QDTB® Transformer
All figures are configurator-generated feasibility-level estimates; drawings are schematic deliverables pending refinement by a licensed design institute, not construction documents.
All Solutions

400 kW Hospital Power: Dual Supply + N+1 Dry Transformer + 200 kVA UPS + 500 kVA Diesel

2× SCB13-400/10 N+1 · 500 kVA diesel · 200 kVA/15 min UPS · medical IT isolation

1 · TL;DR Conclusion

Conclusion: a 400 kW hospital uses 2×SCB13-400/10 dry transformers (N+1) + a 500 kVA standby diesel + a 200 kVA/15-min UPS — $200,667 equipment total. 10 kV dual supply with auto-transfer (2 s switch) + medical IT isolation keeps grade-1/critical loads alive at 84% transformer loading under N-1.

  • •N+1 redundancy: 2× SCB13-400/10 dry transformers — one outage still carries 84% of demand (N-1 verdict: pass).
  • •Dual supply: 10 kV grid + 500 kVA standby diesel — auto-transfer in 2 s < 15 s allowed outage.
  • •200 kVA online UPS (15 min / 40 kWh) rides through ms-level outages for 120 kW medical-IT / ICU loads.
  • •Medical IT isolation (ES710) + arc-flash protection (ARB6, Cat 1) + fire dedicated circuit with end-transfer ATS.
  • •Transformer TCO: upgrading to SH15 amorphous alloy saves ≈ $694/yr (payback ≈ 1.2 yr at 84% loading).

2 · Solution Overview

A hospital is the most demanding reliability load: operating rooms, ICU and life-support tolerate no interruption, so the whole facility is designed as grade-1 (400 kW), with 320 kW critical and 120 kW medical-IT sensitive load. The scheme stacks 10 kV dual supply + auto-transfer + diesel + UPS, plus medical IT isolation and equipotential grounding, meeting IEC 60364-7-710 for group-2 medical locations.

400 kW / 320 kW
Connected / demand load
2× SCB13-400/10 (N+1)
Dry transformers
500 kVA · 400 kW
Standby diesel genset
200 kVA · 15 min
Online UPS
10 kV dual supply + ATS
Supply topology
$200,667
Equipment total (feasibility-level)
SourceRoleShare kWShare
Grid 10 kVbase320 kW100%
Diesel 400 kWbackup0 kW0%
UPS 200 kVAbackup0 kW0%

3 · Design Process & Rationale

① Classify the load first (400 kW → grade-1 & critical)

Split 400 kW into lighting 60 kW, power 280 kW, sensitive 120 kW (medical IT / ICU), critical 320 kW, fire 60 kW. Per IEC 60364 the whole hospital is grade-1 (400 kW); the 320 kW critical load mandates an emergency source — the basis for dual supply + diesel + UPS.

② Dual supply + emergency-source mix

10 kV grid (base) + 500 kVA diesel (standby/backup) + 200 kVA UPS (backup). allowedOutage = 15 s drives diesel auto-transfer in 2 s; the 120 kW sensitive load needs ms-level, hence the 200 kVA online UPS.

③ N+1 transformer redundancy

Demand 320 kW / 0.9 PF ≈ 356 kVA → 2× SCB13-400/10 dry-type (N+1). Dry-type is chosen for indoor fire safety (no oil); N+1 keeps 84% loading after one unit trips.

④ LV distribution + bus-tie + transfer switches

MNS LV switchgear with incoming + bus-tie + feeder panels; ATS-630 (grid/diesel), STS-630 (UPS static transfer), GATS-630 (grade-1 end-transfer), FATS-630 (fire end-transfer).

⑤ Protection & selectivity

50/51 coordination (incoming 0.6 s → transformer 0.3 s), arc-flash ARB6 (Cat 1, 1.58 cal/cm²); LV short-circuit 14.15 kA → 25 kA breaking (1.8× margin).

