QDTB® Transformer
All figures are configurator-generated feasibility-level estimates; drawings are schematic deliverables pending refinement by a licensed design institute, not construction documents.
All Solutions

500 kW Biomass Power: Rotating Genset + Step-up Transformer + House Load Deep-Read

500 kW synchronous genset (1000 kVA frame) · S13-M-500/10 step-up · 80 kW house load · grid-tied

1 · TL;DR Conclusion

Conclusion: this 500 kW biomass plant uses a 500 kW synchronous rotating genset (1000 kVA frame, prime duty) + S13-M-500/10 step-up transformer (0.4/10 kV) + 80 kW house load + 10 kV grid-tie — configurator total ≈ $170,226. The genset carries 100% of the 400 kW site load; the single step-up transformer has no N-1 (single-unit station) (feasibility-level).

  • •500 kW synchronous genset (1000 kVA frame, prime) carries 100% of the 400 kW site load at 63%
  • •S13-M-500/10 step-up transformer (500 kVA oil) 0.4/10 kV at 84% loading
  • •80 kW house load (fuel feed, ID/FD fans, feedwater, cooling); single transformer, no N-1
  • •10 kV grid-tie, 500 kW backup (V9 pass), grid-sync protection
  • •78,702 kWh/yr losses ($11,640); SH15 upgrade saves $284/yr, 3.4-yr payback

2 · Solution Overview

A biomass station is the classic rotating-genset + step-up-transformer + house-load architecture: the synchronous generator generates onto the 0.4 kV bus, house load taps the bus directly, and the surplus is exported through the step-up transformer to the 10 kV grid. Reliability hinges on grid synchronization and house-load self-sustainment.

500 kW synchronous (1000 kVA frame)
Genset
S13-M-500/10 (500 kVA)
Step-up transformer
80 kW
House load
10 kV
Grid tie
400 kW
Demand
500 kW (V9 pass)
Backup
$170,226
Total
SourceRoleShare kWShare
Grid 10 kVbase0 kW0%
Diesel 500 kWbase400 kW100%

3 · Design Process & Rationale

1. Requirement identification

A 500 kW biomass station = rotating synchronous generator + house load (fuel feed, ID/FD fans, feedwater, cooling ≈ 80 kW). Core needs: stable grid connection + house-load self-sustainment.

2. Source architecture

The genset is the base source (prime duty) carrying 100% of site load; the 10 kV grid is the tie/backup (shareKw=0). The synchronous machine generates onto the 0.4 kV bus.

3. Step-up transformer sizing

400 kW ÷ 0.8 PF ≈ 500 kVA → S13-M-500/10 oil step-up (0.4/10 kV), 84% loading in the economical band.

4. House-load bus

0.4 kV bus (GCK-1000) feeds the 80 kW house load + genset output directly, 8 feeders, largest motor 55 kW soft-start.

5. Grid tie & protection

Synchronizing + anti-islanding/reverse-power protection to separate the genset on grid faults; single step-up transformer has no N-1 (single-unit station), 500 kW backup covers house load.

6. Secondary & monitoring

61850 comms + SCADA monitor genset grid status, house-load power quality and step-up temperature for stable operation.

Pain Points → Solution → Evidence

Pain

Generator sync failure / loss of step hammers the set

Solution

Synchronizer + reverse-power/out-of-step protection + 61850 fast comms

Evidence

grid-tied mode, genset base carries 100% load, selectivity 6.8× satisfied (V3)

