QDTB® Transformer
All figures are configurator-generated feasibility-level estimates; drawings are schematic deliverables pending refinement by a licensed design institute, not construction documents.
All Solutions

2000 kW Long-Duration Storage Substation: N+1 Main Transformer + 8 h/16 MWh, Grid-Code & Capacity Deep-Read

2000 kW PCS · 8 h/16 MWh LDES · 2×S13-M-2000/35 main transformer (N+1) · 35 kV feed · 83 clusters

1 · TL;DR Conclusion

Conclusion: this 2000 kW long-duration storage substation uses a 2000 kW PCS + 16063 kWh/8 h battery (83 clusters · 768 V DC) + 2×S13-M-2000/35 large main transformers (N+1) on a 35 kV grid. nMinus1 passes (84% loading after one transformer out); peak shaving ($0.13/kWh spread) saves ≈$379,600/yr; equipment ≈ $2,314,905, EPC ≈ $2,900,000 (feasibility-level).

  • •LDES 2000 kW / 16063 kWh = 8 h, DOD 0.9 (17848 kWh rated), 83 clusters × 215 kWh, 768 V DC
  • •Large main transformer 2×S13-M-2000/35 (N+1); nMinus1 passes — 84% loading after one unit out
  • •Shaving: 2000 kW × 4 h × $0.13/kWh = ≈$379,600/yr (V24 basis)
  • •35 kV feed; short-circuit LV 36.54 kA, breaking 50 kA (1.4×) · HV 25 kA (3×)
  • •Losses 4,510,068 kWh/yr ($541,208/yr); SH15 amorphous upgrade pays back in just 2.4 yr

2 · Solution Overview

Long-duration energy storage (LDES) delivers 4+ hour — even multi-day — charge/discharge for multi-day peaking, frequency regulation and reserve, typically via flow batteries, pumped hydro or compressed air. This is a 2000 kW station with 8 h/16 MWh duration, on a 35 kV grid, with 2×2000 kVA main transformers (N+1).

2×2000 kVA (S13-M-2000/35, N+1)
Main transformer
2000 kW
PCS
16063 kWh / 8 h
Storage energy
83 × 215 kWh
Battery clusters
768 V DC
DC voltage
35 kV
Grid voltage
Grid-tied
Mode
Pass (84% after one out)
nMinus1
SourceRoleShare kWShare
Grid 35 kVbase0 kW0%
BESS 2000 kW / 16000 kWhvariable1600 kW100%

3 · Design Process & Rationale

1. Requirement identification

A long-duration station centers on duration and capacity (2000 kW · 8 h); the deciding points are the large main transformer and the grid-code basis — targeting multi-day peaking, frequency regulation and reserve.

2. Duration sizing

2000 kW PCS × 8 h = 16063 kWh usable (DOD 0.9 → 17848 kWh rated), 83 clusters × 215 kWh at 768 V DC; 8 h is a typical long-duration tier (pumped / compressed-air / flow).

3. Large main transformer

2000 kW / 0.95 ≈ 2105 kVA → 2×2000 kVA (N+1, one unit carries 84%), S13-M-2000/35 — meeting large-capacity connection and reliability.

4. Redundancy design

N+1 makes nMinus1 pass: after one transformer out, the remaining 2000 kVA covers 84% of load (sdKva 1684), ensuring continuous supply.

5. Protection & coordination

50/51 overcurrent grading; IEC 60909 short-circuit LV 36.54 kA, LV breaking 50 kA (1.4× margin) and HV 25 kA (3×), V19 passes.

6. Power quality

High-power PCS rectifier harmonics THDi 20% → detuned reactor + APF/SVG; reactive compensation holds PF ≥ 0.95.

7. Losses & economics

The large transformer loses 4,510,068 kWh/yr ($541,208/yr), a meaningful share; SH15 amorphous upgrade saves 6,920 kWh/yr and pays back in just 2.4 yr.

8. Grid code

35 kV high-side metering needs CT 0.2S / PT 0.2 (V12); LDES connection must be confirmed against the local grid code (ramp / primary frequency / LVRT).

