QDTB® Transformer

Micro-Hydro Power Station Calculator

Enter head and design flow to select the turbine type (impulse / Francis / Kaplan), generator, step-up substation and get annual generation, LCOE and a complete BOM.

Start Calculating Calculators

How a micro-hydro station is sized

Hydro output is P = ρ·g·Q·H·η. The head decides the turbine type — impulse (Pelton) above 200 m, Francis from 30–200 m, Kaplan/propeller below 30 m. The calculator sizes the generator, the 0.4→10.5 kV (or 35 kV) step-up station, and estimates annual energy by the capacity-factor method.

1.6 MW Francis Hydro Station (10 kV grid)

Example 1 — 1.6 MW Francis Hydro Station (10 kV grid)
Small hydro station · Francis
1570 kW
H 80 m · Q 2.5 m³/s · η 80% · 2000 kW generator
Annual energy
6,875 MWh
LCOE
$16.7/MWh
Est. BOM (FOB)
POA
📦 Bill of Materials
EquipmentModelSpecQty
Hydro turbine-generator set1570 kWFrancis · H 80 m · Q 2.5 m³/s · η 80% · incl. governor + excitation · purchased equipment (外购件)1
Step-up transformer2222 kVA0.4/10 kV · oil-immersed (GB/T 17467) · >1600 kVA outside catalogue1
Ring main unit (RMU)10 kVSF6 RMU 630 A · 4-circuit · 10 kV1
LV switchgear (GGD)0.4 kVincoming breaker + feeders · complete cubicle1
Protection & control (secondary)relaymicroprocessor protection 50/51/51N + metering + SCADA interface1
Penstock & forebay (intake)H 80 mpenstock + intake forebay + trashrack · civil/steel (引水系统)1
Intake gate & hoistgateintake gate + hoist (闸门与启闭机) · manually / motor operated1
Butterfly / gate valveDN632penstock isolating valve (闸阀/蝴蝶阀) · DN sized to Q1
Tailrace channelciviltailrace / draft tube discharge (尾水渠) · site civil works1
Power cablesLV/MVgenerator leads + HV feeder cable (2 km step-up distance) · split run1
Control & instrument cablescontrolgovernor/excitation/SCADA control cabling (控制电缆分段)1
Earthing & lightning protectiongroundingstation grounding grid + lightning rods + SPD coordination1
Station auxiliary supplyauxauxiliary power, DC system, lighting, fire alarm1
Summary
Estimated total (FOB Qingdao, EXW) — priced equipmentPOA
📐 Single-line diagram (circuit-level)
MODULAR SINGLE-LINE DIAGRAM10 kV / 0.4 kV · 3-phase · 2222 kVA · single-source · schematicHYDROHYDRO 2000 kW10 kV MV BUS(integrated MV unit in substation)TRANSFORMER2222 kVA0.4 kV LV BUSLV SWG (GGD)0.4 kV incoming + feedersLV feeder 1 · 401 ALV feeder 2 · 401 ALV feeder 3 · 401 ALV feeder 4 · 401 ALV feeder 5 · 401 ALV feeder 6 · 401 ALV feeder 7 · 401 ALV feeder 8 · 401 ALEGENDQFcircuit breakerCTcurrent transformerTtransformerSPDsurge arresterPFCpower-factor correctionDESIGN DATAincoming 10 kVbus 0.4 kVLV switchgear 0.4 kV inco...no PFCfeeders 8SECONDARYBASIC · MODBUSSPECIALscadaSchematic / feasibility-level design construction drawings by a licensed design institute.
⚙️ Hydro station system schematic (intake → turbine → generator → step-up → grid)
HYDRO STATION SYSTEM SCHEMATICintake -> turbine -> generator -> step-up -> grid (full chain, schematic)Intake / PenstockH = 80 mTurbineFrancis - 2.5 m3/sGenerator2000 kW - 0.4 kV2000/5A52G0.4 kV generator busSPDStep-up transformer2222 kVA - 0.4/10 kV87T49Tdifferential + thermalGrid10 kV connection
LEGENDBreaker (52)DisconnectorCT (current transformer)PT (voltage transformer)50/51Protection relay 50/51/51NkWhMeter (kWh)SPD (surge protection)Transformer
🛡 Step-up substation main connection (protection configuration)
PROTECTION CONFIGURATION10 kV / 0.4 kV · 2222 kVA · protection zones (schematic)INCOMING 10 kVCT 200/5A505151Novercurrent / earth-faultQFTRANSFORMER2222 kVA · Z=6%8749CT 3000/5A505151NLV incoming protectionQF0.4 kV LV BUSCT .../5A50/5151NLV feeder 1401 ACT .../5A50/5151NLV feeder 2401 ACT .../5A50/5151NLV feeder 3401 ACT .../5A50/5151NLV feeder 4401 ACT .../5A50/5151NLV feeder 5401 ACT .../5A50/5151NLV feeder 6401 ACT .../5A50/5151NLV feeder 7401 ACT .../5A50/5151NLV feeder 8401 AProtection layout & CT ratios are schematic / illustrative final settings per IEC 60255 / IEEE 242.
⛰ Intake & penstock profile (forebay → trashrack → penstock → turbine → tailrace)
INTAKE & PENSTOCK PROFILE (LONGITUDINAL SECTION)forebay -> trashrack -> penstock -> turbine -> tailrace (elevation schematic)H0gross head H = 80 mnetFOREBAYupstream reservoirwater leveltrashrackpenstockDN791 x 10 mmflow ->TURBINEFrancisTAILRACEdownstream channeltailwater levelPENSTOCK DATAGross head H80 mPenstock DNDN791Wall thickness10 mmPenstock length~100 mFriction loss~4% of HSYMBOLS:forebay (upstream) - trashrack (bars) - penstock (thick line) - turbine - tailrace (downstream)Net head = gross head - friction loss ~= 76.8 m (illustrative confirm with hydraulic study & site profile).
🏭 Powerhouse floor plan (unit bay / governor / control panel / step-up / tailrace)