Pain

House-load outage risks boiler/feed shutdown

Solution

0.4 kV bus taps house load directly + 500 kW backup

Evidence

V9: backup 500 kW ≥ grade-1 + fire load — pass

Pain

Single step-up transformer means any fault kills the plant

Solution

State the single-unit boundary + backup + spare fast repair

Evidence

N-1 = single (no N-1), gap 400 kW — must be covered by backup/spare

Pain

Harmonics and VAR exceed limits, failing grid compliance

Solution

Detuned reactors + capacitor compensation; APF if needed

Evidence

V6 flags THDi over the limit (renewable-hybrid scene) — APF/SVG recommended

4 · Key Parameter Deep-Read

ParameterValueBasisImpact & Boundary
Genset500 kW synchronous (1000 kVA frame)500 kW biomass prime mover → synchronous generator, prime duty63% load on a 1000 kVA frame reserves expansion and transient margin
625 kVA real need at 0.8 PF; frame reserve helps black-start/impact
Step-up transformerS13-M-500/10 (500 kVA)400 kW ÷ 0.8 PF ≈ 500 kVA0.4/10 kV step-up grid-tie at 84% loading
Single unit, no N-1; expansion needs 630/800 kVA
House load80 kWFuel feed, ID/FD fans, feedwater, cooling auxiliariesTapped directly from the 0.4 kV bus for self-sustainment
Largest motor 55 kW soft-start, 1.74% drop (pass)
Grid tie10 kV grid-tiedSurplus exported via step-up transformer to 10 kVGenset base carries 100% of site load
Needs synchronizer + anti-islanding/reverse-power + grid approval
Backup500 kW (V9 pass)Grid/backup covers house loadHouse load stays up during genset service or fault
Needs ATS auto-transfer (ATS-630 included)
Annual losses78,702 kWh ($11,640)84% loading + line lossSH15 amorphous upgrade saves $284/yr
3.4-yr payback (V25)

5 · Drawing Deep-Read

Dwg 3/26Single-line diagram — Synchronous genset → 0.4 kV bus → 80 kW house load + S13-M-500/10 step-up → 10 kV grid
Why: The SLD shows the generate-distribute-export chain: the genset generates onto the 0.4 kV bus, house load taps directly, and the surplus exports through the step-up transformer — the plant's electrical skeleton.
Dwg 4/26System topology — Genset base · grid backup · step-up transformer · house-load bus
Why: The topology visualizes source layers — genset (base), grid (backup), step-up transformer, house load — the locus of the twin goal of grid-tie plus self-sustainment.
Dwg 25/26Fuel oil system — Biomass fuel storage · day tank + storage tank · ~9000 L / 72 h reserve
Why: Continuous biomass operation depends on fuel supply; the fuel drawing gives the day-tank + storage boundary (~9000 L for 72 h autonomy) — the physical guarantee of plant availability.
Dwg 14/26Protection configuration — Sync + reverse-power/out-of-step · 0.3/0.2 s grading
Why: A grid-tied plant fears loss of step and reverse power: the synchronizer plus reverse-power/out-of-step protection quickly separate the genset on grid faults — the second line of grid-safety defense.
Dwg 15/26TCC protection coordination curve — Incomer → step-up → LV incomer → feeder · 6.8× selectivity pass
Why: TCC verifies selectivity: a house-load feeder fault trips only that circuit while upstream 0.3 s holds, with 6.8× ensuring grading so one fault never blacks out the station.

The following drawings are shown for reference (full set in the configurator “View design document”):

Dwg 1 · Electrical design basisDwg 2 · Symbol legendDwg 5 · Distribution systemDwg 6 · MV distribution systemDwg 7 · LV distribution systemDwg 8 · Short-circuit calculationDwg 9 · Applicable codes & standardsDwg 10 · Main equipment technical dataDwg 11 · Construction & testing requirementsDwg 12 · Power quality assessmentDwg 13 · SCADA architectureDwg 16 · Grounding systemDwg 17 · Lightning & surge protection (LPS/SPD)Dwg 18 · Equipment layout planDwg 19 · Reactive & harmonic compensationDwg 20 · Microgrid grid-tied / islanding transferDwg 21 · Secondary control & signal circuitDwg 22 · Terminal strip (protection & control panels)Dwg 23 · Panel front layout & panel scheduleDwg 24 · DC auxiliary power systemDwg 26 · Earthing system (TN-S)

6 · Operation Demo (Deep-Read)

Energy flow

Synchronous genset → 0.4 kV bus (400 kW load, 100% genset-fed) → 80 kW house load + step-up export; system loss 8.98 kW (2.25%), line 4.96 kW + transformer 4.02 kW.