Pain Points → Solution → Evidence

Pain

Large-capacity connection demands high transformer reliability/redundancy

Solution

2×2000 kVA main transformers in N+1, nMinus1 passes

Evidence

nMinus1 verdict=pass · sdKva 1684 · 84% loading after one out

Pain

8 h long-duration battery is huge and capital-heavy

Solution

2000 kW × 8 h = 16 MWh (83 clusters · 768 V DC)

Evidence

capacitySummary storageHours=8; storageBattery 83 clusters

Pain

Large-transformer losses drive up long-run bills

Solution

SH15 amorphous main transformer saves 6,920 kWh/yr

Evidence

transformerTco.upgrade: 2.4 yr payback · $830/yr

Pain

Grid-code requirements (ramp / frequency / LVRT) unclear

Solution

35 kV high-side metering + IEC compliance + grid-code confirmation

Evidence

V12 metering requirement; toConfirm gridCodeNote pending

4 · Key Parameter Deep-Read

ParameterValueBasisImpact & Boundary
Main transformer2×2000 kVA (S13-M-2000/35)2000 kW / 0.95 ≈ 2105 kVA → N+1 dual 2000 kVA84% loading after one out, nMinus1 passes
Longer duration / higher power needs 2500/3150 kVA tier
PCS power2000 kWGrid-following high-power charge/dischargeShaving + frequency capability
PCS must match grid dispatch commands
Storage energy16063 kWh usable / 17848 kWh rated2000 kW × 8 h; DOD 0.98 h long-duration multi-day peaking
Flow / pumped / compressed-air technology caps the duration
Battery clusters83 × 215 kWh768 V DC · 240 series · 3.2 V cell · 280 AhLarge-scale cluster paralleling
Inter-cluster consistency / BMS balancing is the O&M focus
Short-circuit levelLV 36.54 kA · 50 kA breakingIEC 60909 · Ssc 500 MVA assumptionLV breaking 1.4× · HV 3×
Actual Ssc to confirm with grid company
Losses4,510,068 kWh/yr · $541,208/yrNo-load 1.12 kW + load 17.4 kW · 84% loadingLarge-transformer losses are material
SH15 amorphous pays back in 2.4 yr

5 · Drawing Deep-Read

Dwg 3/29Single-line diagram — 35 kV grid + 2000 kW PCS bidirectional → 16 MWh battery → 2×2000 kVA main transformers (N+1) → 35 kV bus
Why: The SLD answers how LDES connects at large capacity: a 2000 kW PCS + 16 MWh battery steps up to 35 kV through 2×2000 kVA transformers, with N+1 keeping supply continuous if one unit trips.
Dwg 4/29System topology — 35 kV grid (base) · BESS 2000 kW (variable, 100%) → 2× main transformers (N+1) → 35 kV bus
Why: The topology draws the energy hierarchy and redundancy: storage as variable at 100% share, dual N+1 transformers as the reliability core — the large-capacity locus of 8 h LDES.
Dwg 20/29Grid-tied / anti-islanding — PCC · anti-islanding · anti-backfeed
Why: Large LDES connection must meet the grid code: PCC opening and anti-islanding protection are configured per local rules — answering the "grid-code (ramp / frequency / LVRT)" pain.
Dwg 25/29Peak-shaving single-line — 2000 kW/16 MWh BESS via PCS to bus · shaving / frequency
Why: This lands the 8 h LDES as a dispatch branch: PCS charges at valley and discharges at peak, 2000 kW × 4 h shaving ≈$379,600/yr — the structural source of the economics.
Dwg 26/29Peak-shaving operation profile — 24 h profile · valley charge / peak discharge + 8 h support
Why: This turns the 8 h characteristic into a timeline: longer charge/discharge covers wider peak/valley windows, supporting multi-day peaking and reserve — the operational evidence.
Dwg 8/29Short-circuit calculation — LV fault 36.54 kA · 50 kA breaking check
Why: A large station has a high fault level (LV 36.54 kA); this verifies breaker breaking (50 kA) and cable thermal stability so the 2000 kW branch trips reliably.

The following drawings are shown for reference (full set in the configurator “View design document”):

Dwg 1 · Electrical design basisDwg 14 · Protection configurationDwg 15 · TCC coordination curveDwg 19 · Reactive & harmonic compensationDwg 12 · Power quality assessmentDwg 13 · SCADA architectureDwg 16 · Grounding systemDwg 17 · Lightning & surge protectionDwg 18 · Equipment layout planDwg 24 · DC auxiliary power systemDwg 27 · BMS communication architectureDwg 28 · Fire suppression & thermal zoningDwg 29 · EMS control state machineDwg 9 · Applicable codes & standardsDwg 10 · Main equipment technical data

6 · Operation Demo (Deep-Read)

Energy flow

At valley the 35 kV grid charges the 16 MWh battery through the main transformer and PCS rectification; at peak the battery discharges through PCS inversion → main transformer → 35 kV bus (2000 kW), with 8 h support covering wider peak/valley windows.

