QDTB® Transformer
All figures are configurator-generated feasibility-level estimates; drawings are schematic deliverables pending refinement by a licensed design institute, not construction documents.
All Solutions

800 kW / 800 kVA Petrochemical Power: Ex Zone 2 + 200 kW ESP VFD + 1000 kVA Diesel Deep-Read

2×S13-M-800/10 N+1 · 200 kW ESP VFD · Ex Zone 2 · 1000 kVA diesel (600 kW standby)

1 · TL;DR Conclusion

Conclusion: this 800 kW petrochemical plant uses 2×S13-M-800/10 oil transformers (N+1) + a 200 kW ESP VFD (Ex Zone 2) + a 1000 kVA (600 kW standby) emergency diesel — configurator total ≈ $585,247, 84% N-1 loading, THDi 25% (needs APF/SVG), SH15 amorphous upgrade pays back in 3.3 yr (feasibility-level).

  • •2×800 kVA S13-M-800/10 oil transformers (N+1), 84% loading after one-unit loss (pass), 640 kW demand
  • •200 kW ESP on VFD — 1.7% start dip vs 8.1% DOL; Ex Zone 2 → Ex d board + Ex MCC (IEC 60079)
  • •Emergency diesel 1×1000 kVA (600 kW standby) covers grade-1 400 kW + fire 150 kW = 550 kW (V9 pass), 20 ft container, 3-day autonomy
  • •THDi 25% over limit → detuned reactor + APF/SVG active filtering (V6 warn)
  • •Economics: $585,247 total; SH15 amorphous upgrade saves $410/yr, 3.3 yr payback; losses 248,596 kWh/yr ≈ $29,832

2 · Solution Overview

A petrochemical plant is a hazardous-area, grade-1-heavy load: fire water, emergency lighting and DCS control must never lose power, while ESP pumps and process motors are harmonic-rich VFD loads. This scheme pairs N+1 oil transformers with Ex Zone 2 distribution, a VFD-driven ESP, and an emergency diesel for fire + critical process.

2×800 kVA (S13-M, N+1)
Transformer
10 kV dual (N+1)
Feed
640 kW (800 kW installed)
Demand
200 kW (VFD)
ESP VFD
Zone 2 (Ex d)
Hazardous zone
1×1000 kVA (600 kW standby)
Diesel
400 kW + fire 150 kW
Grade-1 load
25% (→ APF/SVG)
THDi
SourceRoleShare kWShare
Grid 10 kVbase640 kW100%
Diesel 600 kWbackup0 kW0%

Petrochemical Power System Calculator

Size and configure a high-reliability dual-source power distribution system for continuous petrochemical processes - redundancy level, explosion-proof equipment, BOM and single-line diagram.

Open the Calculator
Smart Monitoring & Control
Add the protection, metering and SCADA (monitoring & secondary) layer to the BOM and architecture diagram.

3 · Design Process & Rationale

1. Requirement identification

800 kW petrochemical unit: grade-1 400 kW (fire 150 + emergency/control + critical process 250), critical process 250 kW, 200 kW ESP VFD, Zone 2, ≤15 s allowed outage.

2. Load & grading

Fire 150 + emergency/critical → grade-1 400 kW; ESP/process → grade-2 250; general → grade-3 150. Grade-1 + fire = 550 kW sets the diesel size.

3. Source & mix

10 kV grid (base) + 600 kW standby diesel. Diesel covers grade-1 + fire 550 kW (V9 pass 109%), transfer ≤15 s.

4. Transformer sizing

640 kW demand ≈ 674 kVA → 800 kVA tier; N+1 → 2×S13-M-800/10 oil (outdoor, fire-separation), 84% loading after one-unit loss.

5. Explosion-proof & ESP

Ex Zone 2 → Ex d board + Ex MCC (IEC 60079); 200 kW ESP on VFD (1.7% dip vs 8.1% DOL); detuned reactor + APF for 25% THDi.

6. Protection & secondary

MV 31.5 kA / LV 36 kA breaking; 104 protocol + secondary schematic + DC auxiliary; selectivity 11.9×.

7. Reliability & emergency

Diesel ATS auto-transfer + fire end-transfer, 3-day fuel autonomy; N-1 keeps 84% loading after one-unit loss.

