QDTB® Transformer
All figures are configurator-generated feasibility-level estimates; drawings are schematic deliverables pending refinement by a licensed design institute, not construction documents.
All Solutions

800 kW Rooftop PV: 0.4 kV Grid Connection with Anti-Islanding & Metering Deep-Read

800 kWp PV · 0.4 kV grid connection · anti-islanding · net metering · 640 kW effective

1 · TL;DR Conclusion

Conclusion: this 800 kW rooftop PV connects at 0.4 kV with 800 kWp of PV (640 kW effective, 100% renewable), anti-islanding + net metering — configurator total ≈ $230,007, EPC ≈ $440,000, 6 yr payback, 18.15% IRR, 345% 25-yr ROI, 487 t CO2 avoided/yr (feasibility-level).

  • •0.4 kV LV grid connection; 800 kWp PV → 640 kW effective demand, stdKva 674, 100% renewable share
  • •PV yields ≈812,160 kWh/yr (P50), 0.8 self-consumption → 649,728 kWh self-used + 162,432 kWh exported (net metering)
  • •Anti-islanding + net metering on the 0.4 kV PCC; compliance pass (no failures)
  • •Economics: $440,000 EPC, 6 yr payback, 18.15% IRR, 345% ROI, LCOE $0.0562/kWh, NPV $412,017
  • •Watch V6 (THDi over limit → APF/SVG) and V7 (160 kW over-generation → export or storage)

2 · Solution Overview

A rooftop distributed PV plant at 800 kW is sized to the 0.4 kV grid connection: inverters feed the LV bus, self-consume 80% on-site and export 20% through net metering. Anti-islanding disconnects on grid loss, and the main design risk is the high LV fault level (24.31 kA) that squeezes the breaking-capacity margin.

0.4 kV LV (3-phase)
Feed
800 kWp
PV
640 kW
Effective supply
100%
Renewable share
Anti-islanding + metering
Grid connection
812,160 kWh (P50)
Annual generation
0.8
Self-consumption
24.31 kA
LV fault level
SourceRoleShare kWShare
Grid 0.4 kVbase0 kW0%
Solar PV 800 kWpvariable640 kW100%

3 · Design Process & Rationale

1. Requirement identification

800 kWp rooftop PV on a 0.4 kV grid connection, self-consumption + export.

2. Load & PV balance

800 kW site demand → 640 kW effective (0.8 kd); 800 kWp PV covers 100% renewable.

3. PV stringing

800 kWp → 250 kW-class string inverters, 1500 VDC MPPT, PR 0.846.

4. LV connection

0.4 kV switchgear + 300 mm² feeders; 640 kW at 0.4 kV → 24.31 kA fault level.

5. Anti-islanding & metering

Grid-tie inverters + anti-islanding relay on the PCC; 162,432 kWh export via net metering.

6. Power quality

THDi flagged (V6) → APF/SVG; PFC for reactive compensation.

7. Over-generation

160 kW instantaneous over-generation (800 vs 640) → export via metering (or curtail/store).

Pain Points → Solution → Evidence

Pain

PV export must not island the grid

Solution

Anti-islanding relay + grid-tie inverter on the PCC

Evidence

Compliance pass; grid-connection approval in toConfirm

Pain

Inverter harmonics pollute the LV bus

Solution

APF/SVG active filtering

Evidence

V6 THDi exceeds limit (warn)

Pain

800 kWp over-generates vs 640 kW demand

Solution

Export the 160 kW via net metering (or add storage)

Evidence

V7 160 kW over-generation; economic export 162,432 kWh

Pain

0.4 kV fault level is punishing

Solution

25 kA gear + 300 mm² cable, verify Ssc

Evidence

ikLv 24.31 kA, 1× margin (tight)

4 · Key Parameter Deep-Read

ParameterValueBasisImpact & Boundary
PV capacity800 kWp812,160 kWh/yr (P50), PR 0.846100% renewable, LCOE $0.0562
Limited by roof area / orientation
Effective supply640 kW800 × 0.8 diversitystdKva 674
Depends on demand profile
Self-consumption0.8Default649,728 kWh self-used, 162,432 kWh export
Higher with storage
LV fault24.31 kA0.4 kV + 800 kW25 kA breaking = 1× margin (tight)
Confirm Ssc; may need 36/50 kA gear
Grid connection0.4 kV + anti-islandingDistributed PVNet metering export
Grid-code approval
Power qualityTHDi (V6 warn)Inverter harmonicsAPF/SVG needed
Filter sizing
Economics$440,000 EPCPV + LV connection6 yr payback, 18.15% IRR
Feed-in tariff / curtailment