⑥ Medical IT isolated system

The 120 kW medical-IT loads (OR, ICU) sit on an isolated power supply ES710 with insulation monitoring — first fault alarms but does not trip; a 20 kVA operating-room UPS is quoted per project.

⑦ Fire + grounding + reliability checks

Fire load 60 kW on a dedicated circuit with end-transfer ATS; TN-S equipotential grounding (18 rods); EPS 60 kW emergency lighting; N-1 verdict pass.

Pain Points → Solution → Evidence

Pain

Even a 15-second outage can interrupt surgery or a ventilator

Solution

10 kV dual supply + auto-transfer (2 s) + 200 kVA UPS (15 min ride-through)

Evidence

nMinus1 verdict pass, switchTimeS 2 s < allowedOutageS 15 s; upsBattery runtimeMin 15

Pain

A first earth fault tripping the medical-IT circuit would interrupt surgery

Solution

Medical IT isolated supply (ES710) with insulation monitoring — alarm on first fault, no trip

Evidence

BOM includes 'Medical IT isolated power supply ES710' + 'Medical IT isolation system'

Pain

A single transformer failure would black out the whole hospital

Solution

2× SCB13-400/10 N+1 — one unit out still serves 84% of demand

Evidence

nMinus1 loadingPctAfter 84%, verdict pass

4 · Key Parameter Deep-Read

ParameterValueBasisImpact & Boundary
totalKw (connected load)400 kWsum of all equipment rated powerdrives transformer / genset / UPS sizing
demand 320 kW at Kd 0.8
loadGrade1 / loadCritical400 / 320 kWIEC 60364 grade-1 = hospitalmandates dual supply + emergency diesel + UPS
grade-2/3 = 0 — everything is grade-1
allowedOutage15 s (s15)grade-1 supply requirementdiesel ATS in 2 s; sensitive load gets UPS
medical IT needs ms-level → UPS bridge
transformer redundancyN+1 (2× 400 kVA)SCB13 dry-type, indoor84% loading after N-1
single = 80% loading but no redundancy
loadSensitive (medical IT)120 kWOR + ICU + life-support200 kVA UPS + isolated supply ES710
scales linearly with OR count
largestMotorKw / start mode37 kW / softHVAC chiller / air-handlingsoft-start limits voltage dip
larger motors → VFD

5 · Drawing Deep-Read

Dwg 3/26Single-line diagram — 10 kV dual supply → 2× SCB13-400/10 → MNS LV (ATS/STS/GATS/FATS)
Why: Shows the full power path from 10 kV grid + diesel through N+1 transformers to the grade-1 / critical / fire buses — the core drawing of the scheme.
Dwg 14/26Protection configuration — 50/51 coordination + arc-flash ARB6 (Cat 1)
Why: The 0.6 s → 0.3 s stage coordination guarantees selectivity; ARB6 arc-flash protection (Cat 1, 1.58 cal/cm²) protects personnel and panels.
Dwg 20/26Grid-tied / islanding transfer — Grid–diesel auto-transfer (BZT) logic
Why: On grid loss the diesel auto-takes over within 2 s (< 15 s allowed) — the timing that makes dual supply reliable.
Dwg 16/26Grounding system — TN-S equipotential + medical IT isolated grounding
Why: Medical locations require equipotential bonding — TN-S + 18 rods keep micro potential differences in patient areas, preventing micro-shock.

The following drawings are shown for reference (full set in the configurator “View design document”):

Dwg 1 · Electrical design basisDwg 8 · Short-circuit calculationDwg 15 · TCC protection coordination curveDwg 24 · DC auxiliary power systemDwg 25 · Diesel fuel systemDwg 13 · SCADA architectureDwg 12 · Power quality assessmentDwg 17 · Lightning & surge protection

6 · Operation Demo (Deep-Read)

Reliability (N-1)

Click 'Grid failure': diesel takes over in 2 s, terminal voltage holds; N-1 scenario: one transformer out still 84% loading (verdict pass).