Pain Points → Solution → Evidence

Pain

A stray spark in a hazardous area can ignite gas

Solution

Ex Zone 2 equipment per IEC 60079: Ex d board + Ex MCC, equipotential earthing

Evidence

V14 zone2 Ex d; grounding + surge-protection drawings

Pain

Fire pumps must run on total grid loss

Solution

Dedicated fire feeder + end-transfer ATS + 1000 kVA diesel

Evidence

V11 dedicated circuit; V9 pass (600 ≥ grade-1 400 + fire 150); 3-day autonomy

Pain

ESP VFDs inject harmonics that overheat the transformer

Solution

Detuned reactor + APF/SVG active filtering

Evidence

V6 THDi 25% over limit → APF/SVG recommended

4 · Key Parameter Deep-Read

ParameterValueBasisImpact & Boundary
Transformer capacity800 kVA ×2 (S13-M)674 kVA → 800 tier; N+1 → 2 oil units84% loading; outdoor oil for fire separation
above ~850 kVA demand, step to 1000/1250
Demand factor0.8 → 640 kWinstalled 800 kW × Kd 0.8sizes transformer & cable at real demand
verify Kd against process schedule
ESP start200 kW VFD, 1.7% dipVFD kst 1.3 vs DOL 6.5no sag on other process; DOL would be 8.1%
confirm downhole cable & braking resistor
Hazardous zoneZone 2gas/vapor present only under abnormal conditionsEx d board + Ex MCC, higher cost (POA)
Zone 1 → stricter Ex ia/ib, more cost
Emergency diesel1×1000 kVA (600 kW standby)covers grade-1 400 + fire 150 = 550 kW3-day autonomy, 75% load, <15 s auto-start
full-site backup needs ≈950 kW
HarmonicsTHDi 25%nonlinear 200 kW / 800 kWneeds APF/SVG; detuned reactor alone won't clear
APF target THDi ≤8%

5 · Drawing Deep-Read

Dwg 3/26Single-line diagram — 10 kV dual → 2×S13-M-800/10 → MNS LV bus → Ex MCC + ESP VFD + fire + diesel ATS
Why: The SLD shows the reliability skeleton: dual incomers + N+1 transformers + fire end-transfer + diesel auto-transfer — four supply layers on one drawing, the structural source of continuity.
Dwg 15/26TCC protection coordination curve — Incomer → transformer → LV incomer → feeder, 0.3/0.2 s grading, selectivity pass (11.9×)
Why: A plant fears one fault blacking out the site; TCC verifies selectivity — a downstream fault trips only its feeder (0.1 s) while upstream 0.3 s holds, 11.9× ensuring grading.
Dwg 19/26Reactive & harmonic compensation — THDi 25% · detuned reactor + APF/SVG
Why: ESP VFDs push THDi to 25% over the limit; the PFC drawing specifies detuned reactor + active filtering — the key to keeping the transformer cool and the bus clean.
Dwg 25/26Diesel fuel oil system — 1×1000 kVA · 20 ft container · 3-day autonomy
Why: The emergency diesel is the last line for fire + critical process; the fuel system drawing quantifies 3-day autonomy — the locus of 'fire still runs on total grid loss'.
Dwg 16/26Grounding system — Hazardous-area equipotential · static earthing
Why: Static and fault current in a hazardous area are drained by earthing; equipotential bonding is the last physical barrier of explosion safety.

The following drawings are shown for reference (full set in the configurator “View design document”):

Dwg 4 · System topologyDwg 5 · Distribution systemDwg 6 · MV distribution systemDwg 7 · LV distribution systemDwg 8 · Short-circuit calculationDwg 9 · Applicable codes & standardsDwg 10 · Main equipment technical dataDwg 11 · Construction & testingDwg 12 · Power quality assessmentDwg 13 · SCADA architectureDwg 14 · Protection configurationDwg 17 · Lightning & surge protectionDwg 18 · Equipment layoutDwg 20 · Grid-tied / islanding transferDwg 21 · Secondary control & signalDwg 22 · Terminal stripDwg 23 · Panel layoutDwg 24 · DC auxiliary powerDwg 26 · Diesel earthing system

6 · Operation Demo (Deep-Read)

Reliability & availability

N+1 84% after one-unit loss + diesel auto-transfer ≤15 s + fire end-transfer, covering grade-1 400 + fire 150 kW; series availability ≈99.9% class.