24h operation

A typical-day curve: long-duration charge/discharge covers wider windows, shaving 2000 kW × 4 h with 8 h supporting multi-day peaking and reserve — showing the LDES time-order effect.

Economics

2000 kW × 4 h × $0.13/kWh = ≈$379,600/yr; equipment $2,314,905, EPC $2,900,000; LDES adds multi-day peaking / frequency / reserve value on top.

LCC (life-cycle cost)

At 6% discount, S13 → SH15 amorphous saves 6,920 kWh/yr (≈$830), 2.4 yr payback — the large-transformer upgrade has the best cost-benefit.

Other views (shown): Power quality & harmonics · Voltage profile · Scheme features · Environmental derating

7 · Economics & Payback

Equipment total ≈ $2,314,905, EPC ≈ $2,900,000 (incl. BESS/main transformers/distribution). Peak shaving 2000 kW × 4 h × $0.13/kWh saves ≈$379,600/yr; losses cost $541,208/yr (large-transformer heavy), SH15 amorphous saves 6,920 kWh/yr ($830/yr, 2.4 yr payback). The engine's main economic model is PV-centric; use the shaving + frequency/reserve basis for LDES value (feasibility-level).

$2,314,905
Equipment total
$2,900,000
EPC investment
$379,600/yr
Shaving saving
$541,208
Annual losses
$830/yr (2.4 yr payback)
SH15 upgrade
8 h (16 MWh)
Storage duration
Key assumptions driving these numbers
$0.12/kWh
Electricity price
$0.06/kWh
Feed-in tariff
80%
Self-consumption
$0.13/kWh
Peak-valley spread

8 · FAQ

What main transformer for long-duration storage?
2×2000 kVA (S13-M-2000/35, N+1); 2000 kW / 0.95 ≈ 2105 kVA → dual 2000 kVA, 84% loading after one unit out (nMinus1 passes).
How is the 8 h battery configured?
2000 kW × 8 h = 16063 kWh usable (DOD 0.9 → 17848 kWh rated), 83 clusters × 215 kWh, 768 V DC.
Long-duration vs short-duration storage?
Long-duration (≥4 h; 8 h here) does multi-day peaking / frequency / reserve; short (2 h) does peak-valley arbitrage. Technologies include flow, pumped hydro and compressed air.
How much does it save?
2000 kW × 4 h × $0.13/kWh spread = ≈$379,600/yr (V24 check basis), plus frequency / reserve value.
Why use N+1 redundancy?
Large-capacity connection demands high reliability; N+1 makes nMinus1 pass — the remaining 2000 kVA covers 84% of load after one unit out.
What about high large-transformer losses?
Losses are 4,510,068 kWh/yr ($541,208/yr); the SH15 amorphous upgrade saves 6,920 kWh/yr and pays back in just 2.4 yr.
Is the 35 kV short-circuit capacity enough?
LV fault 36.54 kA, LV breaking 50 kA (1.4× margin) and HV 25 kA (3×), V19 passes.
What grid-code points to watch?
Confirm ramp rate, primary frequency response and LVRT against the local grid code; high-side metering CT 0.2S / PT 0.2.
When does it pay back?
EPC $2,900,000 with $379,600/yr shaving plus frequency/reserve revenue; the engine's main model is PV-centric, so indicative simple payback is ≈7.6 yr (confirm with real tariffs / ancillary-service prices).
How are harmonics handled?
2000 kW PCS rectifier THDi 20% exceeds the limit — detuned reactor + APF/SVG active filtering (V6).

Special Considerations

  • LDES connection must confirm ramp rate, primary frequency response and LVRT against the local grid code (toConfirm gridCodeNote).
  • Large-transformer losses are high ($541,208/yr); the SH15 amorphous upgrade has the best cost-benefit (2.4 yr payback).
  • 83 clusters in parallel — inter-cluster consistency and BMS balancing are the O&M focus (same for second-life / flow long-duration tech).
  • N+1 nMinus1 passes, but confirm the actual Ssc with the grid company (36.54 kA is based on the 500 MVA assumption).
  • Feasibility-level estimates; drawings are schematic, pending design-institute refinement.

Turn this into your project

Open this exact scenario pre-loaded in the Power System Configurator, then generate the full design document or the operation & techno-economic assessment.

Open in Power System Configurator →

One-Stop Supply of Conventional & Solar Power Equipment

From power distribution system design to solar energy — transformers, switchgear, substations and solar equipment, sized and quoted in one place. Use our calculators to get a complete bill of materials and FOB price.