5 · Drawing Deep-Read

Dwg 3/23Single-line diagram — 800 kWp PV → string inverters → 0.4 kV bus → PCC (anti-islanding + metering)
Why: The SLD shows the 0.4 kV connection skeleton: PV → inverters → LV bus → PCC, with the anti-islanding relay and bidirectional meter on the point of coupling — the structural source of safe grid connection.
Dwg 4/23System topology — PV · grid → 0.4 kV bus → site loads + export
Why: The topology visualizes how PV and grid meet on the 0.4 kV bus — self-use first, surplus exported — with EMS dispatch, the landing point of distributed-PV energy management.
Dwg 7/23Short-circuit calculation — 0.4 kV fault 24.31 kA · 25 kA breaking (1× margin)
Why: The fault level of large 0.4 kV PV reaches 24.31 kA, forcing 25 kA LV gear at only 1× margin — the quantified basis of the breaking-capacity safety line; step to 36/50 kA if Ssc is higher.
Dwg 13/23Protection configuration — Overcurrent 50/51 + anti-islanding 81U/81O + metering
Why: Protection is the second line of defense for distributed PV: overcurrent grading + anti-islanding (IEC 62116 / IEEE 1547) + metering ensure fault clearing and safe interconnection.
Dwg 19/23Microgrid transfer — PCC · anti-islanding + metering · disconnect on grid loss
Why: The microgrid drawing previews the anti-islanding action on grid loss: the grid-tie inverter + anti-islanding relay disconnect immediately to prevent islanding — the safety core of 0.4 kV interconnection.

The following drawings are shown for reference (full set in the configurator “View design document”):

Dwg 18 · Reactive & harmonic compensationDwg 11 · Power quality assessmentDwg 14 · TCC coordination curveDwg 15 · Grounding systemDwg 16 · Lightning & surge protectionDwg 17 · Equipment layout planDwg 9 · Main equipment technical dataDwg 23 · DC auxiliary power system

6 · Operation Demo (Deep-Read)

Energy flow

PV 800 kW feeds the 640 kW site first, the 160 kW surplus exports via metering; the grid fills gaps; anti-islanding disconnects on grid loss — self-consumption + export at a glance.

Economics

812,160 kWh/yr, $87,713/yr saved; $440,000 EPC, 6 yr payback, 18.15% IRR, LCOE $0.0562/kWh, NPV $412,017, 487.3 t CO2 avoided/yr.

Power quality

THDi over the limit (V6) needs APF/SVG; PFC compensates reactive power — the key power-quality point for large 0.4 kV PV.

Fault & protection

0.4 kV fault 24.31 kA, 25 kA breaking (1× tight margin); anti-islanding 81U/81O disconnects on grid loss — the safety core of interconnection.

Other views (shown): Voltage profile · Scheme features · LCC (life-cycle cost) · Environmental

7 · Economics & Payback

EPC ≈ $440,000 (800 kWp PV + 0.4 kV connection). PV saves ≈$87,713/yr (self-consumption at $0.12/kWh + 0.2 export at $0.06/kWh); 6 yr payback, 18.15% IRR, 345% 25-yr ROI, LCOE $0.0562/kWh, NPV $412,017, 487.3 t CO2 avoided/yr. The high self-consumption ratio (0.8) is what drives the strong payback.

$440,000
EPC investment
6 yr
Payback
18.15%
IRR
345%
25-yr ROI
$0.0562/kWh
LCOE
487.3 t/yr
CO2 avoided
Key assumptions driving these numbers
$0.12/kWh
Electricity price
$0.06/kWh
Feed-in tariff
812160 kWh
Annual generation (P50)
80%
Self-consumption

8 · FAQ

Can 800 kW PV connect at 0.4 kV?
Yes, but the fault level reaches 24.31 kA — standard 25 kA LV gear has only 1× margin; confirm Ssc and consider 36/50 kA gear.
How much does it generate?
≈812,160 kWh/yr (P50, PR 0.846), of which 649,728 kWh is self-consumed and 162,432 kWh exported at 0.8 self-consumption.
What's the payback?
6 yr payback, 18.15% IRR, 345% 25-yr ROI, LCOE $0.0562/kWh, NPV $412,017 on a $440,000 EPC.
Do I need anti-islanding protection?
Yes — the grid-tie inverters + an anti-islanding relay disconnect on grid loss; grid-connection approval is required before energizing.
What about inverter harmonics?
V6 flags THDi over the limit — add APF/SVG active filtering on the 0.4 kV bus.
What happens to the 160 kW over-generation?
At 800 kWp vs 640 kW demand there's 160 kW instantaneous excess — export it via net metering, or add storage/curtail it (V7).
How is the export metered?
Net metering at the PCC records the 162,432 kWh/yr export; feed-in tariff $0.06/kWh vs $0.12/kWh retail.
What cables and switchgear?
300 mm² feeders, LV switchgear + PFC + detuned reactors; 25 kA breaking capacity.
How much CO2 does it avoid?
≈487.3 t/yr, roughly the annual footprint of ~106 passenger cars.

Special Considerations

  • LV fault level 24.31 kA leaves only ~1× margin on standard 25 kA gear — confirm the actual grid Ssc and consider 36/50 kA switchgear.
  • V6 THDi exceeds the limit (inverter harmonics) — add APF/SVG active filtering on the LV bus.
  • V7 flags 160 kW instantaneous over-generation (800 kWp vs 640 kW demand) — export via net metering, or add storage to absorb it.
  • Anti-islanding + grid-connection approval are mandatory (toConfirm: local grid code) — do not energize without utility sign-off.
  • Feasibility-level; schematic drawings pending a licensed design institute.

Turn this into your project

Open this exact scenario pre-loaded in the Power System Configurator, then generate the full design document or the operation & techno-economic assessment.

Open in Power System Configurator →

One-Stop Supply of Conventional & Solar Power Equipment

From power distribution system design to solar energy — transformers, switchgear, substations and solar equipment, sized and quoted in one place. Use our calculators to get a complete bill of materials and FOB price.