Fault & protection

MV 28.9 kA / LV 27.8 kA, breaking MV 31.5 kA / LV 36 kA (1.1–1.3× margin); selectivity 11.9×, a downstream fault trips only its feeder.

Power quality

THDi 25% over limit, detuned reactor + APF/SVG; ESP VFD start dip 1.7% (DOL 8.1%), bus voltage 0.983 pu.

Economics

$585,247 total; SH15 amorphous upgrade 3.3 yr payback ($410/yr); losses 248,596 kWh/yr ≈ $29,832.

Other views (shown): LCC (life-cycle cost) · Power quality & harmonics · Voltage profile · Scheme features · Environmental derating

7 · Economics & Payback

Equipment total ≈ $585,247 (2×S13-M-800/10 + Ex Zone 2 distribution + 200 kW ESP VFD + 1000 kVA diesel + 104 SCADA). No PV/BESS in this scheme, so economics = capex + losses + transformer TCO: upgrading S13→SH15 amorphous saves ≈3,416 kWh/yr (≈$410/yr), 3.3 yr payback; annual transformer+line losses ≈248,596 kWh (≈$29,832/yr). Diesel is standby-only — running cost applies only on grid outage.

$585,247
Equipment total
2×800 kVA S13-M
Transformer
3.3 yr
SH15 upgrade payback
$29,832
Annual losses
248,596 kWh/yr
Loss energy
1×1000 kVA
Diesel

8 · FAQ

What transformer for an 800 kW petrochemical plant?
640 kW ≈ 674 kVA → 800 kVA tier; N+1 uses 2×S13-M-800/10 oil transformers, 84% loading after one-unit loss.
How is the hazardous area handled?
Zone 2 → Ex d distribution board + Ex MCC per IEC 60079, plus equipotential earthing and surge protection; quoted per project.
Does the ESP need a VFD?
Yes — 200 kW on VFD keeps the start dip at 1.7% (vs 8.1% DOL), and VFD gives flow control plus soft braking.
How big a diesel generator?
1×1000 kVA (600 kW standby) covers fire 150 kW + grade-1 400 kW = 550 kW; 20 ft container, 3-day fuel autonomy.
How are harmonics handled?
ESP VFDs push THDi to 25%; use detuned reactor + APF active filter (detuned alone won't clear the exceedance).
What happens on grid loss?
The diesel auto-starts and ATS transfers grade-1 + fire loads within the 15 s allowed outage; fire load has a dedicated end-transfer.
What's the payback on a better transformer?
SH15 amorphous vs S13 saves ≈3,416 kWh/yr ($410/yr), 3.3 yr payback at 84% load factor.
Why oil-type not dry-type?
Outdoor substation with fire-separation distance; S13 oil is economical for process plants; dry-type for indoor/IT spaces.
Is the price final?
No — $585,247 is a feasibility-level equipment estimate; Ex equipment and VFD are POA, and site Ssc must be confirmed.

Special Considerations

  • THDi 25% exceeds the limit — a detuned reactor alone won't clear it; add APF active filtering (V6 remedy).
  • 600 kW diesel covers grade-1 400 kW + fire 150 kW = 550 kW (V9 pass); full-site 800 kW backup needs ≈950 kW.
  • Ex Zone 2 equipment (Ex d board + Ex MCC) is quoted per project (POA); final Ex certification per IEC 60079 to be confirmed.
  • The 200 kW ESP VFD is the largest motor; confirm downhole cable and braking resistor for the submersible pump.
  • Feasibility-level estimate; drawings pending a licensed design institute; confirm grid Ssc (500 MVA assumed).

Turn this into your project

Open this exact scenario pre-loaded in the Power System Configurator, then generate the full design document or the operation & techno-economic assessment.

Open in Power System Configurator →

One-Stop Supply of Conventional & Solar Power Equipment

From power distribution system design to solar energy — transformers, switchgear, substations and solar equipment, sized and quoted in one place. Use our calculators to get a complete bill of materials and FOB price.