Grid tie & protection

Rehearses genset synchronization, reverse-power/out-of-step separation on grid faults, and house-load coverage by backup — the grid-tie and self-sustainment chains in full.

Reliability

Single step-up transformer has no N-1 (gap 400 kW on loss); the 500 kW backup via ATS covers house load — the key single-unit-station reliability criterion.

Loss & cost

78,702 kWh/yr ($11,640); SH15 amorphous upgrade saves $284/yr with 3.4-yr payback (V25).

Other views (shown): LCC (life-cycle cost) · Power quality & harmonics · Voltage profile · Scheme features

7 · Economics & Payback

Equipment total ≈ $170,226: genset $80,500, step-up transformer $8,604, fuel system $6,210, EMS $4,025, ATS $3,335. No PV/BESS so no generation payback model; economics rest on operation: $11,640/yr losses, SH15 upgrade saves $284/yr with 3.4-yr payback, and the ~9000 L / 72 h fuel reserve is the continuous-run cashflow item.

$170,226
Equipment total
$80,500
Genset
$8,604
Step-up transformer
$11,640
Annual loss cost
3.4 yr
SH15 payback
72 h (~9000 L)
Fuel autonomy

8 · FAQ

What generator size for a 500 kW biomass plant?
500 kW synchronous rotating genset, prime duty, on a 1000 kVA frame (625 kVA real at 0.8 PF), 63% load, reserving transient and expansion margin.
How big is the step-up transformer?
400 kW ÷ 0.8 = 500 kVA → S13-M-500/10 oil step-up (0.4/10 kV) at 84% loading.
How much house load, and how is it fed?
≈ 80 kW (fuel feed, ID/FD fans, feedwater, cooling), tapped directly from the 0.4 kV bus for self-sustainment, largest motor 55 kW soft-start.
How is it grid-tied?
The genset generates onto the 0.4 kV bus; surplus exports through the step-up transformer to 10 kV, needing a synchronizer plus anti-islanding/reverse-power protection.
Does house load drop when the genset faults?
No — the 500 kW backup (V9 pass) covers house load via ATS auto-transfer during genset service or fault.
Only one step-up transformer — what if it fails?
Single, no N-1, so a fault drops the plant (gap 400 kW); add backup or a spare to cut downtime — an inherent single-unit-station boundary.
How much does the scheme cost?
≈ $170,226: genset $80,500, step-up transformer $8,604, fuel system $6,210, EMS $4,025, ATS $3,335.
Are operating losses high?
78,702 kWh/yr ($11,640); the SH15 amorphous upgrade saves $284/yr with 3.4-yr payback.
Do I need harmonic treatment?
V6 flags THDi over the limit (scene default); with few VFD auxiliaries it's usually mild — detuned reactors + caps, and an APF if needed.

Special Considerations

  • The configurator models the biomass synchronous generator as a prime-duty rotating genset (1000 kVA frame, 625 kVA real at 0.8 PF) — the biomass prime-mover governor and excitation must be coordinated with the generator OEM.
  • The step-up transformer is single (no N-1); a fault drops the plant (gap 400 kW). Add backup (500 kW here) or a spare transformer to cut repair downtime.
  • V6 flags THDi over the limit (renewable-hybrid scene default); with few VFD/soft-start auxiliaries this is usually mild — add detuned reactors, and an APF if needed.
  • Grid tie needs grid approval + synchronizer + anti-islanding/reverse-power protection; LV fault 17.6 kA → 25 kA breaking.
  • Feasibility-level estimate; drawings pending a licensed design institute; fuel system estimated for 72 h autonomy (~9000 L).

Turn this into your project

Open this exact scenario pre-loaded in the Power System Configurator, then generate the full design document or the operation & techno-economic assessment.

Open in Power System Configurator →

One-Stop Supply of Conventional & Solar Power Equipment

From power distribution system design to solar energy — transformers, switchgear, substations and solar equipment, sized and quoted in one place. Use our calculators to get a complete bill of materials and FOB price.