POWERHOUSE FLOOR PLAN (GENERAL ARRANGEMENT)unit bay / governor / control panel / step-up yard / tailrace schematic, not to scalePOWERHOUSE BUILDING (plan view)TURBINE + GENERATORunit 2000 kWrunner + shaftGOVERNORoil-hydraulicCONTROL PANELprotection + SCADASTEP-UP TX2222 kVATAILRACEdraft tube -> channeldraft tubeservice aislebuilding length (indicative, per unit arrangement)LAYOUT NOTESTurbine bay sits above the tailrace; governor and control panel face the unit for short cable runs.Step-up transformer is placed outdoor adjacent to the powerhouse; clearance per IEC 61936-1 (indicative).General arrangement is schematic / indicative construction drawings by a licensed design institute.
🛡 Generator & line protection + metering (CT/PT positions)
GENERATOR & LINE PROTECTION + METERINGunit differential / overcurrent / overvoltage + line protection + CT/PT metering points (schematic)GENERATOR2000 kW / 2222 kVAGCT 87G87Gdifferential51G51N5927overcurrent / earth / overvolt / undervoltkWhgenerator metering0.4kV/100VPT (voltage)52G0.4 kV generator busSTEP-UP 2222 kVA87T49Tdiff + thermal200/5Aline CT10kV/100Vbus PT52HV505151N27/59line protection (overcurrent / earth / volt)kWhrevenue metering (POI)GRID10 kVSPDProtection zones & CT/PT positions are schematic / illustrative final settings per IEC 60255 / IEEE 242.
LEGENDBreaker (52)CT (current transformer)PT (voltage transformer)87Protection relay (87/50/51/51N/59/27)kWhMeter (kWh)SPD (surge protection)Earthing
📊 Hydraulic energy calculation (P = ρ·g·Q·H·η)
ParameterValue
Design head H80 m
Design flow Q2.5 m³/s
Turbine efficiency η80%
Output P = 9.81 × Q × H × η1570 kW
Dry-season output (40% flow)628 kW
Wet-season output (130% flow)2000 kW (capped by generator)
🎛 Turbine & generator selection (H/Q criteria)
ParameterValue
Head band80 m → Francis
Selection ruleImpulse >200 m · Francis 30–200 m · Kaplan <30 m
Series factor×1 (francis)
Generator (standard)2000 kW (2222 kVA @ pf 0.9)
Generator efficiency95%
🏭 Step-up substation scheme
ParameterValue
LV side0.4 kV generator bus → GGD incoming
Step-up2222 kVA · 0.4/10 kV (GB/T 17467)
HV switchgearRing main unit (RMU) · SF6 RMU 630 A · 4-circuit · 10 kV
Interconnectionlocal 10 kV connection
📈 Annual generation & capacity factor
ParameterValue
Capacity factor (CF)50% (adjustable 20–70%)
Annual energy6,875 MWh/yr
Full-load hours4380 h/yr
LCOE (illustrative)$16.7/MWh
💧 Seasonal output range (dry / wet)
ParameterValue
Dry season (40% Q)628 kW
Wet season (130% Q)2000 kW
Generator rating cap2000 kW
Firm design basisuse site flow-duration curve (hydrology study)
🔧 Operation & maintenance essentials
ParameterValue
Runner / casinginspect for cavitation & erosion
Governor & excitationperiodic calibration
Bearings / sealslubrication & leak checks
Trashrackregular cleaning (debris)
Transformer oilDGA sampling per GB/T 7252
Service interval≈2 000–4 000 running hours (Francis)
📏 Standard basis (依据标准)
TopicStandard
Turbine model testIEC 60193 — hydraulic turbines (model acceptance tests)
Field acceptanceIEC 60041 — field acceptance tests for hydraulic machines
Hydro-generatorGB/T 15468 — fundamental technical specifications for hydro-generators
Step-up transformerGB/T 1094 — power transformers
🧮 How it was calculated
1. Output P = ρ·g·Q·H·η = 9.81 × 2.5 × 80 × 0.80 = 1570 kW
2. Turbine type: H = 80 m → Francis (impulse >200 m · Francis 30–200 m · Kaplan <30 m)
3. Generator: 1570 kW ÷ 0.95 → standard 2000 kW (2222 kVA @ pf 0.9)
4. Step-up: 0.4 kV → 10 kV
5. Annual energy = 1570 kW × 8760 h × CF 0.50 = 6,875 MWh/yr
6. Seasonal output: dry season 628 kW (40% flow) ~ wet season 2000 kW (130% flow)
7. LCOE = (CAPEX×CRF + OPEX) ÷ energy = $16.7/MWh (illustrative, turnkey factor 1.6)
📋 Design notes
Pricing basis: Turbine-generator set priced per-kW from the hydro-turbine-sets reference (FOB Qingdao, complete unit incl. governor + excitation; draft, pending final review). Step-up transformer uses the box-type-substations catalogue (≤1600 kVA); larger and 35 kV switchgear are quoted per project (POA).
Intake & civil works: Penstock/forebay, intake gate, butterfly valve, tailrace and station auxiliary works are civil/mechanical scope quoted per project (POA) — they depend strongly on site head, geology and intake layout.
Capacity factor: Annual generation uses the capacity-factor method (default 50%, adjustable 20–70%). Actual hydro output depends on seasonal flow duration curves and must be verified with site hydrology.
Seasonal output: Indicative dry-season output ≈628 kW (40% design flow) and wet-season output ≈2000 kW (130% flow, capped by generator rating). Use the flow-duration curve for a firm design.
LCOE basis (illustrative): Full-cost LCOE annuitizes CAPEX over 30 years at 7% and adds 2%/yr OPEX. The turnkey factor 1.6 covers civil works (intake, penstock, powerhouse), installation and commissioning — actual costs vary widely by site.
Off-grid mode: Grid-connected mode sells all generation to the grid.
Operation & maintenance: Routine O&M: runner/casing inspection, governor calibration, bearing & seal maintenance, trashrack cleaning and transformer oil sampling. Service interval typically 2 000–4 000 running hours for a Francis unit.
Design review: This is a preliminary sizing. A licensed hydro engineer must verify the turbine selection, penstock head-loss, cavitation margins and generator protection before procurement.

