope (collector switchgear + main transformer) is POA — reconcile with the design institute.
  • LVRT / grid code (GB/T 19963) is not explicitly modelled in the engine — confirm fault-ride-through requirements with the grid operator.
  • Collector network and collector switchgear are line items without unit price (POA) — the total is conservative.
  • Receiving-side calcs (10/0.4 kV short-circuit, load flow, arc flash, N-1) are stale in generation-export mode — ignore them; plant-side data is in windCalc/genPlant.

Turn this into your project

Open this exact scenario pre-loaded in the Power System Configurator, then generate the full design document or the operation & techno-economic assessment.

Open in Power System Configurator →

One-Stop Supply of Conventional & Solar Power Equipment

From power distribution system design to solar energy — transformers, switchgear, substations and solar equipment, sized and quoted in one place. Use our calculators to get a complete bill of materials and FOB price.