QDTB® Transformer

Micro-Hydro Power Station Calculator

Enter head and design flow to select the turbine type (impulse / Francis / Kaplan), generator, step-up substation and get annual generation, LCOE and a complete BOM.

Start Calculating Calculators

How a micro-hydro station is sized

Hydro output is P = ρ·g·Q·H·η. The head decides the turbine type — impulse (Pelton) above 200 m, Francis from 30–200 m, Kaplan/propeller below 30 m. The calculator sizes the generator, the 0.4→10.5 kV (or 35 kV) step-up station, and estimates annual energy by the capacity-factor method.

Worked Example — Micro-Hydro Station

Example 1 — 1.6 MW Francis Hydro Station (10 kV grid)
Small hydro station · Francis
1570 kW
H 80 m · Q 2.5 m³/s · η 80% · 2000 kW generator
Annual energy
6,875 MWh
LCOE
$16.7/MWh
Est. BOM (FOB)
POA
📦 Bill of Materials
EquipmentModelSpecQty
Hydro turbine-generator set1570 kWFrancis · H 80 m · Q 2.5 m³/s · η 80% · incl. governor + excitation · purchased equipment (外购件)1
Step-up transformer2222 kVA0.4/10 kV · oil-immersed (GB/T 17467) · >1600 kVA outside catalogue1
Ring main unit (RMU)10 kVSF6 RMU 630 A · 4-circuit · 10 kV1
LV switchgear (GGD)0.4 kVincoming breaker + feeders · complete cubicle1
Protection & control (secondary)relaymicroprocessor protection 50/51/51N + metering + SCADA interface1
Summary
Estimated total (FOB Qingdao, EXW) — priced equipmentPOA
📐 Single-line diagram
Intake / PenstockH = 80 mTurbineFrancis - 2.5 m3/sGenerator2000 kW - 0.4 kVGrid10 kV connection
LEGENDBreaker (52)CTCT (current transformer)PTPT (voltage transformer)50/51Protection relay 50/51/51NkWhMeter (kWh)SPD (surge protection)
📏 Standard basis
TopicStandard
Turbine model testIEC 60193 — hydraulic turbines (model acceptance tests)
Field acceptanceIEC 60041 — field acceptance tests for hydraulic machines
Hydro-generatorGB/T 15468 — fundamental technical specifications for hydro-generators
Step-up transformerGB/T 1094 — power transformers
🧮 How it was calculated
1. Output P = ρ·g·Q·H·η = 9.81 × 2.5 × 80 × 0.80 = 1570 kW
2. Turbine type: H = 80 m → Francis (impulse >200 m · Francis 30–200 m · Kaplan <30 m)
3. Generator: 1570 kW ÷ 0.95 → standard 2000 kW (2222 kVA @ pf 0.9)
4. Step-up: 0.4 kV → 10 kV
5. Annual energy = 1570 kW × 8760 h × CF 0.50 = 6,875 MWh/yr
6. LCOE = (CAPEX×CRF + OPEX) ÷ energy = $16.7/MWh (illustrative, turnkey factor 1.6)
📋 Design notes
Pricing basis: Turbine-generator set priced per-kW from the hydro-turbine-sets reference (FOB Qingdao, complete unit incl. governor + excitation; draft, pending final review). Step-up transformer uses the box-type-substations catalogue (≤1600 kVA); larger and 35 kV switchgear are quoted per project (POA).
Capacity factor: Annual generation uses the capacity-factor method (default 50%, adjustable 20–70%). Actual hydro output depends on seasonal flow duration curves and must be verified with site hydrology.
LCOE basis (illustrative): Full-cost LCOE annuitizes CAPEX over 30 years at 7% and adds 2%/yr OPEX. The turnkey factor 1.6 covers civil works (intake, penstock, powerhouse), installation and commissioning — actual costs vary widely by site.
Off-grid mode: Grid-connected mode sells all generation to the grid.
Design review: This is a preliminary sizing. A licensed hydro engineer must verify the turbine selection, penstock head-loss, cavitation margins and generator protection before procurement.

How it was calculated

Core formulas

P = 9.81 × Q × H × η (kW). Annual energy = P × 8760 × capacity factor. LCOE = (CAPEX × CRF + OPEX) ÷ annual energy (full-cost, illustrative).

Applicable standards

IEC 60193 (turbine model tests), IEC 60041 (field acceptance), GB/T 15468 (hydro-generators), GB/T 1094 (power transformers).

Frequently asked questions

What turbine type does my head need?

Head above 200 m suits an impulse (Pelton) turbine; 30–200 m a Francis turbine; below 30 m a Kaplan or fixed-blade propeller turbine. The calculator selects the type automatically from your head.

How is annual generation estimated?

By the capacity-factor method: rated output × 8760 hours × capacity factor (default 50%, adjustable 20–70%). Actual output depends on the seasonal flow-duration curve of the site.

Which equipment is priced in the BOM?

The turbine-generator set (per-kW reference), step-up transformer, ring main unit / HV switchgear and LV switchgear. Protection & secondary and, in off-grid mode, the diesel backup and battery, complete the list — larger transformers and 35 kV switchgear are quoted per project.

What is LCOE here?

Levelised cost of energy: annualised CAPEX (30 years at 7%) plus OPEX, divided by annual generation. It is illustrative — a turnkey factor 1.6 covers civil works (intake, penstock, powerhouse).

Embed this calculator

Copy the iframe code below to embed this calculator on any site. The embed page is noindex and fits any width.

Related calculators

Results are engineering estimates for reference. Final design must be confirmed by a licensed local engineer against site conditions and applicable codes. Prices are FOB Qingdao (EXW) and do not include freight, duty or installation.

Send my complete design report

Get the full bill of materials, single-line diagram, calculation steps and FOB pricing as a PDF — free, no sign-up.

💬 Chat on WhatsApp

Your data stays private. No spam — only a reply to your enquiry.