How it was calculated

Core formulas

P = 9.81 × Q × H × η (kW). Annual energy = P × 8760 × capacity factor. LCOE = (CAPEX × CRF + OPEX) ÷ annual energy (full-cost, illustrative).

Applicable standards

IEC 60193 (turbine model tests), IEC 60041 (field acceptance), GB/T 15468 (hydro-generators), GB/T 1094 (power transformers).

Frequently asked questions

What turbine type does my head need?

Head above 200 m suits an impulse (Pelton) turbine; 30–200 m a Francis turbine; below 30 m a Kaplan or fixed-blade propeller turbine. The calculator selects the type automatically from your head.

How is annual generation estimated?

By the capacity-factor method: rated output × 8760 hours × capacity factor (default 50%, adjustable 20–70%). Actual output depends on the seasonal flow-duration curve of the site.

Which equipment is priced in the BOM?

The turbine-generator set (per-kW reference), step-up transformer, ring main unit / HV switchgear and LV switchgear. Protection & secondary and, in off-grid mode, the diesel backup and battery, complete the list — larger transformers and 35 kV switchgear are quoted per project.

What is LCOE here?

Levelised cost of energy: annualised CAPEX (30 years at 7%) plus OPEX, divided by annual generation. It is illustrative — a turnkey factor 1.6 covers civil works (intake, penstock, powerhouse).

Embed this calculator

Copy the iframe code below to embed this calculator on any site. The embed page is noindex and fits any width.

Related calculators

Results are engineering estimates for reference. Final design must be confirmed by a licensed local engineer against site conditions and applicable codes. Prices are FOB Qingdao (EXW) and do not include freight, duty or installation.

Send my complete design report

Get the full bill of materials, single-line diagram, calculation steps and FOB pricing as a PDF — free, no sign-up.

💬 Chat on WhatsApp

Your data stays private. No spam — only a reply to your enquiry.