Power quality

Medical IT + UPS deliver clean supply to sensitive loads; THDi 15% on the LV side, online double-conversion UPS removes grid disturbance.

Fault & protection

14.15 kA LV short-circuit → 25 kA breaking (1.8× margin); arc-flash Cat 1 (1.58 cal/cm²); main protection 0.6 s.

Other views (shown): Load flow · Voltage · Losses · Fault & protection · Environment

7 · Economics & Payback

Equipment total $200,667 (feasibility-level). This is grid + diesel + UPS — no PV/storage, so the financial case is availability, not energy savings. Two quantifiable levers: transformer TCO (SH15 amorphous alloy saves ≈ $694/yr, payback 1.2 yr) and losses (3.8 kW ≈ $9,918/yr at $0.12/kWh).

$200,667
Equipment total
$9,918/yr
Annual transformer + line losses
$694/yr
SH15 upgrade annual saving
1.2 yr
SH15 upgrade payback

8 · FAQ

What transformer does a 400 kW hospital need?
2× SCB13-400/10 dry-type (N+1), 400 kVA each. Demand is 320 kW (Kd 0.8); a single 400 kVA unit carries 84% under N-1, the second is redundancy.
Why N+1 instead of a single 630 kVA?
A single 630 kVA runs lightly loaded but has no redundancy — a transformer fault blacks out the hospital. N+1 (two 400 kVA) keeps 84% loading after one unit trips, matching hospital reliability needs.
What UPS size for the operating room?
200 kVA / 160 kW online UPS with 15-min backup (40 kWh battery), covering the 120 kW medical-IT/ICU load; individual ORs add a 20 kVA online UPS (quoted per project).
How fast does the diesel take over after a mains outage?
The auto-transfer switch (BZT) switches within 2 s — well under the 15 s allowed for grade-1 load; sensitive medical loads ride through on the UPS during the transfer.
Is medical IT isolation mandatory?
Yes. IEC 60364-7-710 requires an IT system with insulation monitoring for group-2 medical locations (OR, ICU) — a first fault alarms without tripping, avoiding surgical interruption.
How is the fire load handled?
The 60 kW fire load sits on a dedicated circuit (fireDedicated=yes) with an end-transfer ATS (FATS-630), auto-switching to the emergency source on mains loss.
Dry-type or oil-immersed transformer for a hospital?
Dry-type (SCB13). Hospitals are indoor with strict fire safety — dry units are oil-free and non-flammable. The slightly higher no-load loss is offset by an amorphous-alloy (SH15) option.
What does this scheme cost?
About $200,667 equipment (feasibility-level), covering 2 dry transformers, 500 kVA diesel, 200 kVA UPS, MNS LV switchgear, medical IT isolation and secondary monitoring — 42 items.
How do I cut the transformer energy bill?
Upgrade to SH15 amorphous alloy: no-load loss drops from 0.98 kW to 0.1 kW, saving ≈ $694/yr (84% loading) with a ≈ 1.2-year payback.

Special Considerations

  • Medical IT isolation (ES710) and operating-room UPS are 'price on application' (poa) — excluded from the total, quote separately.
  • The 500 kVA diesel carries 400 kW grade-1 at ≈ 100% loading — verify the load profile and reserve expansion margin.
  • Ssc (grid short-circuit 500 MVA) is assumed — confirm actual fault level with the utility for final protection & cable settings.
  • Arc-flash Cat 1 (1.58 cal/cm²) is preliminary — a formal IEEE 1584 study by a qualified engineer is required before permits.
  • Drawings are schematic deliverables pending design-institute refinement; all figures are feasibility-level estimates.

Turn this into your project

Open this exact scenario pre-loaded in the Power System Configurator, then generate the full design document or the operation & techno-economic assessment.

Open in Power System Configurator →

One-Stop Supply of Conventional & Solar Power Equipment

From power distribution system design to solar energy — transformers, switchgear, substations and solar equipment, sized and quoted in one place. Use our calculators to get a complete bill of materials and FOB price.